MEMORANDUM

To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report Jan. 13-17, 1997

Date: January 17, 1997

Management

Preparations were completed for the LPC workshop which will be held next week on Jan. 21-22. The agenda and charge were finalized for the DOE-BES review to be held on Feb. 23-24. Commitments were obtained for the external reviewers.

In view of the slippage in the fabrication of the new HV for stack assembly, the photocathode gun, coupled with our commitment to install the IRFEL in the FEL Facility by 30 Sept. 97, we formulated a contingency plan that preserves both the schedule and technical content of the Program. The central idea is, if necessary, to delay complete debugging of the injector until after its reinstallation in the FEL Facility. This saves time because it avoids a duplicity of 10 MeV commissioning activities, i.e., in both the ITS and FEL Facility. The resulting schedule accommodates two important global concerns. It employs Jefferson Lab manpower when it is available for the reinstallation activity, namely during summer 1997. It also gives us a reasonable chance to meet the Dec. 97 first-light milestone.

M. Owens and M. Cardarelli, of the defense staff for Senator Robb, toured Jefferson Lab and the FEL Facilities on Jan. 16.

Injector Test Stand

ITS activities have been oriented toward resuming operation of the gun at 250-300 kV. A new wet-etched GaAs wafer was inserted, and we are working on recharging the cesiator to "convert" this wafer into a photocathode. Preparations to bake the gun and beamline continued. We estimate restarting the gun during the first week of February.

Regarding upgrading the photocathode gun:

* Cr/V-Oxide-Coated Ceramics - Last week's report on the Cr/V-oxide-coated ceramics was garbled and should have read as follows: We discovered a glitch with the apparatus recently used to measure the coating resistances of the coated ceramics in vacuum. The result was faulty readings that indicated artificially high coating resistances. After correcting the glitch, subsequent measurements revealed coating resistances on the order of 5-6x10^11 ohms on two of the ceramics. At these resistances, the maximum current the coatings can conduct to ground is projected from the data to be about 0.6 µA. However, this drift current is too low, in that calculations project the field-emitted current from the cathode support tube to be in the µA-range at 500 kV. Assuming the coatings were to conduct this level of field-emitted current to ground, the result would be considerable distortion of the voltage gradient across the ceramics. We estimate that coating resistances below 1x10^11 ohms will result in drift currents that are high enough to keep the voltage distortion acceptably low. On the other hand, coating resistances need to be >5x10^9 ohms to keep the drift current low enough to prevent unacceptably high joule heating of the coatings. In short, we are trying to achieve coating resistances in the range 0.5-10x10^10 ohms. Plans are to decide what to do with these ceramics after we have the ion-implantation results from LBL.

* Coated Cathode-Support Tube - FM Technologies is calibrating their apparatus with a short stub of polished tube that we sent them, and they claim to be on schedule.

* Ion-Implanted Ceramics - Lawrence Berkeley Lab coated the "dummy" ceramic to a dose of 5x10^16 per cm and obtained a resistance of 6x10^11 ohms. The process is successful and shows good potential for achieving coating resistances in the desired range of 0.5-10x10^10 ohms. Plans are to refine the process and implant two of the improved ceramics over the next several weeks.

Accelerator Systems

Regarding the beam-transport system:

With continued testing of the prototype dipole magnet, coupled with Northrop Grumman's continuing work on the designs of the recirculation dipole magnets, we are on the verge of initiating procurement of the optical-chicane dipoles. Associated with this activity, we have scheduled the closeout of the Dipole Magnet Review for next week, 22 Jan 97.

Concerning other beam-transport developments -- All commercially available components for the vacuum system are on order. We have started to develop procedures for cleaning and installing the vacuum system. Design drawings of the stands and girders for the quadrupoles in the back leg of the beam-transport loop were signed off. The main vendor for the quadupoles received the necessary tooling for winding their coils. We are now putting more emphasis on the beam- transport system needed for first light, for example, the design process leading to the injection and extraction dipoles.

Regarding cryomodule fabrication:

We continue to have problems with cracking of ceramic warm windows during testing, and a team of people continues to work vigorously to find a solution. As one potential solution, a warm-window assembly is about to be tested, starting today (17 Jan), that incorporates massive stainless-steel flanges with reduced metalization geometry. In parallel, we have Northrop Grumman engineers looking at window-heating issues, and a SLAC visitor is coming on 27 Jan to consult on windows.

Stainless-steel higher-order-mode (HOM) subassemblies were qualified and delivered. Two assemblies have undergone final brazing. Test and evaluation of final assemblies has started and should conclude on 22 Jan. Additional HOM assemblies are in brazing, with completion of two scheduled for 24 Jan.

Regarding electron-beam diagnostics:

The final meeting of the Beam-Position Monitor (BPM) Review Committee took place. Plans are in place for timely delivery of the baseline suite of BPMs. The beam-diagnostics group also has some ideas for alternative BPM calibration methods that, if viable, would help shorten the schedule and save money. They will explore these ideas on the side, an activity that will not affect the procurement schedule. One challenge for the procurement process is to find a vendor who can fabricate and deliver the BPM suite on a 60-day contract, which is shorter than the norm of 90 days. The search is beginning. There are some other actions from the Review. They include testing the revised prototype stripline BPM, which we received from the machine shop this week, and completing a set of thermal analyses of the BPM designs, the results of which may influence some operating procedures. A memo is in writing that will formally close out the Review.

FEL Systems

Wiggler

Drawings are complete for the wiggler supports, and a meeting was held with Northrop Grumman to finalize the vacuum chamber and its supports. No special problems have been identified. Manufacture of the wiggler is proceeding on schedule. All poles and machine parts have been received. Magnets are due in Feb. 97.

Optics

The machine shop finished fabrication of the mount for the Brewster pickoff for the injector drive laser. Installation of the mirror is in process. Modifications were made to the optical support bracket drawings based on the actual dimensions of the optical mounts. Some of the mount brackets for the optical cavity have been finished. Machining of the rest of the optical mount for the FEL is proceeding well.

Optical components are being received on schedule from the vendors. In a parallel effort all fasteners, etc. are in order. The first iteration on the revision of the optical transport can is drawn and under review. Draft layout of the optical transport in the lower level of the FEL Facility is complete and under review.

Initial computer communication using the EPICS control system was established with the LVDTs used to readback mirror position. This is a major step toward getting computer control of the optical cavity. In a phone conversation with S. Siahatgar and H. Bennett, plans were reviewed for a bench test of the stability of the optical cavity.

Operations/Commissioning

As discussed above under "Management", we formulated a contingency plan and schedule for development/commissioning of the IRFEL injector.

Facility

A significant step forward occurred this week when the second-level floor was poured. This enclosed the interfloor piping and set the stage for construction of the girder framing on the upper floor. However, continued wet weather prevented completion of the building berming required for BOD1. Work continued in the linac vault to mount piping and electrical systems on the walls. Surveying continued to determine the as-built positions of the Facility elements. Construction of the framing for the entrance way and loading area is well underway.

The monthly meeting was held with the contractor to review status and future schedule. It now appears that the contractor will miss the second BOD by approximately 2 weeks due to delays in receiving the framing structure for the second floor. We are now replanning the installation of the FEL equipment racks to minimize delays due to this slip. One approach which will help has been adopted: phased installation, east-to-west, in the upper level based on drywall completion.

A request for bids is out on both the fabrication of the high-voltage power supply for the FEL Facility's 5 mA photocathode gun and the installation of the Facility's clean room.