MEMORANDUM

To: Distribution

From: F. Dylla

Subject: Monthly Report IR Demo FEL Upgrade and Commissioning Project, October 1997

Date: November 24, 1997

Management

October 1997 was the third month for the $3.7M IR Demo FEL Upgrade and Commissioning project. Cost and schedule performance are described in the accompanying "Performance Assessment" report by Gordon Smith. Four cost accounts with appropriate task identification and earned value for task completion were established for the project. A summary of the technical progress of the four cost accounts is given below.

CA 221: Scaleable Optical Cavity

R5 Activity

Discussions were held with NAWC personnel regarding optics requirements and the resulting derived coating specifications for mirrors. NAWC has agree to assist in the calculation of mirror reflectivities in the R5 geometry at 1.6 microns using existing codes and assuming hafnium oxide/silicon dioxide stacks. They will also look at possible alternative materials. We also held a vendor visit to Alpine Research Optics to discuss issues regarding fabrication of R5 mirrors. Preliminary discussions were held with our own designers on establishing the R5 cavity within the physical constraints established by the magnets and vacuum system as they now stand.

CA 321: Upgrade Cryomodule System

Four cavities were prepared, processed and tested for the upgrade cryomodule system. Incremental improvements are being made to cavity processing techniques as cavities for the upgrade cryomodule are being tested. The process changes and resulting effects are being documented. The cavity processing schedule allows time for several cavity processing cycles before final selection for cryomodule production.

A talk was presented by J. Mammosser and J. Preble on the Cryomodule Production Process at a Virginia Beach meeting of the Society for Engineering Management.

CA 421: Commissioning Preparations

Remaining activities in this account include: (1) the final measurement in the arc dipole magnets; (2) the completion of the delivery of the corrector magnet purchase and (3) receipt of the final components and testing of the analog monitoring system.

CA 521: IR FEL Commissioning

After modifying the high-voltage transmission line for the gun to improve its stand-off voltage and SF6 seal integrity, and then successfully reinstalling it, we conditioned the gun to the required voltage for first light. High-voltage conditioning proceeded rapidly, as has been the case in past attempts. We then ran beam at 350 kV from the gun through the buncher cavity to a viewer assembly just upstream of the injector cryounit. The buncher was operated at its nominal power loading of 2 kW. The drive laser in its final configuration ran to the required level of performance in these tests. We now await completion of SRF and RF commissioning of the cryounit before continuing to move electron beam down the injection line.

SRF commissioning of the injector cryounit began the last week of October. The exit cavity was operated at gradients up to approximately 9.5 MV/m until waveguide-guard vacuum trips ensued. SRF commissioning activities were halted and leak-testing began. On 30 Oct. 97, leaks were found at the interface seal for the warm window. The cryounit was then warmed up to allow removal of the warm-window assemblies and installation of new seals. Cool-down was slated for (and accomplished on) Tuesday, 4 Nov. 97.

FEL INSTALLATION

Installation highlights for October are:

The injection line from photocathode-gun assembly to injector dump is now fully installed and ready for commissioning activities. All components for the drive laser assembly and drive laser transport have been completely installed, aligned and tested for operation. Shielding for the injection-line dump was put in place.

The optical chicane vacuum chambers were replaced after they were removed for a minor modification needed for fit-up of BPM assemblies. Final assembly of the wiggler vacuum chamber within its supporting frame was completed.

Considerable progress was made installing the transport lines leading to the first-light and recirculation dumps. The dumps themselves are installed.