Update to run plan Fri. 6 December 19:00 Fri. Dec. 6 through Sat. Dec. 7 13:00 Continue run with straight beampipe, OTR viewer as target. When beam stabilizes, test all detector currents and rates vs. beam current (start with 100 nA), target in/out. Sat. Dec. 7 13:00(firm)-16:00(approx) Scheduled hall access to work on data acquisition hardware. after access completed: Restore beam to Faraday cup ~50 nA Tune beam to tagger dump ~50 nA Measure tagger counter rates with no radiator Measure tagger counter rates with OTR viewer as radiator (10**-5 R.L.) IN PARALLEL: Work on CLAS data acquisition (beam on target not required) Sun. Dec. 8 08:00 or after completion or tagger checkout Restore beam to Faraday cup Test CLAS data acquisition with electron beam on target Mon. Dec. 9 06:00 Beam off, radiation control in hall 07:00 Mini-torus and scattering chamber ready for move 07:00-16:00 (approx) Install scattering chamber and mini-torus 16:00 (approx) Begin pumpdown Evening and night: Start with beam steered to tagger dump to allow tuneup without hitting small mini-torus aperture. When good beam tune, restore beam to Faraday cup and begin testing with target ladder and mini-torus Stay tuned for further surprises.