IR Demo Project Weekly Report, July 12-17, 1998
July 17, 1998
|
|
|
|
|
Management
Highlights for the week include the following: This week was an installation/maintenance period
for (1) completion of remaining hardware for the upcoming recirculation tests and (2)
replacement of the photo cathode and bakeout of the photogun. In addition, planning activities for
the upcoming kW demonstration and first user experiments continued.
On Thursday, July 16, Mr. David Merritt, Program Director for Advanced Technologies for the
Space and Naval Warfare Systems Command (SPAWAR) and Mr. Joung Cook, the Program
Manager for the Navy High Energy Laser Officer visited the lab for a tour and briefing on the
FEL.
On Friday, July 17, Mr. Mark Zacharias, the Jefferson Lab Budget Analyst for the
Commonwealth of Virginia visited the lab for a briefing on the state funded activities that included
the FEL and ARC.
|
|
|
|
FEL Installation Activities
The photocathode for the gun was replaced this week and the gun is being baked.
Four SC (sextupole) magnets were installed, connected, and aligned. Checkout is in progress for
all the installed magnets in the 3F, 4F, and 5F regions. They will be needed for recirculation of the
beam.
The insertable dumps were checked, reworked as needed, and realigned.
The installation of grating over the cryo lines was completed. They provide easier access to
components behind the optical cavity and the back side of the cryomodule.
Steps were installed over the wiggler optical table to the above grating.
|
|