Management
September 1998 was the fourteenth month for
the $3.7M IR Demo Upgrade and Commissioning project. Cost and
schedule performance are described in the accompanying Performance
Assessment report by Gordon Smith. This is the last detailed
cost and schedule report for the project. Subsequent reports
will track the only remaining open account, CA 321, the upgrade
cryomodule system. Highlights for the month include: (1) completion
of major maintenance on the photogun including repolishing of
electrodes and replacement of pumping elements; (2) check-out
of many hardware systems needed for the kilowatt demo and (3)
sign-off of the Navy/DOE extension of the IR Demo contract to
March 1999.
CA 221: Scaleable Optical Cavity
A major alignment check and readjustment of the wiggler viewers
was performed to bring them back to the original tolerances set
in April. All of the viewers were found to be within 100 microns
or better horizontally but exhibited a vertical displacement of
typically 600 microns. They were reset to within 100 microns
vertically also. This brings them well within lasing tolerance.
Subsequently we adjusted the wiggler position and have plans
to readjust the downstream quadrupoles to bring them even more
closely in line. The alignment of the optical cavity fiducials
was reset. The purpose of these adjustments is to allow us to
bring the performance of the FEL to its maximum value quickly
with a minimum of tuning. The readjustment of the quads will
be performed in October as will a final check of the wiggler position.
The Laser Safety System was installed in Lab 1 and an update of
the specifications for that system agreed upon and given to the
electronics group for fabrication. An internal review of the
system and procedures is scheduled for mid-October. Nearly all
hardware is complete for Lab 1. In addition, programming of the
scanner system for the polymer demonstration has been tested and
is nearly operational. Measurements of the high power 3 micron
mirrors are underway at China Lake. A rewrite of the Laser Safety
Operational Procedure is nearly complete incorporating all changes
to the system since April. Finally, the drive laser system was
cleaned and realigned to bring its power and stability performance
back to what we had seen last December. We have experienced a
gradual loss of about 20% in green power. Although several problems
were uncovered and corrected there remains unknown the root cause
of our drive laser power loss. We continue to pursue this investigation.
CA 321: Upgrade Cryomodule System
Cavities IA074, IA076, IA021, IA023 were RF
tested at 2K under various cooldown conditions to identify if
the excessive chemistry during the repair introduced enough hydrogen
to reduce the Q-value if cooled down with cryomodule procedures.
Results showed that IA021, IA023 cavities showed sloping Q value-vs-gradient
curves. These two cavities were heat treated at 900 C for four
hours in a vacuum furnace. IA021, IA023, IA006, IA004 were then
tested with the same slow cooldown as above. This confirmed that
IA021, IA023 were repaired and that IA006, IA004 did not suffer
from this problem.
Preparation for assembly of the module is
under way with IA074, IA076 tuned and aligned for final assembly
steps. All peripheral components are completed for this pair
and a mockup assembly was performed to test the new alignment
scheme and finalize procedures. Mock fitup of a pair also occurred
to finalize cryounit assembly procedures of the new dogleg couplers.
Shields were fabricated for the magnetostrictive tuner tests.
Teststand and vacuum hardware were cleaned and prepared for the
final assembly of pairs.
CA 421: Commissioning Preparations
This account has been closed to further obligations
since October.
CA 431: IR FEL Commissioning
At the beginning of the month, the photocathode gun was being
reassembled after careful repolishing of the ball that supports
the cathode. Following "standard" procedure, it was
then vacuum-baked and high-voltage-processed, and the cathode
was heat-cleaned and cesiated. Unfortunately the photoresponse
of the cathode after cesiation was very poor, and field emission
down the beamline showed up at around 300 kV. Another attempt
at high-voltage processing, heat cleaning, and cesiation likewise
failed. A diagnosis of the location of the field-emission site
was then attempted with the aid of PARMELA simulations to guide
the interpretation of observations of the field emission. The
outcome was inconclusive. The best hypothesis is that the cathode
itself field-emitted, but the rim of the hole in the ball in which
the cathode is inserted field-emitted when the cathode was retracted
due to an accentuated surface electric field. We decided to attempt
helium-arc processing rather than go directly to opening the gun.
The processing was done on 30 Sept. 98, with the outcome to be
determined during the first week of October.
(Note: at press time for this report, after the cathode was removed,
a crack was found near the outer edge of the GaAs wafer, which
is the most likely source of field emission.
A refined Injector Checkout Procedure and an augmented High-Power
Setup Procedure were written. A key feature of the latter is
compression of a large energy spread after the wiggler into a
small energy spread at the energy-recovery dump. The idea is
to introduce quadratic nonlinearity by reinjecting a long bunch
length into the cryomodule so as to take advantage of the RF curvature
for momentum compaction. To do so reduces to a phase-matching
procedure that cannot rely on the cryomodule gang phase because
the gang phase has to be set for achieving a minimal bunch length
at the wiggler for strong lasing. Instead, it centers primarily
on adjusting the path length of the beam around the recirculation
loop.
The simulation code PARMELA was generalized to include sextupole
magnets, and by month's end a PARMELA deck for the entire FEL
machine had been prepared. The purpose for developing the deck
was to provide a tool for ascertaining more fully the character
of the longitudinal phase space of the beam as it propagates through
the machine, and thereby lend support to the aforementioned High-Power
Setup Procedure. Simulations of the full machine are slated for
October.
We also worked toward certifying the full Machine Protection System
(MPS). By month's end, about 80-90% of the MPS was certified,
with a residual four-item punch list awaiting resolution. Certification
was slated to be completed during the first week of October.
FEL INSTALLATION
During the extended shutdown, many hardware and software updates
were made, and they are enumerated in detail in the weekly reports.
The principal hardware updates that bear on commissioning consisted
of: configuring the viewers in the 180-degree dipole magnets so
that they now work; installing two new viewers in the second recirculation
arc; installing the beam scraper in the first recirculation arc;
modifying various drive-laser subsystems for increased power and
better stability of low-power RF; adjusting the 60 Hz raster magnets
in the injector and energy-recovery dump lines (the raster currents
will need to be reset prior to going cw); and upgrading the gun
for increased pumping speed, faster baking, improved heating of
the cesiator, and faster exchange of the conditioning and running
resistors. Software updates accommodate the new hardware on the
control screens and make the Analog Monitoring System functional.
Work on the FEL systems included installation of a low power pickoff
on the FEL beam to allow for calibration of the optical transport
losses. The optical collimator was cleaned, two nonfunctional
picomotors were replaced, and the system was realigned and pumped
down. The alignment of the optical cavity fiducials was reset.
A major alignment check and readjustment of the wiggler viewers
was done to bring them back to the original tolerances set in
April. Finally, the wiggler itself was moved by 250 microns to
bring it in line with the magnetic quadrupoles.
Significant progress on the Laser Safety System for the user labs
occurred. Nearly all hardware is complete for Lab 1. The software
for the overall system is complete, providing a one-look status
of the safety conditions of all labs by way of the EPICS control
system. At month's end, a review of the Laser Safety System had
been tentatively scheduled for 16 Oct. 98.