Management
January 1998 was the sixth month for the $3.7M
IR Demo Upgrade and Commissioning project. Cost and schedule
performance are described in the accompanying "Performance
Assessment" report by Gordon Smith. Summary of the technical
progress of the remaining three open cost accounts is given below.
CA 221 Scaleable Optical Cavity
All work in this area is in connection with
the commissioning of the FEL.
CA 321 Upgrade Cryomodule System
The procurement for the cryounit shields was
placed and delivery is expected on schedule. Additional procurements
are limited to warm window components, beam line valves (4), and
HOM absorber ceramics. The modification of existing CEBAF components
for FEL configuration is underway in the Jefferson Lab machine
shop. Work continues on extending the performance of the cavities
and will continue until performance meets anticipated fundamental
limits or schedule constraints dictate.
During the Shutdown period the 1/4 and full
cryomodules were warmed to room temperature. The 1/4 cryomodule
was inspected for potential beam line obstructions. A valve was
found partially closed and was opened. Additionally, new ceramic
warm RF windows were installed on the 1/4 cryomodule.
CA 421 Commissioning Preparations
This account has been closed to further obligations
since October. Remaining cost obligations (on corrector magnets
and the Analog Monitoring System) should be closed out in January.
CA 521 IR FEL Commissioning
Jefferson Lab's liquid helium plant underwent
a scheduled, thorough refurbishment during January. Consequently
there was no commissioning of the FEL with electron beam. Instead,
the month was devoted to preparing the machine for first light
(see the Installation summary below) and understanding the data
collected during the December run. Restart of commissioning with
electron beam is scheduled for 5 Feb. 98. (Note added in proof
on 19 Feb. 98: Restart turned out to be unsuccessful due to difficulties
with the electron gun. The gun is being refurbished, and restart
is presently envisioned to occur on 5 Mar 98.)
The photocathode gun was refurbished to repair
a slow vacuum leak. It was successfully baked, processed with
voltage up to 410 kV, and heat treated, and a cathode was made.
Considerable work went into installing and
configuring the Machine Protection System in preparation for running
1.1 mA average current as is necessary for first light. This
effort required an interplay between modeling the dump lines and
electronic hardware configurations to establish set points and
time scales for guarding against burn-through that would occur
in the presence of hardware failures. At month's end most of
the requisite hardware was either installed or ready for installation,
and most of the set points had been established. The task was
slated to be completed in mid-February.
As regards the anomalously large injector
emittance associated with 60 pC bunches that had been measured
in December, the cryounit was discovered to have an internal valve
that was not completely open, subtending into the beam aperture
a distance somewhere between 0.95 cm and 1.1 cm. During the December
runs, this necessitated steering around the blockage, and presently
it is thought that the concomitant beam "misalignment"
was responsible for the observed distortion of the beam's transverse
phase space. Simulations of an offset beam with PARMELA lent
additional evidence to this conclusion.
The development of a self-consistent simulation
of coherent synchrotron radiation (CSR) progressed to the point
of modelling the first optical chicane in the FEL, resulting in
a predicted CSR-induced emittance growth in this chicane that,
with the planned bunch charges, would be too small to resolve
with the quadrupole-viewer measurement technique. This result
is favorable for lasing in that it suggests beam quality will
be sufficiently preserved. Of course, we will measure emittances
as we set up the machine. Modelling of the first recirculation
arc is pending.
FEL INSTALLATION
Installation highlights in January included:
Two ceramic warm windows rated to 40 kW of
RF power were installed in the cryounit.
At the beginning of the month it was found
that two of the eight klystrons for the cryomodule could not reliably
be powered to 8 kW, the value needed for first-light electron
beam. They were replaced, and we now have the necessary bank
of eight 8 kW klystrons.
The first set of data from the Magnet Test
Stand for the first 180-degree (DY) dipole magnet was completed
and is in review. The vacuum chambers for both 180-degree dipole
magnets are ready for cleaning and installation. The repaired
coils for the second DY magnet were received from the vendor,
and in-house refurbishment of this magnet was started. The last
DV magnet was installed and the alignment checked. The recirculation
bends are now essentially complete minus the 180-degree magnets
and chambers, the trim quadrupoles, and the sextupoles. The high-field-quality
air-core correctors for the straight-ahead machine were received
from the vendor, and they are in the Magnet Test Stand for characterization
as a family. Upon restarting FEL commissioning in February we
will continue to use the spare CEBAF air cores already installed,
but we will replace them prior to attempting to achieve the high
electron-beam quality needed for first light.
Engineers from Svetlana visited and personally
tested the troublesome spare 50 kW klystron. It would only make
20 kW before failing and is therefore being returned to Svetlana
per their instructions.
The alignment of the cryounit and its constituent
cavities was checked and found to be accurate within about 1 mm,
but an internal valve was discovered not to be fully open. This
may solve the alignment problem that was found during commissioning
in December (see detailed comments in the commissioning section
above).
The straight-ahead dump line was reconfigured
to accept the target chamber required for irradiating GEN targets
in mid-February to support the nuclear-physics program.
Work continued in installing and setting up
the optical systems for lasing. Tests of the alignment HeNe's
suggested it would be advisable to modify the telescope mounts
and the pellicle alignment registration. The drawings were modified
and changes submitted to the shop. The software for the monochrometer
was successfully operated. FEL spectra can now be directly read
in EPICs.