Minutes of Regular Hall C Meeting

October 22, 2001@ 3:00 p.m.

************************************************************************

 

 

¨      General (Rolf Ent)

 

v       The hall will close Wednesday at noon for beam

v       Accelerator started restoring beam after recovering from an LCW pipe rupture

 

¨      Installation (Walter Kellner)

 

 

v       Ferris Wheel work was completed

v       Gen small jobs were completed and are ready for Wednesday

v       Hall beam infrastructure is progressing well

 

¨      Engineering (Paul Brindza)

 

v       Maintenance on HMS magnets is being worked on

v       Quadrupole heaters needed work, almost done

 

¨      Moller Status/ODH event (Howard Fenker)

 

v      Last Friday a test on JT valve controller was made, resulting in N2 exhaust through a relief

v      The N2 loss resulted in an ODH alarm by the He sensor

v      It appeared a N2 sensor was missing, has been installed now

v      The relief valve is going to be changed to 35 PSI (from 15 PSI)

v      A relief line is installed to vent the gas (initially) in the hall.

 

¨      Gen (Marko Zeier)

 

v       Polarized target magnet was turned off over the weekend, start up today to do thermal equilibrium measurements

v       N Detector is operational and ready

v       Hamlet did test on laser and HMS detectors last week

v       Epics monitors were done by Steve Wood

v       Concerns: beam current asymmetry because of 3 laser operation, and beam leakage

v       Injector test at 15 micro-amps slow leakage of less than 1% by Hall A laser, with slits closed to 100-150 nAmps

v       Raster frequency will be 1H2 after all

v       Friday to survey beam line with vertical chicane

 

 

 

 

¨      General (Hamlet Mkrtchyan)

 

v      HMS hodoscopes had some problems, fixed.  Will get Bill to look at it tomorrow

v       Noisy plane (2V1) in chamber

v      Today there were problems with laser, will look into it.

 

¨      G0 (Greg Smith)

 

v      4,000 connections for G0 Ferris Wheel were made, thanks all involved

v      With additional access time, cables could be tested too

v      6 or 7 octants were finished, job well done

v      32 multi connector HV cables, will come in Friday

v      Alignment work of chambers was done, may need one more try

v      Leakage of French octant PMT’s was false alarm, was due to working of monitoring PMT

v      Fiber optics will get plugged in today and tomorrow

 

¨      Gen (Dick Madey)

 

v      Showed data from his run

v      Showed various cuts selecting proper quasifree events in invariant mass spectra