MEMORANDUM


To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report, February 17-21, 1997

Date: February 21, 1997

Management

Presentations for the DOE-BES Review scheduled for 23-25 Feb 97 were polished under the scrutiny of top Jefferson Lab management.

It was decided to defer all 10 MeV injector operations with electron beam to the FEL Facility, and to concentrate activities in the Injector Test Stand (ITS) toward maturing the technology for the photocathode gun and establishing reliable operations of the gun. Complete testing of the cryounit without electron beam will also take place in the ITS as originally envisioned. Plans are to move all gun and injector hardware to the FEL Facility starting 1 June. These injector activities preserve the milestone of installing all hardware in the Facility by 30 Sep 97.

Injector Test Stand

Check out was completed on the hardware and software for the transverse/longitudinal phase-space measurements in the beamline, calibrating the wire scanners (harps) and magnets, and setting up the beam through the downstream wire scanner (harp). Good extinction ratios were also achieved of unwanted ghost pulses from the drive laser. A power supply for the Personnel Safety System (PSS) failed, but we recovered and recertified the PSS. Commissioning of the rf kicker cavity for the longitudinal measurements continued, as did commissioning of the spare 50 kW klystron.

Regarding upgrading the photocathode gun:

* Coated Cathode-Support Tube - The coated cathode support tube was received from FM Technologies and is being prepared for electron-beam welding.

* Ion-Implanted Ceramics - Lawrence Berkeley Laboratory modified the rotisserie to enable continuous monitoring of the ceramic's resistance during implantation. They subsequently commenced ion-implantation of the second ceramic while, in parallel, diamond-scrubbing the inadequate coating off of the first ceramic.

Regarding other ITS activities:

Commissioning was completed on the new resonant-ring fixture for testing warm ceramic windows, and testing of two windows followed. The tests included improved vacuum conditions and a new infrared imaging diagnostic supplied by NASA to monitor window heating. Unfortunately our vacuum interlock failed during the tests, resulting in a broken window. Subsequently we upgraded and tested the vacuum interlock, and we do not expect a repeat of this failure.

Additionally, we began developing a new window-test resource based on using one of the 50 kW klystrons to supply rf power to the window test fixture. This is expected to reduce the complexity of the testing and provide a better model of the actual operating conditions. It will also allow parallel testing of warm windows in both the resonant ring and ITS cave. Warm windows are available for testing.

Accelerator Systems

Regarding the beam-transport system:

The design of the reverse-bend dipole magnets continued, and the back-check changes to the optical chicane dipoles were being done at Northrop Grumman. The completed vellums of the latter, ready for signature, are slated to be at Jefferson Lab on Wednesday morning.

We attempted to glue mu-metal to the prototype dipole pole tips with an epoxy system. The resulting gap was not satisfactory, with .001-.002 inches lost to epoxy thickness. The correlated variation in the field uniformity seen in magnetic measurement of the result convinced us that this is an important parameter and that we have to devote some development effort to it. The magnet will now be used to test the influence of vacuum-chamber welds on magnetic field. Plans are then to grind the mu-metal pole tips flat and parallel to the contact surfaces of the back legs and remeasure.

The prints for the differential pump station, back-leg girder and injection-dipole girder are ready for signature. Layouts of the stands for magnetic elements downstream of the cryomodule were reviewed.

The first-article focusing quadrupole magnet passed its acceptance tests. The stand for the prototype trim quadrupole was readied for more detailed measurements. The prototype sextupole was assembled and is now ready for measurement.

Regarding cryomodule fabrication:

A final internal review of the cryomodule design and existing test results from the ITS cryounit was held on 19 Feb 97. No show-stopping issues were identified. Responses to questions are expected by 28 Feb 97, with close-out documentation eventually to follow on www.

Regarding electron-beam diagnostics:

The beam-position monitor (BPM) contract was awarded with a delivery date of 18 Apr 97.

Specifications for the power supply for the optical-chicane magnets was reviewed and signed, and a purchase requisition was written.

First-article (assembly) printed circuit boards for the beamline and gate-valve vacuum control cards were accepted. First-article control cards for the ion pump power supply (IPPS) was tested and accepted. Enough boards will be produced to replace all of those boards in CEBAF for both the IPPS and gate valve controllers.

A leaky 6-way cross is holding up production of one of the beam viewers. The cross is needed to support the beam-viewer assembly. The vendor has purchased a new one and is machining it now. Assembly and leak checking should be complete by Monday, with shipment of 13 beam viewers by Feb 24th.


FEL Systems

Wiggler

Spectra technology has now measured and characterized a large portion of the magnets required for the wiggler with the result that all magnets measured lie well within the +/- 2% specification. In fact all magnets measured to date lie within a +/- 1% variation. This excellent performance will minimize the amount of trimming needed to achieve the overall wiggler field quality specification.

Optics

Design efforts continued this week on the optical collimator. The installation drawings for the optical transport pipe on the ground floor are nearly complete. Several subassemblies (i.e., bases and stands) for the optical cavity were received and assembly will commence in the coming weeks. The ion pumps were received, along with other vacuum hardware.

Operations/Commissioning

The process of detailing specifications for the insertable dumps (to be used in machine tune-up) and the scrapers began in earnest with the goal of resolving engineering issues that surfaced at the recent internal review of the IRFEL electron-beam dumps. Detailed electron-tracking analyses suggest that the scrapers may be completely unnecessary; deliberations are continuing on this question.

A new procedure was developed for setting the momentum in the arcs using the air-core corrector magnets that are already part of the baseline design of the arcs. The procedure will soon be posted on www as part of the "arc 1 setup procedure".

Facility

The major effort this week was on framing the upper level of the facility. By Friday the major frame steel was complete 3/4 of the way down the facility permitting work to be planned for Saturday in initiating joist installation in the East end. The lower level floor was cleaned after flooding the previous week and several actions taken to ensure that flooding cannot occur again. The HVAC compressors were set on their pads and electrical hookup of the main switchgear initiated. The contractor was sent a get-well letter reminding them that there is a $ 1500/day penalty on not achieveing beneficial occupancy of the second level by 3/15/97. At present it appears that they are 2 weeks behind that schedule.