Management
July 1998 was the twelfth month for the $3.7M
IR Demo Upgrade and Commissioning project. Cost and schedule
performance are described in the accompanying Performance Assessment
report by Gordon Smith. Highlights for the month include: (1)
generation of 311 watts of cw 5 micron FEL light (a new world's
record for FELs); (2) demonstration of electron beam recirculation
and energy recovery while lasing at low power. All hardware components
and operational modes of the machine have now been exercised.
A draft extension of the contract for the period October 1, 1998
to March 30, 1999 was forwarded to the DOE Site Office and Navy
Program Office during July for comments. The extension would
allow us time to continue processing of SRF cavities for the second
FEL module and delay final assembly of the module until we have
reached the point of diminished returns on cavity performance.
Since the second module is not needed for a period of at least
a year, the delayed assembly would yield a higher performance
module. This module would continue to serve as a useful testbed
of processes for the CEBAF Energy Upgrade and as a hot spare for
both the CEBAF accelerator and the FEL linac.
CA 221: Scaleable Optical Cavity
This month we tested the high power outcoupling
mirror for 5 microns with 90% reflectivity. This outcoupler was
used for the new 311 watt cw power record that was obtained during
FEL commissioning. John Foley, an expert in optics modelling
and design from Mississippi State, joined the FEL team in July
for a 6-month sabbatical visit. Dr. Foley began his task of modelling
our present design for scaleable optical cavities for the Demo
FEL and consideration of potential alternative designs that might
have performance and/or reliability improvements.
CA 321: Upgrade Cryomodule System
We received final three cryogenic shields
for the upgrade cryomodule; completed all remaining HOM load braze
assemblies and installed four ceramics to support first cavity
pair assembly. HOM loads will have final RF characterization completed.
CA 421: Commissioning Preparations
This account has been closed to further obligations
since October.
CA 521: IR FEL COMMISSIONING
Several commissioning tasks were done during the first week of
the month. These included, for example: checking the magnetostrictive
tuner for one of the cryounit cavities; running the cryomodule
cavities at their peak gradients; doing lasing studies with both
cw and pulsed beam; and replacing the outcoupling mirror in the
optical cavity with a 90% reflective mirror to deliver higher
power (the original mirror was 98% reflective, as inferred from
the laser pulse profile, and in particular the short fall time
at the end of the laser pulse).
On 9 July 98 we lost the photocathode due to arcing and vacuum
activity near 350 kV. Recesiation did not help; therefore, we
decided to replace the cathode. Mid-month activities centered
on restoring the gun, including changing out the photocathode
wafer. The ultimate result was that, despite successful high-voltage
processing to near 500 kV, we had difficulty holding off voltage
beyond 335 kV after cesiation. Consequently we operated the gun
at 330 kV, lower than its nominal operating voltage of 350 kV.
Despite the difficulties with the gun, by month's end we had achieved
three notable accomplishments: (1) recirculating pulsed beam all
the way around the recirculation loop while recovering energy
from the macropulses (which means beam was taken through the entire
machine), (2) lasing with this beam while maintaining energy recovery
from the macropulses and keeping the beam squarely on the viewer
in the energy-recovery dump, and (3) lasing into the straight-ahead
dump to achieve 311 W cw.
FEL INSTALLATION
Installation highlights in July included:
Completing installation of all eight sextupole magnets and air-core
corrector magnets in the recirculation arcs, adding neutron shielding
to the straight-ahead dump, wrapping mu-metal where possible through
the recirculation loop to screen the Earth's magnetic field, installing
beam-loss monitors along the recirculation loop, and hooking up
most of the back-leg diagnostics.
Installation and alignment of the optical cassette can to the
polymer roller assembly in Lab 1 and putting the transport line
to Lab 1 under vacuum; completion of the electrical hookup to
the large roller assembly and near completion of the electrical
hookup to the web roller; verification of the ability to operate
two labs at once by inserting a 50% mirror in Lab 1 and showing
that a surrogate HeNe laser beam in Lab 3 was unaffected except
in intensity.
Replacing the outcoupling mirror in the optical cavity with a 90% reflective mirror.