MEMORANDUM

To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report, May 19-23, 1997

Date: May 23, 1997

Management

The photocathode gun was successfully baked this week, allowing gun operations to resume next week. With the schedule slip caused by the need to replace the cathode in the gun and one of the warm windows in the cryounit, options for a revised ITS schedule were examined this week. We have a firm date for placing the cryounit in the FEL Facility by July 1 for cryogenic testing. We need to work out the last possible date of having the gun and the RF systems consistent with maximizing gun test time and using the installation labor as efficiently as possible.

The monthly report for the IR Demo project for April 1997 was distributed on May 22. Earned-value cost and schedule variances continue to grow until we can take credit for magnet deliveries by mid-summer and the recent shipment of the wiggler (pending resolution of the shipment problem noted last week).

Preparations continued for the two major project meetings in June: the second MTAC meeting on June 9-10 and the next LPC Workshop on June 25-26. A preliminary agenda and travel logistics were distributed to MTAC on May 20. Comments on the preliminary agenda were received from the MTAC chair, Adm. Baciocco, and J. Albertine. Speakers are being identified for the LPC Workshop.

At the second Virginia Technology Summit, held in Richmond on May 21, the FEL Program was given high visibility in presentations by Senators Robb and Warner, the two gubernatorial candidates from Virginia, and from the group leader for a task force on high-performance manufacturing initiatives.

Injector Test Stand

Regarding the photocathode gun:

Bakeout of the gun was completed. The gun was then reassembled, NEG pumps reactivated, NF3 recharged, SF6 tank and high-voltage (HV) cable reinstalled, and SF6 recharged. We started HV processing Thursday morning, 22 May 97. We are taking the gun to 420 kV for 12 hours as was done last week, and then will do a 20-hour cathode heat-cleaning cycle at 580 C. This will be followed by manufacture of a cathode Sunday or Monday after the cathode area has cooled sufficiently. This should allow field-emission measurements Tuesday, May 27 after which operations with beam would ensue.

Cursory examination of the cathode under a microscope revealed that it was "frosted" (the arsenic was vaporized out of its surface). This was probably caused by heat cleaning at too high temperature when we were attempting to heal the field emmission sites observed last week (we went near 700 C). That is why we are going back to our standard backout temperature of 580 C. At this time, we still do not know definitively what was causing the field-emission problem reported last week although etching caused by the removal of arsenic could certainly lead to field emmission sites

Regarding the cryounit:

Except for the Cavity Window Temperature (CWT) alarm, the interlock checks have been completed for the cryounit in preparation for planned testing with warm windows. The cryounit is presently warm and must be cold in order to set the CWT alarm. We found that the new spare 50 kW klystron has a loose input connector and cable. We contacted the vendor about the problem, but have yet to hear back from them. If need be, we will contact them again next week.

Regarding development of warm ceramic windows for the cryounit:

In view of the string of recent difficulties with the development of robust warm ceramic windows, and in view of the short schedule, we reformulated our development plans. The earliest date for having two ceramic warm windows qualified for installation and subsequent testing in the cryounit is June 14, which may or may not (probably will not) leave sufficient time for the tests prior to moving the cryounit to the FEL Facility. If not, then we will do the remaining tests of the cryounit in the FEL Facility. A synopsis follows.

Short Term: Produce six 50 kW RF warm windows based on the existing design. They have performed satisfactorily under "normal" operating conditions. Failures encountered in the most recently produced warm windows are attributed to off-normal operations that led to run-away conditions, depositing extreme amounts of RF power into the windows.

Scheduled activities are:

- Complete by May 29, 1997: Prepare in house flanges for e-beam welding.

- Complete by June 2, 1997: Remove Japanese ceramic from flange (e-beam weld leaked) and reprocess it, to include removal of nickel foil, metalization of ceramic, and characterization of ceramic in resonant ring. Select four lowest-loss ceramics from existing inventory, send them out for metalization (along with Japanese ceramic), and characterize them in the resonant ring. Fabricate two additional flanges to increase throughput of window fabrication and rework.

- Complete by June 5, 1997: Braze five nickel eyelets to ceramics.

- Complete by June 6, 1997: E-beam weld five ceramics into flanges and leak check.

- Complete by June 10, 1997: Resonant-ring-test five window assemblies to 50 kW in air.

- Complete by June 14, 1997: Test two windows in vacuum fixture to 50 kW. - Complete by June 18: Test two windows in vacuum fixture to 50 kW.

- Complete by June 23, 1997: Test two windows in vacuum fixture to 50 kW.

Medium Term: Two medium-term programs are ongoing to provide alternative solutions for RF warm windows. (1) The BeO Northrop Grumman windows -- Ceramics are in-house, flanges are in production, and final assemblies are due to be completed at the end of June. (2) Redesign of Jefferson Lab windows -- The design uses a thin wall, water cooled, copper waveguide support for the ceramic braze joint. Ceramics have been ordered from Wesco and will be ground locally. Prototype assemblies are expected in August 1997.

Back-Up Plan: Enhanced polyethylene windows -- Cooled polyethylene windows could have an extended power limit to allow for operations at ~ 10 kW. The existing polyethylene window is rated for 8 kW and is borderline for FEL first light. Cooling can be incorporated into the exterior waveguide assembly. It would be trivial to install and could be accomplished on a cold cryomodule. Implementation of this would be required in Feb-Mar 98 if ceramic windows have not surfaced beforehand. This would support first light at 1.1 mA average current and provide additional development time.

Accelerator Systems

Regarding the beam-transport system:

Procurement of dipole magnets are generally proceeding on course. Everson Electric was having some minor difficulties constructing the first-article optical-chicane dipole, but we are working with them to resolve the difficulties. Designs for the sextupole magnets are complete, and they are in procurement. The long Panofsky-style trim quadrupoles are out for bid.

We completed measurements on the mu-metal air-core corrector magnet to quantify saturation and hysteresis effects. There were no signs of saturation, a favorable finding. However, there is nonnegligible hysteresis. In light of the hysteresis data, we are in process of determining where along the machine these correctors could be used.

As reported last week, we also are having another prototype air-core corrector built by Syntronics. This vendor supplies magnets based on a choke-coil design for medical imaging, an application that requires magnets having inherently low harmonics, and therefore high field uniformity. Thus, this design seems like a good candidate, and we may be able to modify the prototype in-house, if needed, in conjunction with measuring it.

The design drawings of the vacuum chambers for the optical chicane are complete. Welding on a six-foot-long, trial square vacuum chamber has begun, from which lessons learned will be used for the X and Y chambers which are ready for fabrication. Northrop Grumman continues to make good progress on the arc vacuum chambers.

Back-leg girders are being assembled and readied for installation.

We made good progress on the assembly drawings for the optical chicane and first-light beam line. Drawings of the final girder for the injection line were finished. Check prints will be available on the beamline just upstream and downstream of the cryomodule next week. Preliminary work has begun on the first-light dump stub. The first-light dump is being fabricated in our Machine Shop. We also made good progress on the insertable dumps (Faraday cups).

Regarding cryomodule fabrication:

The two remaining cavity-pair assemblies completed testing in the Vertical Test Assembly. Both passed their RF performance criteria and are in final leak check prior to turn-over for assembly in their respective cryounits. Cryounit #1 is complete and turned over for assembly into the cryomodule. Fabrication of the second cryounit is progressing on schedule. In general, the schedule for cryomodule assembly remains tight but feasible.

Regarding electron-beam instrumentation and controls (I&C):

Upon closer inspection, there was some question about whether some of the repaired welds of electrodes to the chambers of the stripline beam-position monitors (BPMs) were sufficiently robust to preclude intermittent shorts. Consequently, we decided to inspect more carefully using a borescope and to hit again some of the more dubious welds with the e-beam welder. Though the e-beam welding has been challenging, it seems generally to have worked. Moreover, there was some concern about how to clean BPMs prior to incorporating them into assembly of the beamline girders. We decided to clean them with acetone and alcohol in an ultrasonic cleaner, followed by drying with a clean, dry gas, and then bagging. We are close to turning over 13 BPMs for assembly into the back-leg girders.

The cable pull from the Machine Control Center to the FEL Facility is complete, and all of the fiber-optic connections have been made and checked. The Hewlett-Packard servers have arrived and will be installed in the FEL Facility as soon as power is available (in about two weeks). The networking hardware is in process of being installed.

The racks in the equipment gallery and in the control room of the FEL Facility have been moved into position and are being wired.

Documentation of I&C activities on www continues to progress.

Regarding RF systems:

Hipotronics, the vendor for the 225 kW variable power supplies that will drive the cathodes of the 8 kW klystrons powering the cryomodule, is now assembling the first unit. They expect to start testing it next week, and we might be able to witness acceptance testing as early as the following week. If all goes well, they could ship the first unit about June 9.

FEL Systems

Injector Reinstallation

All components for the injector crane rail are on order. Delivery and installation in scheduled for next week. A new air handler unit has been located by Clean Air Technology. It will be installed after the rest of the clean room. Work on the clean room is still scheduled to start May 28. Design work continues on the drive laser optical transport.

Wiggler

A preliminary dimensional check of the wiggler indicates no problems with the vertical alignement of the jaws (this is the direction which would be affected by a vertical drop). Measurements of the fiducials to gauge the longitudinal alignement will be carried out next week. The machine shop has succeeded in making wiggler vacuum tubing with the proper cross section and flatness. Welding of test pieces is scheduled for next week. All the remaining drawings for the wiggler vacuum chamber and the assembly drawings for the wiggler girder were signed off.


Optics

We received 5 micron mirrors from Rocky Mountain Instrument this week (two months early) and will ship them to China Lake for testing (reflectance and scattering, ROC, figure, roughness). The 3 micron mirrors (from Research Electro-Optics) are being coated this week, and we expect them in several weeks. Some of the calcium fluoride windows used in the optical transport system also arrived. Designs for items mentioned last week are progressing. We are nearly complete with a design for enclosures that will permanently surround the optical cavity assemblies and minimize dust in their vicinity. The bellows assemblies have gone through two of the three steps required to be brazed to the cooled mirror holders. The optical table that will be installed in the new clean room arrived and was placed on the second floor of the FEL building. Several of us attended the Exhibitor's Show at CLEO and met with current (and potential) vendors of optical equipment including the drive laser upgrade.

Commissioning/Operations

Detailed plans were formulated for the content and manning of upcoming gun experiments. The content is essentially unchanged from earlier plans that had been postponed due to the latest field-emission problems. However, there is uncertainty whether it would be prudent to spend the time necessary for executing all of those original plans, i.e., to characterize the longitudinal and transverse beam properties at bunch charges pertaining to "zero current", first light, and full-power operation, then to look at photocathode lifetime, performance at higher voltage, performance at other bunch charges, etc. We will decide on priorities as we see how well the latest gun configuration works.

The newly configured gun includes the cathode-anode spacer for lower cathode-stand-off voltage, which means the simulations for full-current beam from cathode to wiggler need to be redone. We already have some results for the first-light beam from earlier efforts, and have initiated the full-current study.

Having settled on an overall commissioning process, we made a first cut at defining commissioning "teamlets" to turn on various IRFEL systems. This is one of the first steps in lining up necessary manpower, an effort that will evolve continually in the coming months.

Facility

Progress on the FEL Facility continues to be rapid. The glass for the sky light and front entrance is complete. The tile in the equipment gallery has been delayed due to illness, but it should be completed soon. Fibercast piping for low-conductivity water (LCW) between the FEL Facility to the south access building is being finished. This will be connected to the CEBAF LCW system for clean up over the long weekend. The survey crew continues to place stands in the injector and linac areas. The magnet stands for the optical- chicane and wiggler supports are being grouted. Utility work in the control room is nearing completion. Drywall in both bathrooms is complete and ready for painting. Drywall in the upstairs lobby is nearly complete. Work began on the elevator this week. The shaft sleeve has been prepared and inserted, and the remaining work should take about 2 weeks. All of the transformers wiring is complete. Wiring to most wall outlets is in place but not yet terminated. The bulk of the AC power should be available by the middle of next week.

Progress on the cryogenic system is proceeding on schedule. We have now completed welding and leak testing of the 2K liquid-helium supply and return circuits all the way from the Central Helium Liquefier to the injector location in the FEL Facility.

The beams for the injector cranes have been ordered, and the drawings should be completed by COB today (May 23). Plans are being made to load-test both overhead cranes.