To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report, March 24-March 28, 1997

Date: March 28, 1997

Management

IR Demo Project activities this week included replacement of the HV stack assembly in the FEL gun and the placement of the first equipment (including RF and DC power racks) in the second floor of the FEL facilities.

Continuing our preliminary planning of the technology needed to upgrade the IR Demo to the 10 kW range, we have surveyed options for upgrading the injector cryounit to handle the required higher currents. Several options are available for using or modifying 500 MHz cryounits that were designed for Cornell, DESY or KEK. We are also exploring the available options for modelling electron beam transport in high acceptance lattices.

Jefferson Laboratory hosted a workshop this week (March 26-27) on "Contamination: its measurement and control in vacuum systems". The attendees (85) came from the accelerator and microelectronics communities and the supporting industries that supply related vacuum and contamination control equipment. The purpose of the workshop was to look for solutions to common contamination problems that limit the performance of state-of-the art microcircuits and accelerator structures. The workshop was judged a success by the attendees. As a side benefit, we were able to use the workshop to discuss the most recent results on SRF cavity R&D with colleagues from the SRF groups at the DESY, CERN, Saclay, and KEK laboratories.

We returned edits to Alan Todd at Northrop Grumman concerning upgrades to Jefferson Lab's IRFEL for incorporation into the overall Navy HEL Program Plan that Alan is developing.

Internal discussions started this week to preposition Accelerator Division resources for commissioning the IRFEL beginning 1 October 1997.

C. Bohn presented a colloquium to the Applied Sciences Department of the College of William and Mary entitled, "Phase Mixing and Violent Relaxation in Intense Charged-Particle Beams". The talk concerned the formulation and application of a theory of beam dynamics in the presence of nonlinear space-charge forces, such as will prevail in the IRFEL injector. William and Mary expressed interest in putting together a joint proposal for possible submission to the DOE's APT office, or elsewhere, to pursue various questions about the basic physics that arise in the context of the theory. Drafting of the proposal has begun.

Injector Test Stand

Regarding upgrading the photocathode gun:

Fabrication of the high-voltage stack was completed. Both the stack and the coated cathode support tube were successfully installed despite some annoying interferences due to machining inaccuracies. As of Friday (28 Mar 97) the gun was under vacuum once again. A cesium response was obtained on the gallium arsenide disk (which underwent an atomic-hydrogen cleaning as an alternative for the previous chemical-cleaning procedure). We stripped the beamline of diagnostic hardware in preparation for the high-vacuum bake, and we are working over the weekend preparing to start the bake early next week.

Progress on the photocathode drive laser consisted of enhancements to existing diagnostics. We anticipate receipt of a new-style electro-optical modulator late next week.

Regarding other ITS activities:

One ceramic warm window was installed in the cryounit. Cool-down is scheduled for Monday, 1 April, with cold testing to follow.

A test stand was developed to qualify ceramics prior to assembling them into completed warm windows. Qualification of ceramics in our present inventory will begin Monday, 1 Apr. 97. Window fabrication will follow selection of qualified ceramics.

Assembly and alignment of the multislit transverse-emittance diagnostic in the gun's experimental beamline was completed. It is located in the cross with the existing 50 micron slit, thereby allowing cross-calibration between the devices. We replaced the beam-viewer vacuum windows with larger-diameter windows to allow more robust camera placement and better field of view.

We also installed a computer in the Machine Control Center (MCC) with the capability to do video capture. This will allow acquisition of video signals during the May runs from the MCC.


Accelerator Systems

Regarding the beam-transport system:

Magnet Enterprises International, our contractor for the optical-chicane dipole magnets, received their copper and began tooling design. Everson Electric received their allotment of steel to start the torch-cutting step.

Bids for the reverse-bend dipole magnets and the 180-degree dipoles are due on Thursday, April 3.

The drawing-and-specification package for the injection-chicane dipoles was signed off and went out for bid today (28 Mar 97).

We continued to deconvolve the magnet-measurement data on the prototype trim quadrupole, and we also developed requirements for bringing the drawing package for the sextupole magnets up to production grade.

The design process is now underway for the corrector magnets needed at 43 locations around the machine.

The girder for the Y-chamber connecting the energy-recovery dump to the recirculation loop was signed off, and design started on the remaining stands and brackets needed in the injection line. Bids on previously signed-off stands needed for first light are due today, and bids for back-leg girders are due next Wednesday.

Multipole measurements on 8 of the main quadrupoles were reviewed and will be signed-off as qualified upon completion of measurements for strength characterization. At the same time 4 more quads arrived and 4 more of the total of 22 were shipped by the vendor.

Design continued on the vacuum chambers for the optical chicanes. The design package of the vacuum chambers for the reverse bends is being readied for detail design by Northrop Grumman. Specifications for vacuum pumps was prepared in preparation for going to our Procurement Department next week. Parts for the X-chamber connecting the injection line to the recirculation loop are in fabrication. Parts for the Y-chamber connecting the energy-recovery dump to the recirculation loop were sent out for bid. Design of the 180-degree vacuum chambers is nearing completion. A steam cleaner and portable clean room were purchased as part of the equipment we will need for installing the vacuum tubes per our cleanliness standards.

We worked to simplify requirements for the power supplies that will drive the injection/extraction dipoles. This should increase the probability for getting on-schedule delivery as well as lower the price considerably. We may be able to place the order by next Tuesday.

Regarding cryomodule fabrication:

Assembly of the first of four cryounits for the cryomodule is on schedule; its cavity pair is scheduled to be inserted into the helium vessel Monday, 1 April. The second cavity pair is installed in the Vertical Test Assembly (VTA) and is to be tested next week. The third cavity pair will be tested in the VTA following completion of testing of the second pair. The fourth pair is scheduled for assembly next week.

Alignment-tooling drawings for the cryomodule have been signed off, and material is on order for fabrication.

Regarding electron-beam instrumentation and controls (I&C):

In addition to installing the personnel-safety-system box duct and about 30 I&C racks in the FEL Facility, we procured the balance of the charge-coupled-device cameras and lenses required for FEL diagnostics. Design and documentation of the vacuum control system is complete and awaiting review. Preparations continued for the Personnel Safety System/Laser Safety System Review scheduled for next week (1-2 Apr. 97).

FEL Systems

Wiggler

STI Optronics received the final magnets from Shin-Etsu. They plan to measure them next week and assemble the wiggler by 4 Apr. 97. Final-certification measurements are scheduled for 28 Apr. 97 with delivery of the wiggler the following week. The layout design for the wiggler's vacuum- chamber stand is complete. We should have detailed drawings to check next week. The optical bench for the wiggler and 90% of the other wiggler-support components have been received. Assembly will begin next week.

Optics

As is summarized below under "Facility", most of the optical transport pipe was hung in the accelerator enclosure of the FEL Facility.

Several parts for the optical cavity assembly were not built properly, and are being rebuilt. The Mach-Zehnder interferometer we are considering for cavity-length monitoring was moved to the Test Lab and set up with a 16 m round-trip path length. Even with vibration from the HVAC, it appears to be stable enough to work properly. Tests are slated to begin next week.

Operations/Commissioning

Possibilities for improving the rf-phase-reference system of the photocathode drive laser were developed. The objective is to reduce the laser's high root-mean-square phase error. The circuit is observed to oscillate at around 800 Hz, corresponding to the second pole in the system. Plans are, by 22 April 1997, to decide on a set of experiments to try to solve the problem.

In addition, we began to organize the experimental plan for the ITS during May. The "MUST" for this run is to measure transverse and longitudinal emittances, as well as bunch length, at bunch charges of 1 pC, 60 pC (corresponding to first light), and 135 pC (corresponding to full power). In addition, a series of photocathode-lifetime tests are planned, as well as possible experiments at gun voltages exceeding 350 kV. Dates have been set for 24 hour operation in the ITS.

Facility

Even monsoons on Wednesday didn't slow a week of rapid progress on the building. Most contractor effort is now complete downstairs with only touch-ups and punch-list items remaining. The principal downstairs accomplishment this week was the installation of rails around the injector and wiggler pits. Work by Jefferson Lab crews included hanging the optical transfer line except for one spot of interference with the sprinkler lines. It still remains to complete the welding of the optical transfer line, and keep-out zones were established for the optical transfer line. Welding and leak-checking of the cryogenic transfer lines continued on schedule. Progress upstairs was substantial with electrical and plumbing installation continuing all over the Facility. By the end of the week conduits and rough plumbing in the east end were 80% complete, and roof drains more than 50% complete for the whole building. Studs were placed around the entire perimeter of the second floor. Exterior wall panels covered the west end and were proceeding down the south side of the building. HVAC duct was hung, 90% complete. Interior stud bases were attached to the concrete for 50% of the walls, and work commenced on interior studding. Before the exterior studding was finished we took advantage of the easy access to move equipment to the second floor by forklift. We placed over 35 electrical racks upstairs including low-level rf controls, trim magnet supplies, diagnostics racks, the high-power rf amplifier, and a high-voltage rf power supply. Work commenced on fitting the rf waveguides into the penetrations. We also set two workbenches in the area and moved the WSMR optics into the Navy lab for temporary storage. Modifications were made to the placement of interior electrical transformers to provide better access for maintenance, and a storage cage was ordered for tool security. Phone-line installation was ordered.

An on-site review for the FEL Facility clean room is scheduled for Wednesday, April 2. Design work for the ancillary components of the high-voltage power supply is started.