Minutes of Regular Hall C Meeting
October 9 @ 3:00 p.m.
************************************************************************
- Engineering (Bill Vulcan)
- Made cables for GEN
- They need 300 high voltage for G0, and 200 are completed
- Cable tray that is in way of G0 cryo line has been moved 11 3/4 inches
- 15 cables were messed up for G0
- Took 9 ft. off cables for GEN/Madey (signal Veto Cables)
- Requested 9 inch moving of cable tray for G0 cryo
- Cryo-target (Dave Meekins)
- Cleanup and diagnosis
- Finalized testing has been done, check list has been made
- Fabrication of new parts are done, new windows made
- Installation done
- Pump and purge, pump and purge target needs to be done, how-to paper needs to be written
- Design of improvements
- Survey and motion checks in progress
- Survey of scattering chamber has to be done
- Pump and purge storage tanks
- Survey and align have new cells
- Solid target ladder removed
- New viewer on bottom of cryo stack
- Pump and purge written procedure, updated flow sheet
- Setup to fill H2 and D2 tanks
- Problem with angle of beam
- Struggle with moller
- Beam will not be sent until 20th of October
- Initial things: Ion chamber and charyldis test plans to verify beam links center of dump
- Will need to raise voltage a little
- Small problem with spectrum
- Had a detector meeting, things are fitting together good
- Bad news, last shipment will arrive in January
- French detector shipment should arrive here by Thanksgiving
- Will need to schedule test fit and guides in Hall C
- Target meeting on Friday, schedule target parts in January and February
- Magnets will be shipped before Thanksgiving
- Nov. 16th/17th is the next Collaboration Meeting
- Paperwork has been submitted for new staff position
- Was told that there is a short of man power, and we might be hiring more physicists