Pre-commissioning Plan for g6c (August 13, 14, and 15)
Tagger repairs (E and T counters). We use the first 12 T counters in the trigger but want to read ALL counters into data stream.
Target move (1m upstream)
Start counter/scattering chamber move (about 13 cm from target downstream)
Trigger hardware check (ASYNC1 and ASYNC2 logic, thresholds, widths…)
Installation/test of HV control for ST booster
Installation of PWO PRIMEX calorimeter/TAC in Hall (PRIMEX team)
Removal of goniometer/crystal from beam line
Check (visually) for possible background sources from PRIMEX set-up (installation of shielding)