Date Task
6/2/2010 Performed quick cal on the 2 gamma probes in the ITC for Riad.
6/2/2010 Reinstalled RM44 for Hall A after modifications.
6/9/2010 Terminated ion chamber cable and located and tested 7 of 8 cables. 8th cable (#1) may have been cut.
6/10/2010 Percy and Scott helped pull in cable for transport tunnel platform.
6/17/2010 IP-100 repairs.
6/18/2010 Installed ion chambers 1 - 3 in Hall C.
6/18/2010 Refridgerator  updated with new probe positions and numbers.
6/23/2010 Ion Chamber test box training and setup on ion chambers 1 and 2. (Rich and Scott)
6/23/2010 Replaced BSY gamma probe.
6/25/2010 Installed ion chamber 6 (sieve box) in Hall A.