The near completion of the recirculation loop. Installation of the east arc was essentially
completed, including placement of the second 180-degree dipole magnet. Basically all that
remains to be installed are some small corrector and trim magnets, the sextupole magnets (likely to
be "last in", sometime in July), and the beam scrapers.
High-power rf testing of warm ceramic windows. The maximum rf power achieved by the
klystron during these tests was 37 kW, all of which was successfully transmitted through the
windows. Additional tests are planned for June.
|