Minutes of Regular Hall C Meeting
November 8, 1999 @ 3:00 p.m.
- Engineering (Paul Brindza)
- Had a meeting on HMS magnet controls, will need longer data cables to relocate controls
- Showed schedule for running experiment in between Gen installation period, seems possible
- Showed pictures on the transfer line for G0
- Engineering (Bill Vulcan)
- Installation cable tray for G0 upstairs to downstairs is being worked out
- Reports on cryotargets: 3 targets repaired (new bearings)
- Survey done today
- On schedule to start cooldown tomorrow evening, possible beam on Wed.
- Showed the running schedule for the rest of Nov.
- Hodoscope all setup, doing a check list now
- Testing time resolution now
- SSD will arrive next Monday, start installation
- Requesting space in the EEL for equipment
- Everything else is done
- Dec. 20 Collaboration meeting
- 2 people from Ohio will be doing assembly and test for Hampton Gen detectors
- Showed the bearings that went bad in the target, good ones are here and put in
- Pumping on target now, Wed. should be ready to start running
- Looks like there should be enough time to complete experiment providing everything else goes o.k.
- Hall C Collaboration will take place in January, adjacent to the High Energy workshop