Update to run program Monday, 9 December 1996 09:00 There has been no beam since Saturday afternoon, because of sequence of accelerator problems. Currently there is a defective arc magnet in the 4th pass, and the magnet is being removed. It is planned to restore operation Monday night with 3-pass beam (2.4 GeV) to Hall C and 1-pass beam (845 MeV) to Hall B -- the 2nd-pass separator is not operational. We will do the best we can with this. The installation of scattering chamber and mini-torus is taking place as planned, as per the December 6 update. Day and evening run shifts for Monday December 9 are cancelled. The shift schedule will resume at 00:00 December 10.