MEMORANDUM
To: J. Cook, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IR Demo Project Weekly Report, October 20-24,
1997
Date: October 24, 1997
Management
On Friday, Oct. 24 monthly reports (for September) for both the
IR Demo construction project and the commissioning and upgrade
project were distributed to the NRL and DOE Program Offices.
Also on Friday, the Chairman of SURA's Marine Technical Advisory
Committee (MTAC), Adm. Baciocco visited the laboratory for an
update on the FEL project and planning for the Dec. 9-10 MTAC
meeting.
Three more pre-proposals for basic science experiments with the
IR FEL were forwarded to the DOE-BES Division of Chemical Sciences
for review.
Installation Activities
The last vacuum connection in the injector assembly, between the
injector x-chamber and the linac cryomodule, was completed. The
linac is now under vacuum from the photocathode gun through the
linac cryomodule including the injector dump-line. Final alignment
of the injector beamline components was also completed.
The high voltage elbow for the gun power supply was reinstalled
after being removed for rewelding and leak-checking. It was leak
checked and now successfully holds the required static pressure
of SF6/N2.
The diagnostics for the wiggler vacuum chamber were cleaned and
installed. The completed wiggler vacuum chamber passed particulate
and leak-tightness tests.
Vacuum chambers that were removed last week from the optical chicanes
were modified for installation of beam position monitors. These
chambers are scheduled for cleaning this weekend and re-installation
next week. Vacuum installation activities continued for the energy
recovery and 42 MeV dump-lines.
Commissioning Activities
With successful re-installation of the high-voltage transmission
line for the gun, preparations are underway to start operating
the photocathode with the drive laser next week. Goals for next
week include: testing the photocathode with the buncher cavity
powered, verifying operation of the drive laser, and training
people on the respective controls and locations of the hardware.
The PSS for the cryounit was certified and low-level srf commissioning
of the cryounit commenced on Tuesday.