MEMORANDUM
To: J. Cook, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IR Demo Project Weekly Report, December 8-12, 1997
Date: December 12, 1997
Management
Highlights for the week include: (1) completion of all preliminary
alignment activities for the wiggler/optical cavity section; (2)
completion of all vacuum connections from the exit of the linac
cryomodule through the straight-ahead dump; and (3) initial vacuum
checks of this entire sector.
Feedback from DOE-BES reviewers was distributed to the 11 principal
investigators who have submitted preproposals for using the IR
Demo for basic science studies. Five of the 11 proposal teams
have been asked to submit full proposals to the BES Program Office.
The focus of next month's (14-15 Jan 98) LPC Workshop will be
presentations from most of the proposal teams.
On Tuesday, 9 Dec. 97, two staff members from the Congressional
Energy and Water Resources Committee visited the Laboratory for
tours and discussions, including a tour of the FEL Facility.
On Wednesday, 10 Dec. 97, the third meeting of SURA's Maritime
Technical Advisory Committee was held at the Laboratory. The
focus of the meeting was two-fold: (1) a progress report on the
IR Demo commissioning, and (2) the plan for experimental use of
the Demo including various Navy interests.
Installation Activities
The two replacement vacuum valves that protect the cryomodule
were shipped from VAT in Switzerland on Wednesday, not last Friday
as had been hoped. As of noon today, they were still in Customs
in Memphis, TN, and are to come directly to us from there. We
now anticipate receipt Monday morning, with installation slated
for late Tuesday, followed by cryomodule cooldown. Commissioning
activities with beam would then resume Wednesday.
All vacuum connections through the straight-ahead dump have been
made, and initial vacuum checks have taken place. This first-light
beamline will be pumped down as soon as the cryomodule valves
are replaced.
Necessary modifications of the sulfur hexafluoride and nitrogen
lines were completed this week.
All of the QG quadrupole magnets in the beamline between the cryomodule
and the straight-ahead dump line are now installed, and they are
being tested this afternoon. The CEBAF-spare air-core corrector
magnets are being installed today in this beamline and in the
straight-ahead dump line.
The remaining components for the optical cavity (minus the mirrors)
were installed and the cavity was pumped down. A small leak in
one section is being repaired today.
All of the viewers in the beamline between the cryomodule and
the straight-ahead dump line are now installed and tested. The
viewers preserved their alignment during pumpdown of the optical
cavity. The wiggler is scheduled to be removed Monday so as not
to be damaged by stray beam during commissioning.
Commissioning Activities
A detailed schedule of shift assignments and tasks was developed
to take us from the time of valve installation (see above) to
Christmas. The schedule preserves the primary goal of getting
tuneup beam to the straight-ahead dump before Christmas. The
last day shift of installation before Christmas will be on Wednesday,
17 Dec. 97, after which we will run around the clock through 23
Dec. 97.
There has been considerable commissioning activity not involving beam. The optical transport system leading from the wiggler area to the optical control room was pumped down and taken through its first tests with a surrogate laser beam. The pipe was found to be leak-tight, but the beam was seen to wander. The bellows leading into the mirror cans were stiffened, and a retest is scheduled for this evening. Further RF commissioning is continuing on the injector cryounit to enhance the stability of its operation. The source of the 2.7 dB miscalibration discussed in preceding weekly reports was identified and confirmed to be only a matter of downloading to the control screen, meaning the gradients measured during SRF commissioning stand as reported earlier (12 MV/m and 8.5 MV/m for the entrance and exit cavities, respectively). The problem was slated to be fixed this afternoon.