MEMORANDUM
To: J. Cook, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IR Demo Project Weekly Report, December 15-19, 1997
Date: December 19, 1997
Management
Highlights for the week include: (1) completion of the replacement
of the vacuum isolation valves on the linac cryomodule and cooldown
of the module to 2K; (2) placement of the beamline from the exit
of the cryomodule to the tune-up dump under vacuum; (3) restart
of beam commissioning activities; and (4) sign-off and release
of the reverse bend dipole magnets (DQ) from magnetic measurements.
The project monthly report for November 1997 was completed and
distributed to the DOE and Navy Program Offices.
The preliminary agenda for the Jan.14-15th LPC Workshop was prepared
and distributed to the consortium mailing list.
On Monday, Dec.15, F.Dylla, accompanied by W.Lundy and C.Moore
of NASA-Langley Research Center, gave a joint briefing to the
NASA Chief Technologist, Sam Venneri, at NASA Headquarters in
Washington concerning NASA's potential interest in using the IR
Demo User Facility. Venneri suggested that several NASA Centers
should have an interest in using the FEL for NASA-related activities
including: JPL for microfabrication R&D, NASA-Lewis for advanced
coatings development; and NASA-Langley for R&D on materials
and polymers. He asked that a capabilities/facilities use document
for the IR Demo Facility be forwarded to the above NASA Centers.
Commissioning
We began beam commissioning activities at 14:30 yesterday (12/18),
not surprisingly went through a few hiccups in the process of
turning on the injector, and by 0800 had beam at the viewer immediately
preceding the cryomodule after running it through the injection
line with both cavities crested. Beamline parameters from the
November runs seemed to work well, indicating consistent machine
performance.
This morning (12/19), checkout of the vacuum-interlock system
through the cryomodule down to the straight-ahead dump is proceeding.
Open questions at this writing (1100 Friday) include whether
to reset the vacuum-valve trip limits in the vicinity of the optical
cavity, and if so, to what values, and how to configure software
controlling the rf interlock to the drive laser so it does not
needlessly shut down. Both are being worked this morning.
Plans are to take beam through the cryomodule today and do transient
phasing tonight. Then tomorrow we take beam through the optical
chicane and crest the cryomodule cavities. D. Douglas suggested
we consider taking the beam all the way to the straight-ahead-dump
viewer and then crest, a process that he thought would be straightforward
based on experience with CEBAF. We will consider this idea.
J. Preble reported that the cryomodule's performance after thermal
cycling for replacement of the troublesome valves appears unchanged.
Gradients for all of the cavities are consistent with earlier
measurements, as are the unloaded Q's of the entrance and exit
cavities. On the other hand, the static heat load rose, raising
the error bars in the Q measurements. The source of the increased
heat load is not yet identified. Bottom line is that all indications
are that we still have a 47 MV cryomodule.
Installation Activities
The SRF group installed 2 VAT valves on the cryomodule and pumped
it down to 2°K this week. It appears the cryomodule handled
the thermal cycle without cavity gradient or Q degradation, but
with a heat load increase.
The installation of all magnets, diagnostics, and vacuum equipment
for the machine through the 2G, straight ahead dump, were made
and appropriately shielded for operations.
The RF cryo heater control code was tested this week under load
resistors. It is ready to test under RF operations. A software
bug to download the external RF coefficients was found and solved
this week. Additional work is being done to separate the Injector
RF modules into individual systems and make the overall Injector
more robust.
The 4 DQ magnets have been measured, signed off, and are available
for installation in January.
The last DV magnet had its field clamps adjusted so that it now
meets the field flatness specification, but it will be tweaked
next week to improve its effective length.