IR FEL Monthly Report for August 1997

Navy IR Demo Contract WBS Elements

WBS 1 Project Management

August 1997 was the fourteenth full month for the IR FEL Demo project funded by the Navy.

Cost Performance Scheduling

We have expanded the discussion of cost performance/scheduling in this monthly report as the project nears completion.

The original project total available budget was $8,082k. As discussed in last month's report, a funds transfer was negotiated with LANL for $37,645 for an FEL modeling task, reducing the total available budget to Jefferson Lab to $8,044k. This month's assessment includes this performance and the cost of the work. Performance was taken under the Management account as part of the "contingency" pegpoint while the Optics account, where the work was performed, accrued the cost. The project was always fully scheduled.

The IR FEL Demo project through the month of August 1997 has a total of $7,789k (less SRF and the building) of performance scheduled. The work performed through the current period is $7,312k or 90% complete versus 96% scheduled. The actual costs accrued through August totals $7,358k. This results in a negative schedule variance of $477k and a negative cost variance of $46k.

As of the end of August 1997, $7,903k has been costed and/or obligated ($7,358k in actual costs and $545k in current obligations). The remaining unobligated balance is $179k. A plan is in place to fully obligate/cost these funds not later than September 30th. The cost for LANL support ($38k) has been included in the costs and performance quoted in the previous two paragraphs.

One month remains to accomplish the remaining scheduled work of $770k in the project's Performance Assessment "Earned Value System". This represents an increase of $51k per month over the July average of $619k.

Management

The FEL Project received $3.7M of Navy funding for the period Aug. 1997 to Sept. 1998 for the tasks of preparing the IR Demo for commissioning, commissioning the IR FEL, and initial design and procurement activities for the IR Upgrade. Receipt of this funding follows the signature of the second Navy-DOE Memorandum of Agreement for the IR Demo Project.

Scheduling activities are focused on carefully integrating the remaining installation tasks with the start-up of commissioning tasks. Installation tasks are being phased such that remaining installation tasks will have little or no impact on the first commissioning tasks which will proceed from the gun to injector cryounit to linac cryomodule to wiggler to recirculation arc.

Review and revision of the pre-proposals that were submitted last month for initial use of the IR FEL continued. Discussion was initiated with NREL on a possible collaboration on the use of the IR FEL for applications to photovoltaic materials. At month's end, final revisions were collected on the first set of IR FEL proposal summaries that were forwarded to the DOE-BES program office.

F. Dylla visited DuPont Experimental Station for an update on DuPont's proposals and plans for the polymer lab in the FEL User Facility.

Discussions are on-going with both DuPont and Armco with regard to their comments on the initial draft of a User Facility Agreement for the FEL user labs that would incorporate their equipment provisions for the polymer and metals labs, respectively.

Jefferson Lab was invited to co-sponsor a "Workshop on Fourth Generation Light Sources" that will be held at the Advanced Photon Source (Argonne, IL) on Oct. 28-30. The workshop will focus on the FEL technology and applications for deep UV and X-ray FELs.

The FEL project was presented in papers at the International FEL Conference in Beijing in August. The following papers were given by project staff:

"Status Report on Jefferson Lab's High-Power Infrared FEL" - C. Bohn

"Progress on the Study of Emittance Growth Induced by Transient Self-Interaction of a Bunch Entering a Bend" - R. Li

"Experimental Results from a DC Photocathode Electron Gun for an IR FEL" - D. Kehne

"Optical Modeling of the Jefferson Laboratory IR Demo FEL" - S. Benson

"Real-Time Transverse Emittance and Phase-Space Monitor" - J. Song

Congressman Bateman's Office requested an update on the current status of the FEL project. A telephone briefing to the Congressman's staff was followed by a brief written summary of the conversation.

A meeting of the ARC University Coordinating committee was held to discuss the final lay-out of the ARC Building laboratories. We were able to co-locate many similar activities between the four universities and Jefferson Lab, particularly laser/optics labs and materials analysis labs that will have obvious benefits to FEL users, FEL development and Jefferson Lab R&D activities. The ARC universities are making plans for moving into the ARC Building at the end of the calendar year.

We confirmed the attendance at the SURA/DOE Science and Technology Review (Sept. 17-19) of Steve Laderman, from Hewlett Packard Research Laboratories. Steve will be reviewing both the FEL program and the laboratory's relations with industry. In his position at Hewlett Packard, Steve oversees the company's interests at the Stanford Synchrotron Radiation Laboratory.

WBS 5.0 Instrumentation & Controls

Regarding instrumentation and control systems:

The bulk of the beam instrumentation mechanical devices are being installed or are on the shelf. 18 of the 25 stripline Beam Position Monitors (BPMs) are installed, none of the "button" BPMs have been installed since those vacuum chambers are not yet complete. All of the BPM cable assemblies are installed, these were purchased complete with terminations and cable labels. The electronics are being installed in the control racks. 10 of the 24 Optical Transition Radiation (OTR) beam viewers have been installed; of particular note these viewers use a 1.5 micron Al foil as the flag. This has proven to be problematic in the past but by using new tooling the foil is able to be stretched slightly ensuring a flat surface. All of the beam viewer cables are in place, some of the video cables still need to be terminated. The "Happek" devices are coming in under the original cost estimate so we are exercising the option to purchase the third unit. They will be here in early September for a trial fit-up with the stands in the tunnel.

In preparation for cool-down of the cryomodule the temperature diodes were wired-in and connected through the control system. This was the first complete test of the new server configuration, input/output controllers (IOCs) and network. The server computer (ITSserv) is still operational, this was brought over from the injector test stand to facilitate rapid startup of the drive laser systems and support RF commissioning. All IOCs have been installed and are operational. The servers denoting FEL1&2 are running fine. The controls network hub had a slight problem recovering after a scheduled power outage, this was quickly rectified. These start-up problems are expected and are being worked out.

Design work is centered on the Analog Monitoring System (AMS). The system prototype boards are working well, the system is running with flat response out to >20MHz local to the FEL building. The commercial unit used to transmit the analog signal from the FEL building to the Main Control Center (MCC) has a rolloff at 1 MHz (-3dB) (unfortunately). This will be sufficient for commissioning but may be considered for an upgrade in the future. The input buffer boards are out for production, the backplane boards have been delivered; these are four layer printed circuit boards with both a data and address bus. This backplane board was designed with the flexibility to also be used in drive laser, RF diagnostics, and beam instrumentation future applications. The multiplexer is common to both the AMS and the beam viewer video system (and the optics video). The chassis contains four 16 X 16 video crosspoint switches, these have wired-ORed outputs. The video system requires 64:16 and the AMS requires 128:16, the muxing system is designed to be expanded to 256:16 by simply adding the 64:16 building blocks. Another advantage is that the software drivers are common for both systems. This eliminates the additional load on the software group. The VME based driver is the same board that we designed for the Drive Laser Pulse Controller (DLPC), the interface between the DLPC VME board and the video muxes has been prototyped and is being used by the software developers. When the design is verified this will go out for production.

Work continues on the dump instrumentation and interlocks. Most of the parts are in-house, the final design is not yet complete. This will be finalized in early September and the required control chassis will be constructed.

The WWW site for the FEL Facility is progressing rapidly with individual channel assignments being added for the VME boards, and system layouts being added for the accelerator enclosure. The home page for the documentation and engineering can be found at http://www.jlab.org/accel/fel/documentation/evans/felbair1.html. This site is updated on a daily basis reflecting the ongoing installation activities. This site also serves as a database for information on spares and system failures.

The control and readout chassis for the 500 kV gun power supply is in fabrication, this will be installed and tested mid-September. This buffers the drive and readout analog signals for the control system, interlocks the HV to vacuum and provides a remote interface to the control system.

The PSS has been certified, the process will continue as the peripherals are brought on-line. The RF system will be connected to the PSS interlocks when the waveguide shorts are removed and the klystrons are connected to the SRF cavities, likewise the gun high voltage power supply will be connected after the gun bakeout is complete.

The Machine Protection System (MPS) design review was postponed due to personnel conflicts with the main accelerator. This will be held in September. The system installed from the Injector Test Stand is sufficient for beam operation through December when the average current is to be raised to 1 mAmp.

All of the vacuum system control cables have been pulled, the cable tray has had dividers mounted to segregate the high voltage cables from the balance of the cables. An additional cable tray was installed to correct for an under estimate in the loading of the 12 inch power tray. There was not proper clearance for cooling of the 535MCM main dipole cables. All of the ion pump power supplies are mounted as well as both of the vacuum control crates. The software controls are in the works, total system testing will begin in mid-September.

The DC power trim racks are being powered up and checked out. After the bake-out of the injector is complete, the magnets will be connected and field polarity checked. The two large box supplies are ready and waiting for magnets.

The access control hardware for the user lab safety systems is arriving and being checked out. Magnetic locks are being installed as well as the PLCs. The access and Laser Safety System (LSS) will be based on Smart Card technology. Each user and JLab employee requiring access to any of the laser areas will be issued a card. When any smart card is presented to a reader, the database will be checked for relevant information on safety training particular to a specific area, at that point the magnetic lock will be released and the persons name will be recorded as entering a given area. This will allow for easy access throughout the building without relying on administrative controls to prevent accidents.

WBS 7 Beam Transport

Among recirculation dipoles, the coils for the 180 degree dipoles, with three of four wound, are the only parts not on-hand. The reverse bend dipole hardware is at the assembly vendor for final fit-up. All eight optical chicane dipoles are completing magnetic measurement. They have passed all tests except three remain to be adjusted to meet the one hundredth percent uniformity of the field integral over the good field region. We are confident this specification can be met.

Quadrupole acquisition will be complete with delivery of two styles of Panofsky trim quadrupole (11 magnets), expected next month.

In the corrector area, three mu metal styles have been delayed in manufacturing by about a month by manufacturability questions but have restarted. The three styles of air core correctors were detailed, checked and are near sign-off.

In the vacuum system, the optical chicane chambers were completed and welding started on the chambers for the arcs around the reverse bends while the parts for chambers for the 180 degree dipoles were completed.

Design of all stands and girders was completed.

Installation activity continued to concentrate on the injection line and its dump as the vacuum pipe was closed and its conditioning for high vacuum started. More enclosure cable tray was installed as room in the existing tray was exhausted.

Overall summary: 180 degree dipole completion and the measurement of all remaining dipoles and correctors remain on the critical path. Manufacturing chambers is now off critical path. From another point of view, we now have great confidence in meeting beam transport magnetic element requirements. Measurement of the batch of DW dipoles proved that the spectrometer-dipole-like specifications can be met, after some adjustment, with magnet sets of the style we are building. Manufacturing the dipoles according to project specifications and proving it with appropriate measurement slowed the installation process and forced schedule slip, but the slip in installation of the remaining magnets will not impact the start-up of commissioning.

WBS 8 RF Systems

In the Injector, zone 1, the RF systems for the buncher and quarter cryomodule are nearly ready for RF testing into waveguide shorts. They will be operated first in local control and then remote under software control. The software and low level RF racks for the Injector have been used to test the phase stability of the drive laser. In the Linac, zone 2, testing of the low level RF control system was halted to concentrate on the Injector zone.

After repeated calls to the vendor concerning the failed spare 50 kW klystron, we are still waiting for directions for additional testing or return instructions. Both Hipotronics and the 225 kW variable DC power supplies were received this past month. Both units sustained shipping damage. The first unit was repaired, installed, and preliminarily tested. The second unit will be repaired after the first unit is load tested, so that all repairs and any changes can be made at the same time. Except for a small amount of insulation in a presently unused zone, the Master Oscillator installation is complete. The new Divide by 40 chassis was installed and preliminary tests were started on the phase stability of the drive laser system. The location of the buncher water skid is being moved again due to space requirements of other equipment. It is to be connected and tested next month.

WBS 9.2 Injector Move

The vacuum system between the gun and the injector dump was completed, installed, and ready for leak-check by month's end. The design of the upstairs stand for the drive laser transport was completed. The stands for the mirror cans downstairs were received and installed. Two of them had to be modified slightly to account for a design error. Two of the transport cans were installed. The high voltage power supply was tested in air with just the power supply in the tank and then with the elbow to the gun installed. The former test was quite successful but the second test indicated that some work reducing corona in the elbow was necessary. The gas system for the tank was mostly installed by month's end. Substantial work was completed on installation of the RF systems. All three systems were installed with the exception of some waveguide and a great deal of the wiring and checkout was completed by month's end.

WBS 9.4 Wiggler

The wiggler girder was installed and aligned. Pulsed wire measurements of the girder indicated that the four quadrupole magnetic centers were well aligned with each other. The trajectory indicated by the measurement was very close to that calculated from the STI Optronics magnetic measurements indicating that the wiggler was not damaged in shipping. Test pieces for the wiggler vacuum chamber were electron beam welded successfully.

WBS 9.6 Optics

This month we completed assembly of the downstream optical cavity assembly (save installation of the pellicle viewers) and are nearly finished with the upstream assembly. We successfully indium brazed a test mirror in a mirror holder without its cracking. We tested the LVDT readouts for the gimbal mounts, finding there is negligible backlash in the yaw plane, and that the LVDT had sufficient resolution to assist us in maintaining the cavity mirrors orientation. We learned that our sapphire mirrors (coated for 3 microns by Research Electro-Optics (REO)) have radii of curvature longer than spec (0.2%). A test set of mirrors made by Rocky Mountain Instrument met specifications (> 99.7%) for reflectivity. This is a promising development, since RMI is making our first light mirrors. The FEL optical transport line is complete up to the Optics Control Room on the second floor. The stands for the transport line on the second floor are complete, and the pipes have been cut to length and the flanges welded to them. Design for the mirror cassettes is complete and in Procurement. We received the complete order for the Brewster output windows for the User labs (six plus four spares). We've built power supplies for the vidicon cameras that will be used for the cavity alignment, and studied the linearity of the Cohu CCD cameras used for both the optical and electron beam transport viewers. The drive laser's delivery optics are complete to the Brewster window in the Clean Room. A He-Ne laser collinear with the drive laser beam is used to align the transport optics on the ground floor. We hung one mirror can and modified two stands that were designed incorrectly. The drive laser is undergoing checkout, and is operating nominally.

Injector, SRF, Facility, and Other Activities Outside Navy IR Demo Contract

INJECTOR TEST STAND

WBS 3 - CRYOMODULE

Linac Cryomodule

The linac cryomodule was aligned and successfully cooled to 2k.

Warm Windows

The cryounit of the IR FEL's injector requires higher power warm RF windows than does the standard CEBAF cryomodule. Specifically, the requirement is for 50 kW windows in the cryounit, which is needed to drive a 5 mA cw beam current through the superconducting RF cavities. This is an order of magnitude higher than the requirement for the CEBAF cryomodule warm RF windows.

As currently installed in the FEL Facility, the cryounit is configured with ceramic warm RF windows that have been qualified to 10 kW of cw RF in full reflection. This reduced power limit is a result of problems with the thermal control of the warm windows which is driven by excessive dissipated RF power in the ceramics. These windows have been run with cw RF power up to 50 kW traveling wave in our Resonant Ring Test Facility and run at 10 kW full reflection in the cryounit in the Injector Test Stand cave. These power levels are appropriate for supporting first-light IR FEL operations which are projected to continue well into Spring 1998.

The root cause of the warm window limitations has been the RF performance of the ceramic material used in the windows. The material originally used was developed to support the cold RF window production for CEBAF and had demonstrated appropriate warm RF characteristics at that time. Changes in material performance since that time have resulted in a requirement to develop a new supply of ceramic for the present application. This has been done and windows are now in production using this material. Three windows have been produced with this material and tested up to 50 kW cw traveling-wave power in the Resonant Ring Facility. The thermal performance of these windows has been greatly improved and is acceptable for FEL operations. Additional ceramics are now being procured and will be used to produce four windows for full-power qualification.

Two additional efforts are being pursued in parallel to ensure a robust solution to the warm window requirement. The first is a collaboration with Northrop Grumman that has resulted in a new design using a BeO window material in a two-piece flange assembly. We completed the first of these assemblies on 12 Sep 97 and are evaluating it now. The second effort is a new design being developed in-house. It incorporates a water-cooled waveguide mounting of a ceramic window and has potential for even higher-power applications. All required parts for a prototype assembly are in procurement and are due to be received in the next two weeks.

The requirement for the full 50 kW RF windows to support operations is coupled to kW-level operation with 5 mA cw electron beam, which will probably begin not earlier than May 98. Operating plans for CEBAF and the IR FEL accelerator include a shutdown in Jan 98, at which time there will be opportunity to change the warm windows on the cryounit. Production and qualification of warm windows are therefore scheduled to support a Jan 98 changeover, and sufficient in-house resources are in place to support the schedule. The windows will be qualified on the Resonant Ring Test Facility and a test fixture being powered by one of the 50 kW klystrons in the FEL Facility. This test fixture is already installed there.

WBS 2 -- BEAM PHYSICS

Additional simulations of the beam dynamics from photocathode to wiggler were completed. These simulations concern bunch charges for first light (60 pC) and "zero" current. In particular, the beam dynamics were assessed at these lower bunch charges given the machine setup for full-power runs, e.g., 135 pC bunch charges. The 135 pC settings appear adequate for both cases; the 60 pC case actually looks better with the 135 pC settings than does the 135 pC case itself. Code results indicate we will need to be careful about setting the first solenoid (to 280 G) because the results are sensitive to this setting, degrading rapidly as the solenoidal field is increased above 280 G. As a matter of principle, we will also need to check stray fields after the cryounit to ensure they do not interfere significantly with the very weak fields of the quadrupole magnets on the injection line.

Considerable modelling of the longitudinal-phase-space experiments performed in the Injector Test Stand was done, and the results were summarized in a paper entitled "Experimental Results from a DC Photocathode Electron Gun for an IR FEL" that was presented by D. Kehne at the FEL Conference in Beijing. The longitudinal measurements are noteworthy for their general agreement with PARMELA, though there are differences in certain details of the longitudinal phase space.

The procedure for establishing RF phases of the cavities in the cryomodule to facilitate energy recovery underwent further investigation, culminating in a technical note entitled "Fine Phasing for the Cryomodule Using the Energy Recovery Dump". Modelling also proceeded to support development of detailed ("fine") test plans for commissioning the injector, with the basic goal being to identify the diagnostic which is most sensitive to each parameter of the bunching/acceleration devices.

Simulations were done to aid in establishing a procedure for transverse emittance measurements using the quad-scan technique in the wiggler line (between the two chicanes), before the first recirculation arc, and in the backleg. Multimonitor measurements in the backleg using the 6 optical transition radiation (OTR) detectors, and in the wiggler line using the 5 OTRs, were also done. These simulations support the development of test plans for the coherent synchrotron radiation (CSR) experiments. The foundational test plan for measuring the emittance before and after the first recirculation bend is complete, and we are working on the test plan concerning the bunch decompressor. Concerning theoretical developments, R. Li presented a paper at the FEL Conference in Beijing entitled "Progress on the Study of Self-Interaction of a Bunch in a Bend" which describes new analytic results concerning noninertial forces that arise off-axis from the design orbit.




WBS 4 -- IRFEL COMMISSIONING/OPERATION

As one of the preparatory steps for commissioning the IRFEL, performance integration plans were drafted for RF systems, magnets, and electron-beam diagnostics. In essence, these plans identify both the associated tasks and manpower requirements/skills. In general, they are based on modelling results like those mentioned above under "Beam Physics", since simulations are generally used to specify hardware requirements and tolerances.

A spinoff from considering the performance integration plans is a list of software requirements for high-level applications. In some cases, this software is either already available from the Injector Test Stand or nuclear-physics machine, or under development. However, some of the high-level software had not yet been programmed for development, and in these cases we made plans to rectify the situation.

The installation and commissioning schedules were developed up to the first-light milestone. We are presently considering whether to plan for circulating a low-average-current beam all the way around the machine prior to Christmas. Advantages for doing so include ensuring all remaining installation activities are completed this fall and identifying hardware problems prior to the scheduled January shutdown so they can be rectified during the shutdown. Disadvantages include postponement of detailed experiments on parametric sensitivities of machine settings and on CSR until February. Although we have yet to make a final decision, we are leaning toward adopting this plan in view of its advantages.

Difficulties obtaining consistent field profiles among the optical-chicane dipole magnets now appear to be largely resolved. The profiles are very sensitive to the locations of the field clamps. Consequently, with the aid of differential field measurements in the Magnet Measurement Test Stand, we determined the necessary field-clamp locations on each of the eight dipoles and pinned the clamps in place. We will soon release the first set of four optical-chicane magnets for installation in the FEL Facility in early September. Our experience with these dipoles has resulted in a procedure for checking out and adjusting the other dipole types that will follow, and therefore we are hopeful that certification of these remaining dipoles will proceed more expeditiously.

Facility

The facility is essentially complete. There is still some punch list item activity going on. The only major open item is installation of an electrical relay which will permit the elevator to pass code and be operated normally. Negotiation of final cost will occur after the punch list is complete.

Upcoming Meetings and Reviews

SURA Science and Technology Review, Sept. 16-17, 1997 (Jefferson Lab)

Construction Project Close-out Meeting, Oct. 2-3, 1997 (Jefferson Lab)

Scientific Opportunities for Fourth Generation Light Sources, October 27-29, 1997 (Argonne National Lab)