MEMORANDUM



To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report, March 10-March 14, 1997

Date: March 14, 1997

Management

A revised proposal and statement of work for the 1 µm IR FEL upgrade was sent to the Navy High Laser Office that incorporates their preliminary comments on the first draft.

The second meeting of SURA's Maritime Technical Advisory Committee has been scheduled for June 11-12.

Management focus this week was on coordination of the near term ITS schedule, progress with the rf windows, and start-up of installation activities in the first floor of the FEL building.

Injector Test Stand

We continued operating the photocathode gun at 250 kV. We calibrated the viewers for the multislit transverse-emittance diagnostic which will be commissioned with the upgraded gun. In the process, we also generated a test set of multislit data using the existing slit assembly to provide example data for analysis. A measurement of bunch length versus transverse position on the bunch was made using the rf kicker cavity. Measurements like this provide information on the three-dimensional density profile of the bunch for comparison with code. We also did a continuous-wave run to test photocathode life, and in the process delivered 10 coulombs to the beam dump. This run was controlled and monitored from the Machine Control Center on the accelerator site.

The infrared-wavelength optical modulator and the bias supply for one of the two 527 nm optical modulators failed during this week's runs.

Regarding upgrading the photocathode gun:

In attempting to assemble the new high-voltage stack, we detected an error in the position of the kovar flanges on the new ion-implanted ceramics. The rings were brazed in a position 0.5- 2 mm higher than specified. Thus, we spent the week working a solution to bend the flanges to close the resulting gap using tooling that will not stress the delicate braze joints. At week's end that tooling is scheduled for completion on Saturday. As a back-up, we made a second tool to do bending by hand. We might use the back-up ceramic to replace the most severely misbrazed ceramic. It was ion-implanted at Lawrence Berkeley Lab to a resistance centered within the range of the two ceramics we have on hand, and we will receive it from LBL on Monday. The bottom line is that we plan to weld the high-voltage stack not later than Tuesday, 18 Mar 97. We plan to continue operating the gun in the ITS until we have completed fabricating and leak-checking the new stack, which, again, should be early next week.

The coated cathode-support tube was electron-beam welded to its flange and cleaned in preparation for installation. We decided to remove the spacer from the photocathode gun when upgrading it for higher- voltage performance. At 350 kV voltage, this action will result in a direct-current field gradient of about 7 MV/m at the cathode, as opposed to 4.2 MV/m with the spacer in place, and is therefore favorable from the perspective of electron-beam dynamics. The action is regarded to be low-risk because the highest fields on the cathode support tube and ball are near the equator of the ball and are insensitive to this change-out.

Regarding other ITS activities:

Qualification of ceramic warm windows continues. We have found that the supplier has not been producing ceramics of consistent quality. We successfully ran two warm windows to 25 kW with the 50 kW klystron setup, and thus, as of now, we have two windows for the cryounit and plan to install them early next week for subsequent off-line cryounit tests. Contingency plans are being developed in the event there are problems. Control software for the cryounit is in final debugging.

Due to problems with a vacuum leak, the spare 50 kW klystron (the fourth unit) was removed from its test stand and is being returned to the vendor for repairs. We are anticipating a turn-around time of about two months.

Accelerator Systems

Regarding the beam-transport system:

The bids for the optical-chicane dipole magnets were received. One vendor requested an extension to close-of-business Tuesday, March 28. Since this bid is the first in the series of three bids for dipoles, we did extend the due date to keep this qualified vendor in the running and enhance our ability to maintain parallel manufacturing of these magnets.

The second dipole-magnet bid package (for the reverse-bend and 180-degree dipoles) is one-third complete, missing our intent to get all the drawings out for bid by Friday. The prints for the 180- degree dipole are lagging the furthest behind. Were we not to intervene, they would arrive next Thursday. However, we are attempting to accelerate sign-off. The package's check prints were checked during the week and sent back to Northrop Grumman on Friday. We are taking a portion of the Northrop Grumman electronic files and working in parallel to incorporate these back-check items. As good news, the completed drawing package for the first reverse-bend (DX) dipole was received on Friday, and the package for the second reverse-bend (DQ) dipole is due to arrive from Northrop Grumman on Monday.

Design of the injection-chicane dipoles continued at Jefferson Lab, also missing the target Thursday date for getting them out to bid. Check prints are in evaluation and the package is being worked over the weekend.

We are working to create an industrial process to make the Purcell gap and glue the mu-metal onto the poles of the dipole magnets. Tests that involved gluing aluminum shim material between two 1-ft-square aluminum tooling plates under very uniform, high-pressure conditions showed that virtually zero epoxy thickness was obtainable. We will therefore try again with the prototype dipole using similar bonding methods. We plan to evaluate the shear stress on this epoxy bond at Northrop Grumman. Tests of other methods for creating the Purcell gap are also planned.

Tests with the prototype dipole with welded vacuum chambers indicated slight alteration of the edge of the good-field region in three locations. Two of those locations were rectified by increasing the width of the as yet undetailed chambers. The third location is at the intersection of the injection line with the recirculated beam line. It has no solution, but from the perspective of electron-beam dynamics, we can live with the small effect.

Design of the vacuum chambers for the optical-chicane dipoles began. We also started establishing the cleaning procedures and equipment to fabricate all of the vacuum chambers under the particulate-free, ultra-high-vacuum conditions required by our specifications.

Eight weak quads were shipped from the vendor. All are beautifully made but failed inspection due to an irregularity in the length of one of their poles. We are working that issue.

The magnetic optics of the recirculation-dump line was finalized and incorporated into the master layout. We need two additional wide-aperture (4-inch) quadrupole magnets for this line, much like our QTS. They will have to be added to the procurements.

The back-leg stands and cable trays were installed in position, marking the first part of installation of the beam-transport system in the FEL Facility.

Drawings of the remaining stands and girders for first light were signed off, and their procurements were started.

Regarding cryomodule fabrication:

Cryomodule assembly has begun. Following successful acceptance tests of the first cavity pair, assembly of the first cryounit is now started. The second cavity pair has been assembled and is scheduled for acceptance testing next week.

Regarding electron-beam instrumentation and controls:

The balance of the drawings for the Oregon Micro Systems (OMS)-based stepper-motor-control system were completed and signed off. All of the constituent boards are complete or in fabrication.

Design of the vacuum-control crates continues. They will hold 67 individual printed circuit boards of 9 different types. Only the fast valve control card has not yet been manufactured.

All of the hardware necessary for mounting and testing the multislit transverse-emittance diagnostic with the upgraded photocathode gun is now ready.

The optics setup for detecting synchrotron light in the vacuum chambers of the 180-degree dipole magnets was successfully bench tested using the same optics and geometry to be installed in the linac arcs. The system will permit non-invasive imaging of the beam at a point in the transport dominated by dispersion. This enables sensitive energy stability and energy spread determinations of the electron beam to be made. The camera to be used has also been tested and is expected to have sufficient sensitivity to even see pulsed beam while setting up the beam transport.

FEL Systems

Wiggler

Gage blocks for supporting a 12 mm wiggler gap were ordered from STI Optronics. Delivery of the magnets from Shin Etsu has slipped again and is now projected for 24 March, with expected delivery of the wiggler in late April. The design layout for the wiggler vacuum-chamber stand is nearly complete. We will make the tubing necessary for the chamber in house. Techniques from other labs that have made similar tubes have been gathered.

Optics

Efforts on the new design for the optical collimator have been somewhat slowed by the unexpected resignation of the designer. We are in the process of hiring new designers, but this may delay our efforts by several weeks.

Our machine shop reports the output Brewster window is about 50% complete. This will complete the work they can do until several long-lead items are received later this month or early next month.

We ordered mirrors for 5-micron operation. We also ordered hardware to support installation of the optical-transport system in the FEL Facility.

Operations/Commissioning

A procedure for setting up the electron beam prior to wiggler installation was drafted. Part of the consideration is doing early experiments concerning the effects of coherent synchrotron radiation on the electron beam. The quad-viewer method for making transverse-emittance measurements in the back leg of the recirculation arc was detailed, and correspondingly the precise locations of the optical-transition-radiation viewers were pinpointed. Generally speaking, we are in process of freezing the precise locations of all of the elements of the beam-transport system, which must be done in time to implement the installation plans. So far, all of this activity is on track.

Facility

FEL Facility construction and installation proceeded at a rapid pace. The most visible progress is upstairs where wall frames and studs were placed around the entire lobby area and entire utility room. About half of the roof decking is in place. Some door frames are in place. A striking view now exists from the east side with all exterior wall panels attached. Large quantities of HVAC equipment and ducting were craned to the second floor. Plumbing work continued on the bathrooms. It is starting to look like a laser facility!

No less important was lots of detail work performed downstairs including finishing the floor sealing and painting the ceiling and piping. Doors were hung on all exits and painted. The exterior roll-up door to the truck ramp was hung and is fully operational. Work continued on the site electrical service. It may be possible to power up the main lighting for the lower floor next week. Survey crews marked the placement of the cryogenic lines and the lines were wrestled into position. A welding trailer was moved into the area as welders set up to begin connecting the pipes.

Markers for the optical transfer lines were surveyed on the ceiling setting the stage for hanging of the transport piping next week. All back-leg stands were bolted to the floor becoming the first set of transport elements to be installed as planned. Jefferson Lab personnel continued the installation-planning efforts to the second floor area (first floor task list is in good shape and we are proceeding according to plan). Additional personnel were assigned to detail the electrical rack installation, hookup and site power coordination. A draft of the initial wiggler installation and alignment was produced and reviewed.

Fabrication of the high voltage tank proceeds on schedule. Design started for the crane rails and clean hood in the injector area. A site review for the clean room is tentatively scheduled for 25 Apr 97.