Revised Commissioning Schedule Revision -- 14 April 1997 Dates Particle/Energy Target Days Equipment May 15-23 e 1.6/4.0 none 9 Beam line devices (No CLAS) RadPhi tests Photofission tests Jun 4-9 e 2.4/4.0 LH2 6 6 sectors DC,EC,TOF(Panel 1-3) 2 sectors LAEC 3 sector CC DAQ: all crates, ATM Trigger: Level 1, 2 (partial) Jun 12-23 e 1.6/4.0 LH2 12 Jun 26-29 e 4.0 LH2 4 Jul 17-28 gamma 1.6/4.0 LH2 12 Start counter Complete photon commissioning and run Exp. g5 EITHER Jul 31-3 gamma 1.6/4.0 4 Experiment g5 contingency Aug 9-11 e 1.6/4.0 H2 gas 3 Resume e commissioning OR Aug 6-11 e 1.6/4.0 H2 gas 6 Resume e commissioning Aug 14-29 e 1.6/4.0 H2 gas 16 Sep 11-15 e 1.6 H2 gas 5 Begin Experiment e1 Sep 18-25 e 1.6/2.4 H2 gas 8 Oct 16-27 e 2.4 H2 gas 12 Continue Experiment e1 through end of 1997 -- 62 days total. January 1998: accelerator down February 1998: begin Experiment g1