Management
December 1997 was the fifth month for the
$3.7M IR Demo Upgrade and Commissioning project. Cost and schedule
performance are described in the accompanying "Performance
Assessment" report by Gordon Smith. Summary of the technical
progress of the remaining three open cost accounts is given below.
CA 221 Scaleable Optical Cavity
The efforts of the Optics Team this month
was devoted to alignment sensitivity and reproducibility measurements
on the optical cavity assembly installed in the IR Demo. The
results of these measurements have immediate impact on the first-light
commissioning effort that begins in February; however, these results
also affect the design options being considered for the scaleable
optical cavity.
CA 321 Upgrade Cryomodule System
The first eight cavities were re-processed
and readied for testing. Processing/assembly/testing cycles will
continue until cavity pairs are needed for cryomodule assembly
late in the fiscal year to gain more process experience and improvement.
Vacuum tests were successfully completed on the three inch ID
gate valves used in cavity assembly. Four so-called "dogleg"
power couplers with windows have been completed for testing next
month. These re-designed coupler assemblies have shown considerably
less (~10e-3) field emission in prototype tests than the traditional
straight-through coupler design. One dog-leg coupler assembly
was prepared for cryo-vacuum tests next month with an indium-sealed
vacuum plate to simulate make-up to the helium vessel.
CA 421 Commissioning Preparations
This account has been closed to further obligations
since October. Remaining cost obligations (on corrector magnets
and the Analog Monitoring System) should be closed out in January.
CA 521 IR FEL Commissioning
The focus of the month was getting tune-up
beam to the straight-ahead dump, a goal that was completed on
21 Dec. 97, on which day we succeeded in depositing a 38 MeV/c,
2 µA electron beam on the dump. Following that achievement,
we ran the beam momentum up to 48 MeV/c to verify consistency
of the momentum measured in the first optical chicane with that
inferred from the gradient settings on the control screen. Lastly,
we ran the charge per bunch up to 60 pC in the injector and measured
the transverse emittance using the multislit monitor. The result
was high, in excess of 20 mm-mrad versus the expected 6 mm-mrad.
Preliminary indications (from the necessary magnet settings)
are that the axes of the cryounit cavities are significantly misaligned,
a situation that we will look into and correct, if necessary,
in January. (Note: the problem was traced to a partially open
valve within the cryounit which was corrected. Alignment checked
out within tolerance).
In summary, our 1Q98 commissioning goals were
achieved. Moreover, the beam delivered to the straight-ahead
dump meets the requirements for the GEN polarized-target irradiation
experiment that will be installed in early 1998 to support the
nuclear physics program at Jefferson lab. The 38 MeV/c momentum
is also the required value to support first light.
FEL INSTALLATION
Installation highlights in December included:
Completing all hardware installation from
the photocathode to the straight-ahead dump in preparation for
the commissioning activities described above. Spare CEBAF air-core
correctors were installed pending receipt of the actual air cores
from the vendor (now slated for January). Installation of the
optical cavity (minus the mirrors) was completed. The optical
transport line was completed and checked out under vacuum.
Making further progress toward installing
the recirculation arcs. Fit-up of the arc vacuum chambers was
completed. All of the dipole magnets have now been released for
installation, with the exception of the two 180-degree dipoles.
Measurements of core field and field uniformity along the beam
path of the first 180-degree dipole are within tolerance. A defect
in the coils of the second dipole is being corrected. Its reassembly
is slated for late Jan. 98. The large-diameter probe for the
sextupole measurements was tested, and four of the eight trim
quads were received.