Date Task
1/5/2010 FEL instrumentation investigation. (RF Rad. Alarm)
1/7/2010 New B1000 Dose Rates calculated.
1/8/2010 Adjusted calibration range's platform to accommodate new Bicron procedure. Editing calibration procedure.
1/11/2010 Trail run of procedure for badge shots.
1/18/2010 BICRON 1811 failed source check and 1812 was observed spiking on lowest setting.
1/19/2010 Started field probe verification.
1/26/2010 GTS Radiation Monitor certification. (RM211)