MEMORANDUM


To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report, June 9-13, 1997

Date: June 13, 1997

Management

The second meeting of SURA's Maritime Technical Advisory Committee was held on June 9-10. The Committee reviewed the laboratory's FEL development program, the Navy's interest in high energy lasers and the potential linkage of these interests. Recent assessments from ONR have significantly impacted the prospects for FY98 Navy funding. Although, the ONR assessment was positive with respect to the broad utility of the Jefferson Lab program for industry and materials science, the Navy has declined near term support for laser technology for more general defense applications because of the current tight budgets and higher priority development programs. MTAC has recommended that we focus all available FY97 Navy funding and any potential FY98 funding (which will not be determined until the end of the current Congressional deliberations) towards commissioning and operating the baseline 1 kW demo and, as funds permit, initiate the upgrade program to shorter wavelengths and higher powers.

The Navy Program Office reviewed the status of the ITS experiments and the cryounit warm window development effort during a half day review following the MTAC meeting. Criteria for declaring completion of the ITS tests were agreed upon which should allow start of the ITS cryounit move to the FEL Facility and the ITS gun move on June 23. (See ITS report for details.)

The preliminary agenda for the June 25-26 LPC workshop was prepared and distributed to the LPC mailing list. The workshop will focus on reviewing proposals for initial research applications of the IR Demo and start-up of the User Labs.

Injector Test Stand

Regarding the photocathode gun:

Most of the week was dedicated to measurements of bunch length and longitudinal emittance at bunch charges of "zero", 60 pC, and 135 pC. The first step was getting the kicker cavity to operate in the pulsed mode, and we successfully obtained 300 W/pulse, a value sufficient for the longitudinal- emittance experiments. We also needed to make a new cathode at mid-week. As of Friday morning (13 Jun 97) we had obtained the bulk of the data. Though we had anticipated depleting the cathode during the 135 pC runs Thursday night, it was still performing well on Friday morning, and we were therefore planning to augment the 135 pC measurements over the weekend. We seem to have a bug in the data-reduction software, in that it gives about a factor of two larger bunch lengths than the PARMELA simulation code despite otherwise "sensible" inputs. As a result, we still need to resolve the discrepancy between the PARMELA algorithm and that of the data-reduction software.

Plans are to finish the 135 pC longitudinal measurements over the weekend, do a long run next week to monitor dark current versus time in an effort to gain some additional insight into the field-emission behavior of the gun, and then begin moving the gun and supporting systems to the FEL Facility on 23 Jun 97.

The drive laser operated continuously for 97 hours this week in support of the gun experiments. Its power output was quite stable over this period. Two brief (less than 1 hour each) intervals were used to check and optimize the beam alignment. The overall extinction ratio from the dual set of modulators continues to be excellent. We did discover that for macropulse lengths longer than ~10 microseconds, the micropulse intensity is modulated for ~200 microseconds (which, for example, causes corresponding jitter in the energy spread of the bunches). The problem is due to piezoelectric resonances in the KD*P crystals used in the modulators. We have begun discussions with the vendor to determine ways to dampen the oscillations.

Regarding the cryounit:

The cryounit is now warmed up and is being disconnected in preparation for the 16 Jun 97 move from the ITS to the FEL Facility. Prior to warm-up we completed testing its waveguides, with forward power limited to 10 kW. Test results verified that the ceramic warm windows will support planned commissioning of the IRFEL all the way through first light with head room available. We also did a first test of the magnetostrictive tuners on the cryounit. These tuners are designed for compensating the modest frequency shifts that will result from electron-beam loading during turn-on of the injector, which is a relatively slow process. The tuners have a bandwidth of 0.3 kHz. We found that we could successfully drive and lock them over their bandwidth, thereby validating their operability.

Regarding development of 50 kW ceramic warm windows:

Production continues with carefully selected ceramics. We expect to qualify these windows to the 50 kW-level during July. Additional work continues toward understanding the variability of ceramic performance. Alternative BeO windows from Northrop Grumman are in production, with final parts being manufactured by a local machine shop. Final assembly of these windows is now scheduled for July.

Accelerator Systems

Regarding the beam-transport system:

The injection chicane dipole parts and optical chicane parts are 95% complete. Reverse bend and 180 degree dipole core parts are in final machining and the first article coils for reverse bends passed dimensional inspection at the vendor while good progress was being made on the tooling for the 180 Degree coils. Trial pole pieces used for prototyping the assembly process are finished at Everson Electric to begin trials next week.

One and a half sextupole core bodies of the eight required were cut to the finish dimension by Process Equipment Co. using electro-discharge machining while the winding mandrel tooling is complete at the coil vendor. The Trim Quad package was prepared for bidding. The three, long Panofsky-style quadrupoles (QIs) for the recirculation dump were continued at New England Electric Co.

Design of the mu metal phasing dipoles was laid out. Broad brush measurements on the several configurations of a mock-up of an air core corrector made of four coils in an approximation to a cosine distribution convinced us that to get the 1% harmonics or less, we will require a formal cosine distribution dipole. Magnetic modeling using TOSCA by Steve Lassiter using a wrap-around end turn configuration was started. Advanced Magnetics Laboratory (AML) is preparing a preliminary proposal of their own, using their proprietary winding process, to produce the air core magnets. Our response will tell them if they are in our technical, price and delivery comfort zone before they prepare a formal proposal.

The chamber for the 180 degree dipoles was awarded to Master Machine. Welding of the body on the X Chamber for the Injection Chicane was completed, the ends machined and we are now checking magnetic properties in the prototype dipole. The Recirculation Dump's Y chamber is tacked up. Optical Chicane Chamber plates are now on hand and being prepared for welding. We are preparing to send reverse bend chamber parts out for fabrication and are talking with Stanford Linear Accelerator Center about having them do cleaning, welding and leak checking.

Design of the final batch of stands and girders for the arcs continued while a number of girders were installed in the back leg.

Details of the insertable dumps are near sign-off while design of the beam scraper continued. The straight ahead dump body parts are done and are being sent out for brazing. Design of the details of the dump shielding supports continued.

Though much of the instrument air system is installed, we have finally settled on what compressor to buy and that procurement is imminent.

Regarding cryomodule fabrication:

Cryomodule assembly continues without issue. The cryounit assembly area is progressing on the last three cryounits. The cryomodule assembly area is waiting for the next cryounit, which is scheduled for delivery next week. The overall schedule leading toward installing the finished cryomodule in the FEL Facility on 4 Aug 97 remains tight but doable.

Regarding electron-beam instrumentation and controls (I&C):

Configuring the I&C-related racks in the FEL Facility is an ongoing activity that is progressing vigorously. As just one example, the chassis for the beam viewers was installed, and its documentation (chassis schematic, wiring diagram, front-panel schematic, art work, fabrication and assembly on both boards) is now ready for sign-off. Channel assignments are continually being updated and posted on the www with associated software requirements. Installation of the safety system for the Facility's clean room will be completed today (13 Jun 97).

FEL Systems

Wiggler

The machine shop had to reinstall one of the quadrupoles on the wiggler girder after the alignment group noticed that its angle was wrong. Alignment of the downstream quads and wiggler is complete. The girder should be installed next week. The vacuum chamber supports should be finished next week.

Optics

We received initial test results from China Lake on the set of mirrors from Rocky Mountain Instruments (reflectivity ~ 89%). The mirror figure, surface roughness, and reflectivity are within their respective specification. However, the ROC appears to be out of specification. We are consulting with the vendor to check their metrology. The mirror cans were tested to ensure the input and output flanges were welded correctly. Our results are in agreement with the vendor, 8 are better than specification, and 4 are not. Rather than send the 4 back, we'll use them downstairs where this specification is not critical. We also tested the mirror-can camera assembly and found it worked well. The mirror stands are complete and will arrive on Monday (16 Jun 97), and installation begins next week. Optical cavity components went through an initial cleaning. We tested a Cohu charge-coupled-device camera, of the type we'll use in the accelerator vault, that had been irradiated with 45 kR of bremsstrahlung from the accelerator. It tested fine with no dead pixels.

Commissioning/Operations

An initial, rudimentary test plan for coherent-synchrotron-radiation (CSR) experiments was devised and is published on JLab's www site at ~douglas/FEL/csr_emittance/emittanceindex.html. Sustaining these experiments early in the commissioning process should not be a problem, even at 135 pC/bunch because they will be done in pulsed mode, i.e., at low average current. If the software is available, we will try to augment the measurements with phase-space tomography.

We have made noteworthy progress on self-consistent N-body simulations that include CSR. The simulations incorporate Gaussian macroparticles, as opposed to point particles, to eliminate numerical noise. The key ingredient is a correct calculation of the interaction force between macroparticles, and we have developed what appears to be an efficient algorithm for this calculation. To benchmark the algorithm, we simulated the dynamics of the Gaussian rigid-line charge using macroparticles and checked to see if the code replicated our analytical steady-state wakefield, and it rapidly did so with only 40 macroparticles. Having thereby established the validity and efficiency of the algorithm in one dimension, we are moving on to two dimensions. The force is correspondingly more complicated, but the ingredients of the algorithm remain unchanged. Although it remains to determine the speed and efficiency of the calculations in two dimensions, the prognosis for having a self-consistent simulation tool available in the next few months is good. Of course, our intent is to use it to predict more accurately emittance growth in the bends of the transport lattice of the IRFEL and correlate the results with those of the planned experiments.

We have been following through with our plan for the magnetic-field-measurement probe for the dipole magnets. The probes are off-the-shelf, obtained from Rawson-Lush Instrument Co. They have very good absolute measurement and good reproducibility. However, they do present a challenge in that the probes are much larger than a normal Hall probe, and mounting them in the tight magnets will be difficult. We believe the difficulty is manageable.

Facility

Finish work continued at flank speed during this week. The entrance lobby and stair well was dry walled as well as the entrance double door area. Ceilings were put on the front and back porch covers. A large fraction of the earth fill was brought in and bermed around the facility. Electrical finish work continued. Power was brought to all the HVAC units and the new clean room. The elevator crews worked through the week to install doors and controls. Ceramic tiling continued in the bathrooms; walls are complete in both men's and women's, flooring in the men's. Showers in the men's room are 80% complete. Plumbers are preparing to install fixturing. Touch up painting was done in several areas. Major painting included break area and stair wells. Preparations are underway to begin energizing the HVAC units next week. A new drain was added to the wiggler pit sump. Downstairs Jefferson Lab crews surveyed the optical cavity tables. Additions were made to the cable trays in the injector to support cryo and controls. Dump stands were placed and grouted. The crane hoist was welded and hung for the cryounit installation. All activities are in place for moving the cryounit on 6/17. A second rail support was hung for the gun in preparation for its anticipated move 6/24 (barring unforeseen experimental ITS problems). Cryogenic controls were pulled and began to be hooked up in preparation for the cooldown. Leak check continued on the transfer lines. Layouts of the optical transfer can mounts were passed to the installation crews for drilling mounting holes on the ceiling. Flooring was laid and sealed in the clean room. The electric power switch gear was mounted. Safety system equipment began to be installed in the clean room. Other safety system equipment was installed all over the facility: warning lights, ODH sensor wiring, run/safe boxes, etc., RF installation and hookup of the low level, high voltage power supply, and high power amplifiers continued. Welding of the LCW piping continued upstairs. Electrical hookup of the equipment racks is beginning. Control LAN worked continued.

The crane rails are installed and awaiting load testing. Most of the work on the Clean room is done. The LSS is installed. We will have to wait until June 19 to test the cooling system since chilled water will not be available until then.