MEMORANDUM


To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report November 18-22, 1996

Date: November 22, 1996

Management

The project financial reports were prepared for the October monthly report which is planned to be released next week.

Preparations continued for three major upcoming meetings: the SURA Maritime Technical Advisory Committee meeting on Dec. 17-18, the LPC Workshop on Jan. 21-22, and the DOE FEL Review on Feb. 25-26.

A colloquium was presented at Argonne National Laboratory on Nov. 22 on the subject of materials processing with high average power light and the FEL development program at Jefferson Lab.

A first draft of technology timelines leading to a MW-class FEL was prepared, and it will be refined in the coming weeks as part of the preparations for the upcoming meeting of SURA's Maritime Technical Advisory Committee.

Injector Test Stand

Regarding operation of the 250 keV gun:

We made several transverse-emittance measurements with the laser beam displaced off-axis on the photocathode. These measurements were done to test the viability of running the FEL using off- axis portions of the photocathode to reduce the number of recesiations and thereby improve the overall availability of the gun. Preliminary results indicate that the emittance varies significantly as the laser beam is moved across the photocathode. We have initiated numerical simulations to understand the mechanism.

We took three more sets of publication-quality data using the 4-mm-diameter, 2-mm-diameter, and 1-mm-diameter apertures on the laser beam. We then recesiated the photocathode, once again achieving a quantum efficiency of 4%, and resumed taking data.

Regarding fabrication of the new high-voltage stack:

All three ceramics (Serial #1, #6, and #2, in that order) have now been sprayed a second time in an effort to drive their conductivities to a range where we are sure the field-emitted current will drain off and the uniform gradient will not be altered excessively. The vendor in California has had a difficult time taking reliable measurements to determine if their resistivities match. The measurements are sensitively affected by atmospheric conditions, and they have been complicated by rainy weather and a damp atmosphere. At week's end a retest of #6 after heating in an oven and purging with dry nitrogen showed that its resistivity matches that of #1 to within 20%, an improvement over the previous test which showed a 100% difference. We are assessing whether to do a final qualification test using vacuum facilities here at Jefferson lab prior to brazing the rings.

Regarding other progress, we decided to ship the rotisserie for ion implantation to LBL and sent it by air freight. The new mid-voltage ring for the stack is being polished at 9 micron diamond grit on one shift. The samples of ion-implanted aluminum oxide coupons provided by LBL need to have come conductive paths on their edges removed by bead blasting.

Regarding testing of the injector cryounit:

Data reduction for the cryounit test was completed. The data support a nominal operating point for which the accelerating gradient of the first cavity the electron beam sees is 11 MV/m, and the accelerating gradient of the second cavity the beam sees is 9 MV/m. These are consistent with earlier testing of the cavity pair prior to its installation in the cryounit's cryostat. However, the temperature profile in the waveguide deviated somewhat from predictions, and this detail will be monitored in future superconducting rf tests for the FEL.

Accelerator Systems

A punch list was compiled to enumerate the few details that still need to be resolved prior to a formal freeze of the top-level machine drawing. Conceptually, the most important detail is a slight revision of the second recirculation bend to make it more compatible with upgrade paths and thereby reduce the work that will be necessary to reconfigure the machine whenever future upgrades are done. We anticipate being able to institute the freeze by mid-December, at which time we will establish a change-control process for the overall layout. The change-control process for the diagnostic suite is already in effect and continues to work smoothly.

The design of the IRFEL cryomodule was updated based on test results of the cryounit.

A thorough test of the low-level rf system for the IRFEL took place on 21 November on the main machine at the South Linac 21 location. The test was very successful, resulting in a short punch list containing only minor hardware modifications.

We recently modified the specifications of the power supply for the 8 kW klystrons to make them more compatible for installation and use in the FEL Facility. The procurement package is back on the street. We have given the vendors a short time to respond.

The rf racks for the IRFEL arrived this week.

The process of carrying out an internal review of the design of the dipole magnets commenced. Some of the specifications needed to be solidified based on new data relating to suppression of fringe fields in the prototype dipole. A staff member traveled to Northrop Grumman to finalize details of their design of the optical-chicane dipoles. The plan is to close out this review hopefully next week, but at latest during the first week of December.

Quotations on the coil assemblies for the weak-field quadrupole magnets were received and are being evaluated. Fabrication of the prototype trim quadrupole was completed. The contract to fabricate the core of the prototype sextupole magnet was awarded, and we are expecting to receive it by mid-December.

Detail drawings of the injector vacuum pipe neared completion and are undergoing a final evaluation of impedances. Cable tray and utility layout is nearing completion.

Work has continued to characterize the expected performance of beam-position monitors around the IRFEL in preparation for an internal design review. In view of schedule conflicts, we slipped the review date from 22 November to 27 November.

The Software Group put together a detailed design of the configuration of computer hardware and networking that is needed to control the IRFEL, to include specifications and cost estimates.

FEL Systems

Wiggler

A meeting was held to settle the design of the wiggler support at the 85%-level. This is preparatory to ordering the optical bench. We are in the process of developing the specifications for the vacuum chamber and its support.

Optics

We ordered more diagnostic equipment (e.g., a power meter, infrared detectors) and more catalog items for the optical cavity, such as the alignment He-Ne lasers and the linear translation stage. We are requesting new quotes on optical transport mirrors, as we are now interested in getting gold- (instead of silver-) coated optics to cover the full range of expected wavelengths. Our intent is to order these mirrors next week.

Operations/Commissioning

To date, procedures have been written for single-pass commissioning of the IRFEL hardware from the gun through the cryomodule and into the energy-recovery dump. From here, the process will continue as we work our way to the straight-ahead first-light dump and then through the recirculation pass.

Facility

Work on the interfloor area continued with gravel being placed in the entire floor and approximately 1/3 of the area covered to height with sand. Penetration tubes were placed and cut to length in the filled area. Positioning of the lights in the tunnel was readjusted based on the latest layout information. Wiring was begun in the tunnel. The filling and layout of the loading dock and lobby area continued as did the truck ramp retaining wall layout.

We continued working on the layout of the injector in the FEL Facility, and we resolved interferences with lights. The budgetary quotes for the 600 kV power supply tank came back and are within budget. Minor changes are being made to the drawings, then we will prepare the final bid package and get the final quotes. Delivery is expected in 12 weeks. We received one bid for the new clean room at a price of 75-90 k$ and are still waiting for an estimate from the vendor who built the clean room in the Injector Test Stand for 39 k$.