|
|
To:
cc:
From:
Subject:
Date:
|
|
J. Cook, D. Helms, W. Skinner
Division (M7), FEL Coordination Group
F. Dylla
IR Demo Project Weekly Report, July 6-10, 1998
July 10, 1998
|
|
|
|
|
Management
Highlights for the week include beginning the process of replacing the cathode wafer in the gun,
and replacing the 98% reflective outcouplingmirror in the optical cavity with a 90% reflective
mirror to extract higher power.
FEL Installation Activities
We installed and hooked up the air-core correctors in the back leg, and we began to wrap mu-metal
where possible through the recirculation loop to screen the Earth's magnetic field. We installed
beam-loss monitors along the recirculation loop and hooked up much of the back-leg diagnostics.
We also replaced the outcoupling mirror in the optical cavity with a 90% reflective mirror. Both
the optical transport line and the Laser SafetySystem for Lab 1 (Polymer Lab) are nearing
completion.
FEL Commissioning Activities
Yesterday (9 July 98) we lost the photocathode due to arcing and vacuum activity near 350 kV.
Recesiation did not help; apparently a field-emitting site came into being that emits after cesiation at
the voltage indicated. Consequently, we processed the gun at 500 kV overnight and through this
morning to try to burn away field-emission sites. At 1245 today we decided to pull the cathode
since it exhibited observable field emission at 440 kV coincident with the location of the drive-laser
spot, and since we had some evidence of hydrocarbon contamination duringhigh-voltage
processing that would make recovery improbable. The processof replacing the cathode and
reconstituting the gun will take about ten days, but the time will be well spent toward completing
more installation tasks and working on additional detailed procedures for kW lasing.
Prior to losing the cathode we accomplished several commissioning tasksthis week, including
checking the magnetostrictive tuner for one of the cryounit cavities (its current drive circuit needs
more work); running the cryomodule cavities at their peak gradients (for 1.5 hours with only one
rf trip, indicating we should be able to produce and sustain 47 MeV beam for straight-ahead lasing
|
|