MEMORANDUM
To: J. Cook, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IR Demo Project Weekly Report, January 5-9, 1998
Date: January 9, 1998
Management
A visit to NRL was made on Thursday, Jan. 8th by F. Dylla, C.
Bohn, and G. Neil. A presentation on the Jefferson Lab FEL Project
was given as part of a seminar series hosted by NRL's Condensed
Matter and Radiation Effects Division. We talked to a number
of staff members from this Division and the Chemistry Division
about planning and executing experiments using the IR Demo. Several
NRL staff members will be visiting the lab during next week's
LPC Workshop.
Final preparations were made for the LPC Workshop which will be
held on Jan. 14-15th. As of today (Jan. 9th), over 50 registrants
from outside organizations were planning to attend.
A planning/brainstorming session was held this week to look at
various options for upgrading the IR Demo to higher powers (>10
kW in the IR) and an expanded wavelength range (0.2-60 microns)
based on the use the higher voltage cryomodules under development
for the CEBAF energy upgrade program.
Commissioning Activities
We outlined key top-level tasks that need to be accomplished prior
to resuming commissioning with electron beam for which the planned
date is 26 Jan 98. All of the key tasks are being worked, and
they are updated during the daily (11:45 a.m.) status meetings
in the FEL Conference Room.
A schedule for the first light commissioning through the first
user experiment from Jan. 26 through June 30th was formulated
at this week's commissioning meeting.
Installation Activities
The last 2 DQ magnets were installed and aligned in the east arc.
All 4 DX magnets, their bend chambers, and the straight chambers
connecting to the DQ's are also installed.
The last DV magnet has been adjusted, measured and released for
installation.
The beam line was opened in front of the 2G, straight ahead dump,
in preparation for the GEN target hardware.
Additional software work is scheduled for next week to separate
the Injector RF modules into individual systems and make the overall
Injector more robust. Work on the main machine is taking priority.
Testing will start next week to find two 8 KW klystrons and a
spare for the FEL cryomodule. After installation, the klystrons
will be conditioned to 14 KV.
The upstream alignment pellicle was installed in the optical cavity
and its preliminary alignment was completed. The downstream alignment
pellicle is scheduled for installation early next week. The laser
beam collimator has been assembled in the optics lab with installation
scheduled for 2 weeks.