Management
Highlights for the month: (1) attainment
of 300 watts of cw laser power with energy recovery of the 1.6
mA drive curent; (2) before commissioning operations ceased on
Dec. 15, a total of 180 conlombs of charge was delivered from
the photocathode.
A meeting of Maritime Technical Advisory Committee
(MTAC) was held on Dec. 9 to review progress with the FEL and
plans for a potential collaboration with Northrop Grumman on the
FEL Upgrade.
Preparations continued for January's visit
to the lab by Secretary Richardson (on Jan. 12) and DOE for the
lab's presentations at the Jan. 19-21 BESAC panel on "Novel
and Coherent Light Sources."
The Jefferson Lab FEL project received a 3-month,
no-cost extension in our current Navy/DOE MOA for the commissioning
milestone (from Dec. 31, 1998 to March 31, 1999).
CA 321: Upgrade Cryomodule System
Pair number AIA074/76 was vertically tested with good performance.
The total gradient less any field emission was 10.3 MV. Gradient
limitation for both cavities was a quench at 13.5 and 18 MV/m,
respectively. The next step is to assemble tuners and instrumentation
and then complete the helium vessel.
Pair number IA004/006 was vertically tested with good performance.
The total gradient less any field emission was 8.8 MV. Both cavities
reached a quench as their final limitation. The next step is to
assemble tuners and instrumentation and then complete the helium
vessel.
Pair number IA017/18 is in teststand and waiting vertical test.
Pair number IA021/23 is leak checked and waiting teststand insertion.
IA076f
IA074h
Note: Ia004/6 data was not complete and will be available in January
report.
CA 521: FEL COMMISSIONING
Commissioning of the recirculation loop in
the presence of cw lasing continued through 15 Dec 98 to the point
of reproducibly generating ~200 W cw laser power upstairs in the
Optical Control Room at cw average currents ~1.5 mA. Best performance
was 211 W cw upstairs (corresponding to about 300 W cw out of
the FEL proper given roughly 40% losses in the optical transmission
line) with 1.6 mA current. At that point we were experiencing
a trip of one of the beam-loss monitors indicating beam scraping
in the reinjection region, i.e., near the end of the recirculation
loop. A second limitation also emerged, namely heating of the
infrared detectors in the waveguides of the accelerating cavities
that led to persistent trips in one of the cryomodule cavities.
Preliminary off-line measurements indicate that the detector itself
is sensitive to microwaves. A copper screen with about 1 mm mesh
size removes all the measurable RF response at 19.5 GHz and below,
and still allows 60-65% of the IR signal to be detected. Consequently
we are planning to install a screen over each IR detector in the
cryomodule during the January down.
On 15 Dec 98 we lost the quantum efficiency
of the cathode and decided to begin the process of replacing it
with a new one. Plans are to resume running on or about 25 Jan
99. The present cathode proved to be quite resilient in that
it delivered roughly 180 C of total charge during its operational
lifetime.
FEL INSTALLATION
A comprehensive list of tasks for the January down was compiled and prioritized. "Must-have" tasks to aid in expeditiously achieving kW-level operation were compiled based on commissioning experience to date, and they include:
- Repair or rebuild the cesiator for the gun.
- Install a new photocathode in the gun.
- Provide 74.8 MHz operation in the Drive Laser Pulse Controller (to get ~4.5 mA cw current with 60 pC bunch charge).
- Resolve the IR detector trip problem (see FEL Commissioning above).
- Add a post-raster viewer and temperature sensors in the energy-recovery dump line (to permit quick, unambiguous setup of the dump line).
- Put a hole in the post-cryomodule viewer (to pass the accelerated beam unperturbed and thereby aid in observing the recirculated beam).
- Install two new rf cavities for path-length measurements.
- Calibrate the gradient of the buncher cavity.
By Christmas break, most of these tasks had been initiated. Numerous other tasks of lesser priority had also been initiated. One example is starting construction of a new viewer that will be installed just downstream of the scraper in the first arc. That viewer will permit quick centering of the electron beam in conjunction with changing its energy, and it will permit unambiguous observation of the effect of the scraper (which to date has not yet been used).