MEMORANDUM

To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report Jan. 20-24, 1997

Date: January 24, 1997

Management

We held the winter workshop of the LPC on January 21-22 and approximately 65 attendees were present. Fifty participants were from outside the lab. Three of the working groups, polymer processing, metal processing and micromachining made good progress towards planning for initial utilization of FEL user laboratories. Plans for a fourth laboratory presently designated for use by personnel from the Navy and NASA are still in an early stage of discussion. No firm commitments are in place from NASA yet nor could be represented by NASA attendees at the workshop. Proposed experiments by the NRL staff are projected to require only a small amount of beamtime. There were preliminary discussions at the workshop on mechanisms for laser user interaction with the user facility, methods of allocating beamtime and draft user facility agreements.

The DOE distributed the preliminary agenda to the reviewers for the February 23-24 review. During the LPC meeting, commitments were obtained from three speakers for the FEL applications section of the review.

Injector Test Stand

The cesiator on the gun was successfully recharged and the unbaked GaAs wafer in the gun was tested with white light. A photocurrent three orders of magnitude above background was achieved with a 42 volt bias. This is a positive result and indicates proper operation of the cesiator and cathode.

Preparations continued toward baking the gun and beamline to allow the new beamline configuration to be tested at lower voltages (250-300 kV) with the current ceramic stack on the gun. By checking systems, software and beam dynamics now, we will be able to optimize our operating time at 350 kV once we upgrade the gun. The vacuum bake of the beamline and gun started 23 Jan and will continue until 27 Jan. We will then start reassembling the non-bakeable portions of the beamline and gun, and plan to resume operating the gun during the first week in February.

Regarding upgrading the photocathode gun:

* Coated Cathode-Support Tube - FM Technologies reports that they will finish coating the cathode-support tube by the first or second week of February.

* Ion-Implanted Ceramics - Lawrence Berkeley Lab (LBL) continued to implant the "dummy" ceramic to a dose of 7.5x10^16 per square cm, and they obtained a resistance of 2.4x10^10 ohm, right in the middle of our target range. Unlike the Cr/V-oxide-coating process, the ion- implantation process offers far better control of, and provides a real-time in-situ measurement of, the resistance.

The refurbished leak-test fixtures were received by Hitemp, and the subsequent leak test of the braze on the flanges of the first improved ceramic was successful. That tube was cleaned and sent to Lawrence Berkeley Laboratory for implantation while they take care of accumulated work, improve their electronics, and prepare for the next runs. We are buying some 1/4" platinum rods. They will be required to complete the second improved ceramic.

* Cr/V-Oxide-Coated Ceramics - In view of LBL's success, we plan to remove the Cr/V-oxide coatings with the unacceptably high resistances on the three other ceramics and substitute the ion- implanted surface.

Accelerator Systems

Regarding the beam-transport system:

The close-out meeting of the Dipole Magnet Review was held on 22 Jan. The review committee concluded that we should proceed with procurement of the optical-chicane dipoles. However, a number of actions remain. Two are of note. The first action is the need to confirm, via measurements on the prototype dipole, that a suitably uniform drop-off of the end field required across the "good-field" aperture can be obtained. The dipoles are already designed to be wider by a half gap on each side to provide the drop-off, but the increased width may not be enough. The second action is to consider a method for orbit correction that minimizes use of corrector dipoles, thereby simplifying machine operation. The method is physically to shift the sextupoles and trim quads in the recirculation arcs. The idea will be modeled using our linear-optics code.

The design of all of the recirculation-bend dipoles continued at Northrop-Grumman in parallel with checking the drawings of the optical-chicane dipoles. Specifications were written for manufacturing the optical-chicane dipoles, and their procurement packages are being prepared.

The layout of the injection/extraction dipoles was solidified based on measurements of the prototype dipole, including saddle coils and field clamps. One net result is that the magnets are larger in size. In the extraction region leading to the recirculation dump, there are two phasing dipoles in close proximity to the extraction dipole. Thus, the larger size of the extraction dipole is of concern because its edge fields could be warped beyond specifications by the presence of the constituent iron in the nearby phasing dipoles. Based on favorable high-field performance of the prototype dipole, we are presently considering a work-around that involves increasing the maximum design field in the extraction dipole and eliminating the phasing dipoles altogether.

Measurements of the prototype trim quadrupole and the prototype sextupole have been delayed in favor of additional measurements of the prototype dipole and of magnets supporting the main machine. We cannot continue the delays indefinitely and are searching for ways to expedite the measurements.

A kick-off meeting on the girder for the injection dipoles was held to review the requirements document for these girders. Kick-off meetings are now planned for the remaining stands that are needed for the beam-transport system supporting first light. The X-chamber drawings (for the vacuum chamber connecting the injection line to the recirculation loop) are now in our machine shop.

Regarding cryomodule fabrication:

The pursuit of ceramic warm windows continues. Testing of the warm-window assembly mentioned in last week's report was unsuccessful because the ceramic cracked. We now conjecture that the problem may not be with the window assemblies, but with the vacuum in the ring-resonator test stand. Consideration of existing experimental data revealed that the combination of the test-stand vacuum conditions and the field gradient at the ceramic window is conducive to rf breakdown. In response, we spent this week improving the vacuum and are preparing another window assembly for testing. The improved vacuum corresponds to that expected in an operating cryomodule, so the improvements to the ring-resonator test stand serve to make it a better model of the windows' operational environment.

We now have on-hand four stainless-steel higher-order-mode (HOM) subassemblies. Two of them were tested and passed all of our standard acceptance tests. As an additional check, we are in process of qualifying them in a cold-cavity assembly.

Our machine shop has started to modify a standard CEBAF liquid-He-containing vessel to incorporate penetrations for the FEL HOM designs. This activity is on schedule.

Regarding electron-beam diagnostics:

As the prototype stripline beam-position monitor (BPM) was being modified to incorporate shorter electrodes, three of the four electrodes shorted to the end ring during the final weld. This is being corrected. Acceptance tests require two adjacent electrodes to function.

A memo documenting the results and decisions of the BPM Review has been drafted and is circulating among the Review Committee members for comment. It should be finalized in a few days, and it then will be posted on www. The cable data base for the BPMs was finalized this week as a preparatory step for developing the BPM procurement packages.

The FEL-server requisition (60 k$) was signed and delivered to procurement.

Operation of the linear variable differential transformer (LVDT) VME board was successfully demonstrated. This is a position sensor that will be used to monitor the FEL optical-cavity length. The constituent printed circuit boards (PCBs) were surplus from the Superconducting Supercollider Project.

The prototype PCBs for the ion-pump power supply arrived and are being tested.

The Software Group demonstrated the (preliminary) operation of the latch card used in Argonne National Lab's Advanced Photon Source (APS) Machine Protection System (MPS). This is one of two PCBs from APS that will form the backbone of the FEL's MPS.

We finalized the cable data base for the vacuum-system components. Having done so, we can now finalize the corresponding installation activities as well as the software requirements for the vacuum system.



FEL Systems

Injector Reinstallation

Northrop Grumman has completed a finite element analysis of the high voltage power supply chamber. The design is sound with a factor of 5 safety factor under test conditions and a factor of 8 under operating conditions. We are still awaiting bids from fabricators of the clean room and the high voltage power supply.

IR Demo wiggler

All drawings of the wiggler support elements are signed off and out for bid. Design work is nearly complete for the vacuum chamber. Layout and detailing of the vacuum chamber support will start next week.

Optics

Work this week continued on detailing drawings for the optical transport. Specifically, we are checking drawings for the diagnostic pick off, and the mirror cans. Work continues to progress on the collimator and the mirror cassettes. We now have engineering support to design the optical table stands. Most of the revisions to mounting hardware for the optical cavity assemblies have been made and were signed off this week. Work continued on fabrication, although it was slowed somewhat by the need to fabricate HOM loads for the FEL cryomodule. We received the IR detectors that will be used with the diagnostics monochromator. The LabVIEW program that is supplied with ARC monochromators is undergoing revision to better adapt it to our needs. The electronics for the interferometer length diagnostic went through a redesign, and the new version is being tested.

Operations/Commissioning

As described above under "Accelerator Systems", operations/commissioning activities focused on supporting the closeout of the Dipole Magnet Review and also on exploring questions related to operation of the dipole magnets.

Facility

Work this week involved installing lighting systems and services piping in the tunnel area. By the end of the week nearly half of the lighting fixtures had been hung and welding was underway on the cooling water piping. The steel framework staging was started for the second floor of the building. That work is expected to get into full swing next week. The base for the utilities building was poured and that area was in the process of being prepared for equipment installation.