Minutes of Regular Hall C Meeting
May 10, 1999 @ 3:00 p.m.
************************************************************************
-
Engineering: (Bill Vulcan)
-
The bulkhead connectors are in
-
Panels for connectors are in, need to drill holes
-
AC supplies are ordered for HNNS (2-3 days)
-
DC cable was ordered (be in Wed.)
-
All vesda heads will be replaced this down period,
vesda in HMS will be moved to forward wall
-
The chips on quad interface are Hct chips, which are c mos;
will replace with Ls; will replace are parts on board
-
A(e,e’p) status (Kevin McIlhany)
Calo – peds
Calo – thresh
Calo – calib
-
VESDA – radiation damage, expect trips lost ~16 hours
-
Coincidence timing HMS« SOS
-
Q123, D1 trips lost ~ 7 hours
-
HV crate/card replacement lost ~ 7 hours maybe more!
-
MCC related lost ~ 12-16 hours
-
Maintenance Days (Rolf Ent)
-
Coincidence timing (hardware)
-
SOS pointing at large angles
-
VESDA heads swap/shielding
-
Target Raster Modification in June 1999 (Chen Yan)
-
Make two parallel system: Pseudo-spiral (1998) and TV
Type (1996)
-
They can be alternated within two hours:
-
Switch power resonance loop (Hall C)
-
Switch BRm monitor and FSD setting (Fast electronics)
-
Switch EPICS control (Machine software)
-
Karen agreed to make two software switchable (two down load time) during
June shutdown
-
Machineshop is producing 4 power resonance loops, due by 05/30/99
-
Fast electronics group needs either re-calibrate the two system or build
the second chassis (Chris?)
-
Paul Brindza
-
Cynthia Keppel
-
Jiang Xiaodong
-
Richard Madey
-
Steve Wood