Management
August 1998 was the thirteenth month for the
$3.7M IR Demo Upgrade and Commissioning project. Cost and schedule
performance are described in the accompanying Performance Assessment
report by Gordon Smith. Highlights for the month include: (1)
successful operation of the linac in the recirculation mode with
cw currents up to 0.6 mA. (2) demonstration of cw lasing with
energy recovery at low power (6W) and (3) hosting of the 20th
International FEL Conference and FEL Users Workshop in Williamsburg.
CA 221: Scaleable Optical Cavity
Work continued to finalize the mounting of
the high power 3 micron optics. By month's end the mirrors had
been successfully brazed into their holders with additional stresses
and resulting distortion within tolerances. The mirrors were
then packed and sent to China Lake for final confirmation that
they meet all specs. Assuming this is true, the high power 3
micron optics are now ready for installation in the FEL. Results
of the testing will be available in September. In optical modeling,
J. Foley, our visiting scientist was able to get the GLAD optics
code operational with an upgraded version of the software running
on a PC under Windows NT. He successfully set up a first test
of the display capability with parabolic mirrors in a rooftop
configuration which might be useful for 1 micron operation at
high power. The goal of this effort will be to determine the
tolerances associated with using a system of this kind as well
as the rejection capability of higher order cavity modes. In
the User Labs mounting of the mirror cans was completed in Lab
3 in preparation for alignment of the scanning systems for the
metal processing system built by the LPC Metals Working Group.
CA 321: Upgrade Cryomodule System
Cavities IA017, IA018, IA074 and IA076 were
subjected to a series of three 2K RF tests to determine if they
did have increased amounts of hydrogen from rework procedures.
This hydrogen can precipitate out during cooldown and increase
the cavities surface losses and increase the heat load to the
cryogenic bath. Cooldown rates in the FEL will be slower then
that of the typical vertical test rate and can cause this hydrogen
precipitation (Q-disease) to occur. This series of tests showed
that two of the four cavities were sensitive to Q-disease at 50K/hr
cooldown rates. These two cavities were produced from the same
material (same niobium vendor). We suspect that this material
which is in four of the eight cavities slated for the second module
assembly will all behave the same and all four will need vacuum
baking to 900°C for 4 hours. The furnace is being prepared
for cavity treatments and the cavities are being mechanically
measured for preparation.
A teststand dedicated for FEL pair testing
was cleaned, baked and vacuum leak checked for the start of the
assembly process. Plans are to start assembly of the first cavity
pair that was not sensitive to Q-disease (IA074 and IA076) as
soon as the cleanroom comes back on line from upgrade construction.
HOM loads for all eight cavities were fabricated, tested and assembled. Helium vessel modifications are underway to accept the FEL style HOM loads.
We inspected all shield assemblies. Minor
repair was required as a result of shipping damage. This repair
will be done in house. HOM loads were qualified for first cavity
pair.
CA 421: Commissioning Preparations
This account has been closed to further obligations
since October.
CA 431: IR FEL Commissioning
The month began with a deteriorated photocathode. Efforts to
resuscitate the cathode via a combination of high-voltage processing
and heat treatment ultimately resulted in a cathode suitable for
operation at 330 kV, and subsequent commissioning involved operating
the gun at this nominal voltage, as opposed to the usual 350 kV.
Commissioning efforts focused on recirculation, energy recovery,
and lasing with energy recovery as we set out to achieve as much
as possible prior to the FEL Conference that we hosted in Williamsburg,
VA during 16-21 Aug. 98. We began by restoring lasing at low
duty cycle with complete recirculation and energy recovery. While
in the energy recovery mode, we doubled the drive laser operating
frequency to 37 MHz and lased in the pulsed mode with a macropulse
current (2 mA) that was twice the supplied current limit in the
non-recovered mode (1 mA). We continued by running electron beam
in the recirculation mode with the goal of improving beam transmission
and beam quality through the recirculation and energy recovery
hardware. Ultimately we achieved a maximum cw current in the
energy recovery mode of 0.6 mA, and we had several periods of
testing cw lasing at low laser power (6 W cw maximum).
Operations ceased on the evening of 13 Aug. 98 when an arc occurred
in the gun during high voltage processing. The arc caused a vacuum
leak which was subsequently localized to a flange in the high-voltage
stack. Consequently we began implementing a plan for refurbishing
the gun that will enable resumption of FEL commissioning in mid-September.
During the down-time, the FEL Operations and Safety Procedures,
an annually updated document, was rewritten and coordinated through
the cognizant individuals in the Accelerator Division.
FEL INSTALLATION
Installation and maintenance highlights in August included:
With regard to the gun refurbishment: removal of the cathode ball
and anode plate for minor repolishing of blemishes due to arcing
damage; completion of new, higher conductance getter shields;
replacement of getter and ion pumps, and commencement of numerous
minor modifications to external hardware.
Completion of hook-up and check-out of the sextupole magnets;
all the magnetic elements are now installed in the FEL. Installation
and leak check of the beam scraper.
Completion of the 3 µm high-power optics; they subsequently
were sent to China Lake where the figure and optical loss will
be measured.
Commencement of installation of the Analog Monitoring System (AMS);
software control of the AMS oscilloscopes was used during this
month's operations.
Installation and alignment of mirror cassettes in User Labs 4, 5 and 6; initial testing of DuPont-donated equipment for polymer processing was started.