1 2 3

To:

cc:

From:

Subject:

Date:

J. Cook, D. Helms, W. Skinner

Division (M7), FEL Coordination Group

F. Dylla

IR Demo Project Weekly Report, May 11-15, 1998

May 15, 1998

Management

This week was not a productive week as far as machine commissioning activities were concerned. Most of the week was devoted to diagnosing a problem with the photogun. By week's end, circumstances forced us to prepare for replacing the photocathode. This will necessitate a break in electron beam operations for most of the next two weeks. Nevertheless, we note that the cathode that will be replaced served us very well during the past 7 weeks of operations. As detailed in our previous weekly reports, we learned quite a bit about establishing stable, mA level beam from our first high current operations.

As noted in the commissioning and installation reports that follow, the down time this week and the projected down time over the next two weeks are being used to complete installation/check-out tasks and to prepare detailed "first light" procedures based on our commissioning experience to date.

The first shipments of user equipment for the polymers lab and metals lab were shipped to us this week. The lead scientists from DuPont, Armco, Virginia Power and Northrop Grumman will be visiting the FEL Facility next week to begin the process of installing this equipment. Our goal is to have at least one installation in each of these two labs operational by the middle of June so that the respective user groups can take advantage of the alignment laser system which is now installed in the optical transport system and to be positioned for use of FEL light later in the summer.

Installation Activities

The last DY 180º Bend Magnet is assembled with its vacuum chamber and is scheduled for installation on Monday 5/18/98.

Tests for the high power RF windows for the 1/4 cryounit are scheduled for this weekend using the injector 50 kW klystron.