MEMORANDUM
To: J. Albertine, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IRFEL Weekly Report, May 27-30, 1997
Date: May 30, 1997
Management
The highlight of the week was a successful re-start of photogun
measurements on the Injector Test Stand. Excellent progress was
made on characterizing the performance of the gun at 350 kV.
Details are given below in the ITS section of the report. Also
of note: on the basis of further inspection and dimensional checks
on the wiggler, we accepted the device for use in the IR Demo.
Lots of high level activity occurred in Washington this week concerning
potential FY98 funding for the FEL program. Senator Warner requested
a briefing from ONR management on FEL R&D for Naval applications.
A follow-up briefing will be held on Monday, June 2, with Adm.
Baciocco (the chair of MTAC), and representatives from SURA and
Jefferson Lab.
F. Dylla was invited to make a presentation at the Combustion
Science Workshop held this week in Chantilly, VA sponsored by
DOE-BES. Several attendees expressed interest in using the IR
FEL for combustion research.
Injector Test Stand
Regarding the photocathode gun:
High voltage processing of the gun at 420 kV was completed by
week's end. Twenty hours of heat cleaning of the cathode was completed
and a new cathode was fabricated with a measured quantum efficiency
of 7.2%. The initial cathode degradation was not bad (40% in
first 24 hours of operation). The dark current (field emission)
was measured at 1.3 nA at 350 kV cathode voltage; however, measurements
indicate the emission current is doubling in magnitude for every
10 kV increase in cathode voltage. We performed bunchlength measurements
at 1, 10, 60, and 135 pC at 350 kV. Transverse emittance measurements
were performed at 1, 30, 60, 100, 135 and 150 pC/bunch. We have
observed some beam scraping during the transverse measurements
and subsequently verified the light box as the location using
Geiger Muller tube detectors. To correct the beam scraping, we
are investigating possible changes to the ITS. Modelling has
been started to address the issue.
Regarding development of warm ceramic windows for the cryounit:
Warm windows have been tested and qualified in the resonant ring
and vacuum fixture. These windows are limited to 10 kW operation
levels which will support first light operations. These will be
installed on the 1/4 Cryomodule Monday 2 June. A short cold test
cycle on the 1/4 Cryomodule will follow to characterize window/waveguide
performance. Work continues on the production of 50 kW warm windows.
Accelerator Systems
Beam-transport system report, 5/3097:
Fabrication of dipole magnets is proceeding on course. All 16
Optical Chicane coils are on hand and most machining is done on
the cores. The first article Injection Chicane coil (DU) was
received and most machining is done on the cores while they await
the mu metal delivery. PECO has most of the incidental parts
ready for 180 degree dipoles and reverse bends and the pole pieces
should be back from heat treatment next week to begin final machining.
Everson Electric will glue up a few trial pieces before they
retry gluing more optical-chicane dipoles and proceed with assembly.
The sextupole core bids came in high. We are clarifying our requirements
to reduce the price with the responsible bidders. The Trim Quad
design package is in checking. The bids for the long Panofsky-style
quadrupoles for the recirculation dump are due today.
Discussions with D. Douglas indicated the most difficult high
aspect ratio correctors in the arcs and the phasing dipoles may
utilize the mu metal design even though hysteresis is present.
Additional analysis indicated that reducing the maximum required
field integral by 44% is a prudent change to the requirement for
the remaining air core correctors. To home in on a cost effective
air core concept that meets specified harmonics, we are measuring
a mock up, made of four coils in an approximation to a cosine
distribution. Early results are encouraging. The prototype air-core
corrector built by Syntronics will undergo testing Monday but
just from initial impressions, results may not be encouraging.
We will start the TOSCA magnetic modeling once we have blocked
in a direction to go. At the same time, AML a Florida company
that specializes in precision field, air core magnets, is putting
together a preliminary proposal to produce most of the air core
correctors.
Parts for the vacuum chambers for the optical chicane are out
for bid and the chamber for the 180 degree dipoles was signed
off. Welding on the X Chamber for the Injection chicane started
this week. Northrop Grumman completed details for the first of
six Return Bed chambers. We will have to design the remaining
three chambers.
Stands for the Optical Chicane and the injector were installed
in the enclosure.
Regarding cryomodule fabrication:
The fourth and final cavity pair is expected to be turned over
to for cryounit assembly the beginning of next week. The third
cavity pair has been turned over to cryounit assembly. Tuners
and instrumentation are being installed and a normal cryounit
assembly is expected. The second pair turned over has been inserted
in the helium vessel and assembly continues without issue. Cryomodule
assembly is progressing without issue with the first cryounit.
Thermal shielding has been installed and rough alignment completed.
The return end can beam pipe is scheduled for installation the
beginning of next week.
Regarding electron-beam instrumentation and controls (I&C):
Beam Instrumentation: Documentation continues. The beam viewers and BPMs have been turned over to the installation group for installation with the beam tubes and magnets.
Safety: The cable way and conduit is complete for the personnel safety system, and the cable installation has begun. This is in preparation for the cooldown of the Quarter cryomodule July 1. Preparation continues for the Machine Protection System design review next month. The logic controllers have arrived for the laser safety systems. These will be assemble in July for installation in each of the optical labs.
Controls: The network hub and server computers are being installed in the FEL building. Also the network connection to the cryogenic control racks from the central helium liquifier (CHL) plant is in progress. These racks will be powered and controlled from the CHL for added reliability; they are an extension of the CHL systems. Software continues to be developed and debugged in the injector test stand.
DC Power: Trim rack cabling is being staged in the north linac,
two of the four sets of cable are ready for installation. These
cable the 32 channel power supplies to the distribution boxes
in the tunnel.
Vacuum controls: The control chassis are being fabricated. The
four equipment racks are progressing well, they should be powered
up next week. The control cards for the ion pump power supplies
are being fabricated now.
Regarding the cryogenic distribution system:
All major transfer line welding is complete. All vacuum jackets
are being pumped. I&C engineering and fabrication are both
complete. Installation will be completed after 1/4 cryomodule
is in the FEL building. 4 of 5 U-tubes for CHL connection are
complete. Number 5 is 75% complete U-tube designs for the 1/4
cryomodule in the FEL building were released. The shield return
U-tube is 60% complete but on hold for transfer line installation.
Final connections of gas lines at Flex can are being worked.
Gas lines in FEL User Facility Accelerator enclosure are complete.
We are on schedule for July 1 cooldown. Detail plans still need
to be made.
FEL Systems
Injector Reinstallation
The high voltage tank had to have its legs shortened to correct
a design error. This was completed by weeks end. Continuing
delays with the delivery of the air handling unit for the clean
room have moved the completion date to the week of June 16th.
We have obtained permission to install the laser safety system
and the new optical table in parallel with the final installation.
This will minimize the overall schedule slip. The room itself
was installed this week and looks quite good.
Wiggler
The wiggler has been accepted from the vendor STI Optronics.
Measurements indicate no damage to the wiggler from shipment.
The machine shop is making progress on the wide wiggler tubing
and is planning for a test weld next week. The wiggler vacuum
chamber support has been ordered and is due in mid-June.
Optics
FEL
Inspection of the transmission curves for the mirrors from Rocky
Mountain Instrument indicates that two of the three sets most
likely will not meet specifications (the R=99.7% and R=98% mirrors),
so they were returned to the vendor. The optical collimator has
been awarded to a local machine shop. Designs for some mirror
stands will be signed today (5/30). The bellows assemblies are
brazed to the cooled mirror holders, and we will begin assembly
in a clean room next week. The stands for the optical tables
were grouted, and the survey team has alignment fiducials for
the upstairs optical transport line.
ITS
The laser was operated for over 60 hours in support of gun experiments.
The power output was quite stable over this period. We received
some new information on modulator biasing that raised the overall
extinction ratio of the two variable-speed modulators by over
a factor of two. The second "dry" EO modulator was
also installed in the beamline. The divide-by-two EO modulator
suddenly quit responding to changes in the DC bias, the unit was
returned to the vendor.
Commissioning/Operations
The main consequence of the experimental finding in the ITS that
there is scraping of the outer portions of high-charge bunches
inside the light box is a reduction in the measured transverse
emittance of these bunches. The outer parts of the beam are weighted
heavily in the coordinate and velocity moments that comprise the
transverse emittance. Consequently it is more difficult to compare
the experimental results with scraping to numerical simulations
wherein scraping is absent. In view of this development, we embarked
on a series of numerical simulations to assess whether scraping
can be significantly reduced or eliminated by varying the laser
spot size at the photocathode. For instance, one would expect
space charge to have less influence in a larger beam, so perhaps
increasing the spot size will reduce scraping. At this writing
(noon Friday, 30 May 97), the investigation is in progress.
Simulations from cathode to wiggler were also done by including
the cathode-anode spacer for lower electric field at the cathode,
as is now the case in the ITS. The present status is that it
has been easy to find settings that deliver the required beam
at the wiggler, but the bunch lengths in the injection line are
longer than desired given the performance specifications of the
interferometric bunch-length diagnostics that will be installed
there. These simulations are continuing in an effort to find
solutions with acceptably short bunches in the injection line.
We made considerable progress establishing locations and types
of weak-field corrector magnets based on the measured performance
of various prototypes constructed to date. This activity is continuing,
and our goal is to finish it very soon, pending the outcome of
additional measurements in our Magnet Test Stand of existing prototypes
that have been slightly modified for what hopefully will be improved
field quality.
Facility
A small army labored through the week trying to bring the upstairs
to a finished state. Despite several days delay in getting started
on floor tiling, two labs and a large fraction of the RF gallery
were tiled by week's end. Several other areas are prepared and
will be done shortly. Electricians spent the week pulling cable
to outlet boxes in all the labs from the breaker panels. Drywall
was completed in the break area and the stairwell. Only the downstairs
lobby and touch-ups remain to be drywalled. Glass is placed in
the stairwell skylight and double doors are on the front of the
building. The facility is fully enclosed now. Tiling has begun
in the bathrooms. The hydraulic piping was lowered into the main
elevator shaft. That work is 50% complete. We expect the elevator
to be complete in 2 weeks and ready for inspection. Despite having
to co-exist around tilers, electricians, etc., the photo-injector
clean room was delivered, assembled, and installed except for
electrical hookup, and installation of the air handler. The air
handler is still about two weeks from being installed. The safety
system box duct was installed in the upstairs and cables are being
pulled to the downstairs duct from the communications room racks.
The second (and final) line of cable tray was 20% complete upstairs
by the end of the week. Berming is 80% complete outside. Downstairs
grouting is underway on the magnet stands previously installed.
More stands are due today (5/30/97). The gun HV tank was discovered
to have been constructed 2" too high so welders cut the legs
and reinstalled the tank. Installation of the power supply should
get underway next week. Both the supply and return cryogenic
transfer lines were welded to the lines installed last week in
the sleeves and are undergoing leak check. A power outage is
scheduled for Saturday to energize the upstairs electrical panels.
Over the holiday weekend the low conductivity water circuit was
hooked up to the CEBAF main system and pressurized. No problems.
We now have cooling water available in the building. Since the
tiling is nearly complete in the RF gallery, the LCW lines can
be finished in the coming weeks as welders are available.