MEMORANDUM
To: J. Cook, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IR Demo Project Weekly Report, October 13-17,
1997
Date: October 17, 1997
Management
The laboratory's quarterly scheduling meeting was held on Oct.
17 for priority ranking of project tasks for the next 15 months.
These meetings are used to arbitrate and allocate the laboratories
resources for these tasks. The contractual objectives for the
IR Demo Commissioning and Upgrade project remain first priority
goals for the laboratory.
At the Oct. 27-29 workshop on "Scientific Applications of
4th Generation Light Sources," five members of the FEL user
group will be presenting talks about IR FEL experiments.
A draft proposal is being prepared by a subset of the FEL users
for designing and fabricating User Lab infrastructure that will
support the proposals that are in-process. The proposal is being
prepared for submission to the SURA New Projects Committee at
the Nov. 5-6 meeting at the SURA Board of Trustees.
C. Bohn presented an invited talk entitled "Radiofrequency
Superconductivity Applied to Free-Electron Lasers" on Oct.
10, 1997 at the RF Superconductivity Workshop in Abano Terme,
Italy. He then gave a talk entitled "Overview of Jefferson
Lab's FEL Program" at Rossendorf Laboratory, Dresden, Germany
on Oct. 13, 1997. There, he discussed details and possibilities
for collaboration on Rossendorf's superconducting RF gun and superconducting
FEL projects. Geoff Krafft also gave an invited talk at a Diagnostics
Conference entitled, "Diagnostics for Ultra-Short Bunches."
Installation Activities
Highlights for installation accomplishments this week include
the following: removing the transmission line for the photocathode
gun's high-voltage power supply and redoing several leaky weld
joints (reassembly and testing are taking place today, Oct. 17,
1997); nearly completing installation of the 50 kW klystron systems
for the cryounit, with final interlock checks in progress; installing
and commencing tests of RF software on both the injector and the
linac; installing the 3 DU dipole magnets for the injection line
and its dump; and removing two optical chicane vacuum chambers
for rework of the mechanical interfaces for the beam-position
monitors.
Commissioning Activities
We are presently engaged in commissioning the injector. This
week's progress includes: heat cleaning the GaAs wafer and making
a new cathode; baking the beamline between the cryounit and the
differential pumping station to reduce the vacuum base pressure;
commissioning the water skid and controller for the buncher cavity;
operating both klystrons under software control and generating
RF into their waveguide shorts; and completing the software requirements
document for controlling the photocathode gun.
Regarding commissioning the accelerator as a whole, this week's
progress includes: completing the SAVE/RESTORE files for the magnets
and RF systems of the accelerator; successful high- voltage testing
of the first 225 kW variable power supply for the cryomodule klystrons
with a small load; and completing the software requirements document
for controls of the viewer/insertion device.