Jefferson Lab > Physics > Hall D
Privacy and Security Notice

Replacement Solenoid Conceptual Design for Hall D/GlueX - Reports

JLaB Reports

June 29, 2011

  • D0000004-02-3000_RevA.pdf (Interface)
  • MIT Reports

    October 18, 2011

  • JLab_Final_Report-MIT.pdf (Conceptual Design Report - Deliverable)
  • Action_Items_Final_Status.pdf
  • September 28, 2011

  • JLAB_Hall_D_Cost_and_Schedule_Estimate.pdf (Preliminary Project Schedule and Cost - Deliverable)
  • August 23, 2011

  • Rationale_for_Conductor_Choice-08-22-11.pdf (Rationale for Conductor Choice - Deliverable)
  • August 23, 2011 - Internal Documents for reference only

  • GlueX-AR-110808.pdf (GlueX Coil Sizing, Rev 4)
  • GlueX-AR-110715.pdf (Sizing cold mass support rods)
  • GlueX-BASmith-110808.pdf (Cable in conduit conductor)
  • GlueX-BASmith-110804.pdf (SSC cable in aluminum extrusion)
  • GlueX-BASmith-110801.pdf (SSC Cable-in-copper channel)
  • July 6, 2011

  • GlueX-AR-110706.pdf (Coil Sizing Memo)
  • June 22, 2011

  • Conductor_options.pdf