MEMORANDUM
To: J. Albertine, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IRFEL Weekly Report, August 11-15, 1997
Date: August 15, 1997
Management
Highlights for the week include installation of the 10 MeV dump
hardware and connection of the cryomodule instrumentation in preparation
for cool-down later in the month. Low conductivity water is now
flowing through all the RF systems.
Management attention was focused on closure of the July financial
reports for the project and set-up of accounts for the use of
the commissioning/upgrade funds which were released to the laboratory
last week.
Scheduling activities are focused on carefully integrating the
remaining installation tasks with the start-up of commissioning
tasks. Installation tasks are being phased such that remaining
installation tasks will have little or no impact on the first
commissioning tasks which will proceed from the gun to injector
cryounit to linac cryomodule to wiggler to recirculation arc.
Final preparations were concluded this week for the project's
presentations at next week's International FEL Conference in Beijing.
The following papers will be given by project staff:
"Status Report on Jefferson Lab's High-Power Infrared FEL"
- C. Bohn
"Progress on the Study of Emittance Growth Induced by Transient
Self-Interaction of a Bunch Entering a Bend" - R. Li
"Experimental Results from a DC Photocathode Electron Gun
for an IR FEL" - D. Kehne
"Optical Modeling of the Jefferson Laboratory IR Demo FEL"
- S. Benson
"Real-Time Transverse Emittance and Phase-Space Monitor"
- J. Song
Accelerator Systems
Regarding the beam-transport system:
All optical chicane dipoles are now in house and in-coming mechanical
inspections and Hall probe measurements have been completed.
As noted on last week's reports, these magnets have not met specifications.
We are planning to improve the assembly procedure in-house and
re-measure these magnets.
We have sent a Jefferson Lab staff member to the vendor (Everson
Electric) for several of the dipole magnets to review assembly
procedures.
The RF shielded bellows was successfully redesigned, fabricated,
and leak tested. The radiation shielding for the tune-up, recirculation,
and straight ahead dumps was reviewed and it was decided that
the usage of existing SEG blocks and some lead bricks would satisfy
our needs.
The drawings for the magnet stands in the recirculation line are
complete and await signature. One differential pumping station
was assembled this week and ready for installation.
Regarding cryomodule fabrication:
The cryounit remains stable at 2k. Plans are in place for cool-down
of the full cryomodule on Aug. 24-25. Commissioning will start
when associated RF systems are complete.
Regarding RF systems:
Both 50 kW klystron systems are now in the FEL building. The
installation for the quarter cryomodule is about 40 % complete.
Both 225 kW variable power supplies from Hipotronics have been
installed. The first unit has been connected to AC power. Its
installation is just getting started. The second unit is for
an upgrade next year. Minor repairs need to be made to both units
as a result of shipping damage. The RF system for the linac is
about 40 % complete. We are still waiting for direction from
the vendor on what they want us to do with the second failed spare
50 kW klystron. The buncher water skid is ready for installation.
The RF system for the buncher is about 40 % complete. The Master
Oscillator (M.O.) and its components are installed in the FEL
building. Insulation of the LCW pipe and M.O. distribution cables
are to be finished this month. The M.O. system is about 80 %
complete. The elbow for the 500 kV High Voltage Power Supply
was reworked and is back on site. Next week J. Fugitt will determine
if it now usable.
Regarding instrumentation and control systems:
The installation activities included beam position monitor electronics
and completion of cabling. The vacuum cable installation was
delayed due to additional cable trays being hung in the tunnel.
All of the ion pump power supplies are checked out and are being
installed in the racks, both crates are already in.
Beam viewers are being fitted with 1.5 micron Al foil for installation,
also the multislit devices are awaiting installation.
The Personnel Safety System will be certified beginning next week.
Hardware and software debugging continued on the cryomodule temperature
diodes.
The IOC's are operational, the network hub had a slight problem
recovering after a scheduled power outage, this was quickly rectified.
The servers FEL1 and 2 are running fine.
The Analog Monitoring System (AMS) system prototype boards are
working well, the system is running with flat response out to
10MHz. The design should be finalized by this week with production
PCB's to go out by next week. Work continues on the dump instrumentation
and interlocks.
FEL Systems
Wiggler
Another clearance problem in the wiggler vacuum chamber support
was found. The T-bars were then sent out to be modified. The
plates for the wiggler girder were lowered by one inch and regrouted
and the wiggler was reinstalled and surveyed into its final position.
Optics
The week was spent finishing up work on the optical transport
pipe in the accelerator enclosure. Pipes were cut (or added)
to the correct length, and flanges were welded to them. We will
begin vacuum checks next week. The mirror can stand in Optics
Control was shortened to the correct height, and was aligned so
the transition pipe will be properly aligned to the beam. That
pipe is being fabricated today (8/15). The installation crew
set all of the upstairs optical transport stands to the correct
height and began installation. The TJNAF machine shop modified
the gimbal mounts to the correct i.d., this allowed us to complete
the downstream cavity assembly. We will leak check it and then
move it to the FEL building when the cable tray installation and
cable move is more or less complete. The parallelism between mirrors
and their mounts was checked. There is a definite improvement
when the mirror is loaded during the indium brazing procedure.
The residual tilt is < 1 mrad, easily corrected by the gimbal
mounts.
Commissioning/Operations
The Diagnostic Integration plan was presented at the weekly commissioning meeting. The slides can be viewed on the www at: http://www.jlab.org/~legg/081297_comm/commtg.ps. The main points were:
The diagnostic integrators are responsible for the hardware.
The diagnostic integrators are responsible for the software to operate the devices.
They are not responsible for data analysis or high level applications.
High level software to execute particular test plans will require
the Principal Investigator to write it or see the software group
and discuss the need. They will put it in the queue for software
tasks and ask the commissioning group for the FEL to assign it
a priority within the FEL tasks. Similarly, the Diagnostic Review
committee will rule on changes to diagnostic hardware and priorities.
It was reported that it was not possible to align the wiggler
using the pulsed wire system. However, the four wiggler quads
have been aligned to within 100 microns and the measurement corroborated
the STI measurements on the wiggler which verified that the wiggler
was undamaged magnetically in shipping. We still would like to
check the alignment between the wire and the wiggler which will
allow cross alignment to the quads.
There appears to be a problem with the first cavity in the cryounit's
Qext. The optimum loaded Qext for 1.1 mA (first light) is different
enough from the 5 mA case, which was designed for, that the RF
power requirement will increase by 5 kW if the situation is not
corrected using a stub tuner or waveguide iris. It was decided
after discussion with members of the SRF department, that the
power lost was not sufficient to necessitate redesigning the
waveguide into the cavity. The second cavity in the unit was
acceptable and the data on the cryomodule from the VTA had not
been analyzed yet.
The results from the Injector Test Stand 350 kV tests were summarized
in the paper, "Experimental Results from a DC Photocathode
Electron Gun for an IR FEL", Kehne, et al., to be presented
at the FEL conference in Beijing. The longitudinal measurements
in the paper are noteworthy for their agreement with PARMELA.
A technical note on "Fine Phasing for the Cryomodule Using
the Energy Recovery Dump" was completed after review by the
Performance Integrator for RF phases for the FEL.
Facility
Punch list work continues as does site preparation for seeding.
The elevator is operable under Plant Engineering control but
has not been signed off. Problems with condensation dripping
from chilled water lines are being addressed.
Clean Air Technology certified the clean room. The waveguide
for the buncher was installed. The second 50 kW klystron and
power supply were moved to the FEL facility. The final stand
for the drive laser transport line was signed off.