MEMORANDUM


To: J. Cook, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IR Demo Project Weekly Report, March 9-13, 1998

Date: March 13, 1998

FEL Management

Highlights for the week include (1) completion of the bake cycle for the gun and start of its high- voltage processing following its reassembly; and (2) completion of the initial longitudinal alignment of the FEL optical cavity.

Draft Field Work Proposals (FWP's) for FY 99-00 FEL activities were sent to the DOE BES Program Office and our collaborators for review. One FWP dealt with the design and implementation of beamline infrastructure that would support IR spectroscopy in the user lab. The second FWP dealt with extending the capabilities of the IR Demo to the far-infrared.

On Thursday, March 12, Howard Schlossberg, a program officer from AFOSR and Henry Helvajian from Aerospace Corp. visited the lab to discuss laser processing applications with the IR Demo.

FEL Installation Activities

Highlights for this week include:

Alignment of the optical cavity was finished.

The first 180 bend vacuum chamber was removed from its magnet to install a view port and cross hairs on it as diagnostic aids for energy recovery. Plans are to reinstall the chamber this afternoon and to pump down the region on Monday.

Recertification of the Personnel Safety System was completed.

A SEG block was placed over the insertable dump at the end of the recirculation loop. Low- conductivity water is scheduled to be connected today.


FEL Commissioning Activities

This week was devoted to continued preparation for resumption of commissioning. Bake of the gun is complete, and high-voltage processing commenced last night, progressing to 385 kV. Plans are to go to 420 kV tonight and let the gun set at that voltage for several hours. Plans are to turn on electron beam at swing shift Monday, 16 Mar 98. The basic task is to get 2 µA, 38 MeV beam down to the straight-ahead dump as expeditiously as possible, hopefully by owl shift Thursday, then install the GEN target chamber Thursday and Friday, then irradiate GEN targets through Wednesday of next week.

As wiring for the Machine Protection System (MPS) progressed yesterday, problems with integrating various subsystems arose. They are being worked out with the goal of completing the MPS before Monday turn on.

All first-light magnets are now in place except the oval air cores, one of which goes on each optical chicane. At present there are spare CEBAF air cores at these locations, and the spares are sufficient for supporting irradiation of the GEN targets.

We still need to finish preparing the "operator page" (www posting of viewer images) and initial save/restore file (from PARMELA simulation). B. Yunn discovered an inconsistency with how PARMELA establishes cavity phases and is in process of verifying all of the calculated machine settings up to the wiggler location. D. Douglas awaits handoff from Yunn so he can update his spreadsheet and calculate all of the post-cryomodule 60 pC settings and beam dynamics.

An extensive set of higher-order-mode measurements in the FEL cryomodule cavities indicates many more resonances are present than in the geometry of the conventional CEBAF cryomodule, and one question was whether cross-coupling between cavities was the cause. The data suggest that cross-coupling is weak, at the 80 dB level. Rather, the lesson seems to be that a small change in geometry can lead to considerable change in Q of strong modes and large change in Q of weak modes. For example, the strong 1890 MHz mode has Q~10^5, about ten times larger than in the original CEBAF test cavities, and the weak 1730 MHz mode has Q~10^7, about 1000 times larger than in the original test cavities. For the cryomodule itself, the beam-breakup-threshold current is estimated to be about 60 mA (i.e., >>5 mA) assuming a somewhat pessimistic frequency distribution in the eight constituent cavities.