MEMORANDUM
To: J. Albertine, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IR FEL Weekly Report: July 27-August 2, 1996
Date: August 2, 1996
Management
A summary presentation on the IR Demo FEL project was given at
the FEL Program Review meeting held by the Navy High Energy Laser
Office at NRL on July 30. The morning session was devoted to
laser-materials damage and atmospheric propagation effects and
the afternoon session was devoted to hardware topics including
injector designs (LANL and Stanford) and system studies (NRL and
Northrop Grumman).
On July 30-August 1, Northrop Grumman hosted a series of tours
and discussion sessions on issues related to FEL development at
the Northrop Grumman facilities in Bethpage, LI and Princeton,
NJ. The meeting was hosted by the N-G Advanced Technology Development
Center at these locations and included representatives from other
company divisions at Rolling Meadows, IL, Sunnyvale, CA and Pittsburgh,
PA. We found that there are useful hardware development activities
on Favry-Perot interferometers, fly-wheel energy storage devices,
and ceramic engineering that can be added to the existing collaboration
with Northrop Grumman that supports FEL development at Jefferson
Lab.
We mad preliminary plans to hold a workshop on the issues relevant
to extrapolating the IR Demo to higher powers (~MW) on Sept. 24-25.
IR FEL Accelerator Systems
Detailed design of the transport line for the IRFEL's injector
dump was started. The magnetic optics envisioned for the injector's
transport line are well-suited for measurements of emittance and
energy spread.
Detailed design of the transport line for the IRFEL's recirculation
dump was also started. The preliminary design is encouraging
in that it generates reasonable beam sizes at the dump.
Many more accelerator-subsystem schedules and plans have been
added to the Web.
Injector Test Stand
We are presently holding to our revamped schedule for the Injector
Test Stand. The vacuum bake of the gun and its beamline has started.
A concerted effort has been initiated to procure improved ceramics
and investigate an anti-field emission coating for the stem.
FEL Systems
Wiggler
A review was held of the magnetics design at the vendors on 7/29/96.
The design of the main field structure, the magnetic materials,
shimming techniques and the measurement approach were all found
acceptable. Further work was desired in the end correction approach
to reduce the possibility of beam offsets. Also required is an
approach for dealing with errors due to the earth's field. A
meeting to discuss mechanical design is scheduled for September
13 at the vendor's.
Optics
Orders were placed for the main optical cavity mounts which will
be adapted to handle cooling, remote tuning and length control
The engineering detail drawings for the optical cavity including
these modifications to commercial hardware are to be complete
early next week. Orders are also being written up for the raw
pipe for the optical transport system.
Operations/Commissioning
Several schemes were considered for phasing the electron beam
with the accelerating cavities for deceleration and energy recovery,
and a promising scenario was adopted.
Facility
Work continued per schedule on the facility. Rebar was tied into the west half of the lower floor and wall joints early in the week. Despite a break in a 12" water main which flooded the excavation and 3" of rain on Wednesday and Thursday, concrete was poured on Friday to form 1/2 of the lower level floor before rains move in again. The major portion of the rest of the dig is complete and surveyed. Tie ins to the South Linac low conductivity water and main site electrical service have been scheduled for September 3 to coincide with a scheduled CEBA shutdown.