MEMORANDUM

To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report, August 4-8, 1997

Date: August 8, 1997

Management

Highlights for the week included testing of the new HV supply for the gun in the FEL facility to 200kV in air and the wiggler was reinstalled and surveyed into the correct final position.

This week the FEL Project received $3.7M of Navy funding for the period Aug. 1997 to Sept. 1998 for the tasks of preparing the IR Demo for commissioning, commissioning the IR FEL, and initial design and procurement activities for the IR Upgrade. Receipt of this funding follows the signature last week of the second Navy-DOE Memorandum of Agreement for the IR Demo Project.

Review and revision of the pre-proposals that were submitted last month for initial use of the IR FEL continued. Discussion was initiated with NREL on a possible collaboration on the use of the IR FEL for applications to photovoltaic materials.

On Friday, F. Dylla visited DuPont Experimental Station for an update on DuPont's proposals and plans for the polymer lab in the FEL User Facility.

Discussions are on-going with both DuPont and Armco with regard to their comments on the initial draft of a User Facility Agreement for the FEL user labs that would incorporate their equipment provisions for the polymer and metals labs, respectively.

Jefferson Lab was invited to co-sponsor a Workshop on Fourth Generation Light Sources that will be held at the Advanced Photon Source (Argonne, IL) on Oct. 28-30. The workshop will focus on the FEL technology and applications for deep UV and X-ray FELs.

The Navy Program Office has tentatively identified Oct. 1-3 as the timeframe for a site visit and review of the IR Demo Project.

Work intensified on writing papers and preparing presentations for this month's Free-Electron Laser Conference. Jefferson Lab has five scheduled presentations there concerning the IR Demo.

Accelerator Systems

Regarding the beam-transport system:

Installation of the injection line in the FEL Facility continues to progress. The mismatch in the height of the injection-line dump reported last week was completely fixed; the dump is now bolted to the beamline leading to it.

We characterized with the Hall probe six of the seven optical-chicane dipole magnets that came in last week. Their field profiles generally look reasonable. Results from the core-field measurements show a deviation from the population average by ± 0.2% as compared to our desire to achieve ± 0.1%. Though we still need to do a careful assessment, we believe the measured deviation will prove satisfactory. The last optical-chicane dipole is due to be received next week. All of the magnet measurements on these magnets (Hall-probe measurements and dipole-field mapping) are slated to be complete by 24 Aug. 97. We suspect that the machining and assembly tolerances at the vendor (Everson Electric) can be improved, which in turn should improve field-profile deviations in future deliveries. Consequently, we are sending a Jefferson Lab staff member to Everson Electric early next week to review and discuss manufacturing procedures and resolve related questions that have recently arisen there in regard to assembling the injection/extraction dipole magnets. Everson Electric now has the parts and are ready to assemble the first article of this dipole type. At the vendor's (Magnet Enterprises) request, we ordered more conductor for use in manufacturing the two 180-degree dipole magnets.

Design of the skew-quadrupole magnets is in final detailing. They will be manufactured in-house at Jefferson Lab. The quadrupole magnets for the energy-recovery dump line are all in final assembly at New England Technicoil and are slated for delivery in about 10 days.

Design of the air-core corrector magnets that are to be mounted on the beam-position monitors is complete.

Stands and girders for the straight-ahead dump area are on order, and all of the vacuum components supporting first light are either on order or in fabrication. Girders for the X and Y vacuum chambers and for the double-quadrupoles are in assembly. The straight-ahead dump was successfully brazed and is in final welding.

Fabrication of the insertable dumps is about 1 week away from brazing of their main-body components. Designs of the stands for the insertable dumps and scraper are complete. Regarding the electron-beam scraper, the assembly drawing for installation of its cross is complete, and the design of its main body is once again in progress after being on hold for three weeks to accommodate higher-priority design activities.

Concerning vacuum chambers, four of six optical-chicane chamber components are complete and ready for installation, and the other two chamber components are at the Magnet Measurement Test Stand where they are being used to assess the effect of the vacuum chambers on the field profiles of the optical-chicane dipole magnets. For the recirculation arcs, the straight vacuum-chamber components are in fabrication (two are tacked), and the curved vacuum-chamber plates are due in from the vendor next week.

Regarding cryomodule fabrication:

Work focused on cabling for the installed cryomodule instrumentation. Instrumentation will support cooldown, commissioning, and operations. Planning for commissioning the cryounit and cryomodule continues.

Regarding RF systems:

Both of the 8-unit klystron power supplies built by Hipotronix were received and moved into the klystron gallery in the FEL Facility. Prior to this, the #2 power supply was run to full power at the factory and passed our acceptance tests.

The remaining (second) 50 kW RF system was moved from the ITS into the FEL klystron gallery.

We are still awaiting final shipping instructions from Russia for our failed spare klystron. It is worthwhile to note that almost all factories in Russia are closed for holiday the entire month of August. Any communications are extremely difficult. However, the spare 50 kW RF circulator was tested with the klystron in the ITS prior to its move, and passed our acceptance criteria.

Regarding instrumentation and control systems:

Installation activities included cable pulls for analog monitoring, video distribution, cryomodule instrumentation, beam position monitors, and control room patches. The vacuum cables will be installed next week.

In preparation for cool-down of the cryomodule the temperature diodes were wired in and connected through the control system. This is the first complete test of the new server configuration, input/output controllers (IOCs) and network. All seems fine. All IOCs have been installed and are operational. The servers denoting FEL1&2 are running fine.

Design work centered on analog monitor system with the check prints for the backplane done and a prototype board for the input buffer board in test. Work is also progressing on the dump instrumentation and interlocks.

The WWW site for the FEL Facility is progressing rapidly with individual channel assignments being added for the VME boards, and system layouts being added for the accelerator enclosure.

FEL Systems

Wiggler

Another clearance problem in the wiggler vacuum chamber support was found. The T-bars were then sent out to be modified. The plates for the wiggler girder were lowered by one inch and regrouted, and the wiggler was reinstalled and surveyed into its final position.

Optics

Two significant accomplishments occurred this week. The first was the successful indium braze of a test mirror in a mirror holder without its cracking. The second was final alignment of the last three mirror cans in the accelerator enclosure. We are transporting a He-Ne upstairs to the Optics Control room with very little (not visually apparent) vibration. We are close (~ 1 week) to installing connecting bellows and the optical components in Optics Control. The optical cavity assemblies are nearly complete, we are awaiting particulate tests on the valves. We must also open up the i.d. of the gimbal mounts, they were made slightly smaller than spec., and this slipped through the inspection process. This will cause a slip of less than a week. We received a verbal report from China Lake on the metrology results for the sapphire cavity optics made by Research Electro-Optics (REO). The results show all of the radii of curvature are longer than the spec (0.2%); the mirror figure was also out of the tenth wavelength spec. We've sent one mirror to REO for immediate inspection, China Lake is preparing to send the others. We received one set of cavity optics from Rocky Mountain Instruments, they will be sent to China Lake this week.

Commissioning/Operations

Additional simulations of the beam dynamics from photocathode to wiggler were completed. These simulations concern bunch charges for first light (60 pC) and "zero" current. In particular, the beam dynamics were assessed at these lower bunch charges given the machine setup for full-power runs, e.g., 135 pC bunch charges. The 135 pC settings appear adequate for both cases; the 60 pC case actually looks better with the 135 pC lattice than does the 135 pC case itself. Code results indicate we will need to be careful about setting the first solenoid (to 280 G) because the results are sensitive to this setting, degrading rapidly as the solenoidal field is increased above 280 G. As a matter of principle, we will also need to check stray fields after the cryounit to ensure they do not interfere significantly with the very weak fields of the quadrupole magnets on the injection line.

Work continued on the performance integration plan for RF systems. The simulations feed into this plan by establishing baseline RF settings and specifications for their sensitivities. Delineating the sensitivity specifications is the current priority.

Facility

Punch list work continues (180 items and counting down) as does site grading. The fire alarm and sprinkler system were tested. There are a few things to fix but the system is operational, although it reports only locally. Touch-up of tile work was done, and a display case was installed in the entrance lobby.

Jefferson Lab folks did lock-down positioning of the optical transport lightboxes, and they made preparations to cut the pipe and weld the flanges in place. The wiggler was placed and surveyed into the correct final position. Cables were pulled into position for the beam position monitors. Survey located the positions for all of the arc stands in preparation for setting them.

Cabling to the cryomodule is being terminated. Cool-down of the cryomodule has been delayed to early September, coinciding with a CEBAF maintenance day, to avoid the possibility of interference with the nuclear-physics accelerator. The large high-voltage power supplies for the 8 kW RF system that drives the cryomodule were placed in the RF gallery, and hookup began. Some shipping damage (broken resistors, etc.) was discovered which will require a site visit by the vendor to repair.

The gas-insulated high voltage power supply for the photocathode gun was tested this week at atmospheric pressure. We were able to hold 200 kV continuously and about 220 kV for short periods. Our design goal was 180-200 kV. This is an important test data point for us, because it is the basis for extrapolating by a factor of 4 to 5 to the final design voltage with pressurized SF6 gas. The elbow for the coaxial line to the gun was received but did not pass inspection and was returned to the vendor for corrective action.

Clean Air Technology certified the clean room. The waveguide for the buncher was installed. The second 50 kW klystron and power supply were moved to the FEL Facility. The final stand for the drive laser transport line was signed off, and the other stands were ordered for delivery 29 Aug. 97.