MEMORANDUM

To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report Feb. 3-7, 1997

Date: February 7, 1997

Management

Preparations moved into high gear for the DOE-BES review of the FEL project which will occur February 23-25. A briefing package was prepared for the reviewers and DOE observers. Outlines and rough drafts for the Jefferson Lab presentations were prepared. Guidance was provided to the outside speakers who will be presenting talks on FEL applications. All WBS managers were asked to review cost and schedule performance and to prepare summaries for the review.

Two talks to be presented at next week's SPIE Conference on high-power lasers were prepared by G. Neil and M. Shinn. Two of our FEL collaborators, M. Kelley and A. Todd, are also presenting papers at the same conference on the respective topics of industrial and defense applications of high power FELs.

A draft report from the meeting of MTAC on December 18 was received from SURA. Comments were returned to SURA and the Navy HEL Office. The committee urged the Jefferson Lab team and our industry collaborators to work with the Navy Program Office to strengthen the long-range plan for further discussions with Navy officials and congressional staff.

A draft Field Work Proposal for FY98-99 support of the FEL project by the DOE-BES program office was prepared for internal review prior to submission to DOE in March.

Injector Test Stand

We have manufactured a good cathode. The SF6 tank was reinstalled and charged. The existing ceramic stack was high voltage processed to 320 kV. Beamline diagnostics and magnets were reassembled and checked out. ITS control system was moved over to a new network server. We have aligned the drive laser onto the new cathode, therefore all systems are ready for startup of beam operations.




Regarding upgrading the photocathode gun:

Coating on Cathode Support Tube - FM Technologies reports the tube will ship on Wednesday, February 12.

Ion Implanted Ceramics - Lawrence Berkeley Lab is in the third day of implanting the first ceramic, and the second ceramic with newly brazed, leak tight rings is in their hands. Contact difficulties prevented uniformity test readings on the test ceramic. We were unable to convert our supply of platinum to rod. The powder was sent to Berkeley where their materials department will be able to do it by Monday afternoon which is just in time for use implanting the second ceramic. The mid-voltage ring is welded and is leak tight.

Regarding other ITS activities:

The waveguides and HOM filters with their LCW are all assembled and waiting for the installation of the warm windows on the quarter cryomodule. The Chopper coupler, cables, and water skid were installed again after the beam line was baked. The new cooling fins for the Chopper's drive probe were attached and connected to the water line.

The waveguide penetrations in the cave roof were plugged with sand last week. RadCon has approved and will inspect when we start beam operations.

Accelerator Systems

Regarding the beam-transport system:

The problems with interferences between the Optical Chicane dipoles and shielding for the optics were resolved with some slight alteration of the chicane dimensions by the machine optician and a change in diameter and down beam shift of the optical cavity enclosure.

The design of the reverse-bend dipoles and the 180-degree dipoles continued at Northrop Grumman.

Substantial portions of the vacuum hardware have been ordered over the past few weeks.

A kick-off meeting was very productive for design of the stands for magnetic elements downstream of the cryomodule.

Regarding controls and electron beam diagnostics:

Monday was spent at the beam viewer vendor machine shop for final inspection of the 13 shielded beam viewers. These were assembled and are being leak checked for shipping on February 7. The BPM has passed all of the tests, the drawings have been updated, and the requisition is being circulated for approvals. We are asking for 60 days for fabrication.

Argonne is reviewing the price of the Machine Protection System (MPS) hardware that we are procuring. Half of the boards are complete and awaiting the cost numbers.

The Personnel Safety System drawings for installation and rack layouts are complete and signed off.





FEL Systems

Wiggler

All elements for the wiggler support have been ordered. Design work is at the 90% level and holding for the vacuum chamber. This week's work has concentrated on the vacuum chamber support which is at the 30% level. STI Optronics reports that they have received most of the magnets from Shin-Etsu, and measurements are ongoing. STI projects that final measurements of the wiggler will be done by March 21.

Injector Reinstallation

Bids are due today (2/7) for the high voltage power supply tank. The bid period for the laser clean room was delayed to allow time for two more vendors to reply. Only one vendor had replied, and that quotation was higher than the budgeted amount. Design work is on schedule for the injector layout with about 30% of the work completed.

Optics

Design efforts this week continued on investigating potential interferences between the new optical chicane dipoles and the optical cavity assemblies. The problem was resolved as noted in the Beam Transport report given above. We also held a design meeting on optical table stands supporting the optical cavity assemblies. A follow-on meeting will be held next week. Several subassemblies (i.e., bases and stands) for the optical cavity are complete and are being inspected. A layout of the optical transport system is being developed to assist the installation team. The windows for the optical transport system mirrors were ordered.

Facility

Structural steel was loaded onto the second level throughout the week as preparations were made to assemble the framework. The rebar was laid in and the loading dock poured. At the same time, the pads were set for the HVAC compressors and the retaining walls for the electrical main transformer. Heavy rains managed to flood the injector and wiggler pits downstairs when power was accidentally removed from sump pumps early in the week. Cleanup of the lower level was begun so that cryogenic piping can be brought in and welding initiated using a rental generator. Installation of the warm gas lines in the tunnel is 80% complete.