MEMORANDUM
To: J. Albertine, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IRFEL Weekly Report Oct. 21-25 1996
Date: October 25, 1996
Management
The September 1996 monthly report was finalized and distributed.
Interim milestones for the IRFEL Program were finalized this week.
They are serving as a communication aid in phasing the Accelerator
Division resources that will be needed for installation, alignment,
and checkout of the various subsystems.
The WBS managers began preparing for an informal review of the
status of the IRFEL Program by the Navy which is scheduled to
take place next Tuesday, 29 October.
A draft agenda was prepared for the first meeting of the SURA
Maritime Technical Advisory Committee on December 17-18.
Injector Test Stand
Regarding operation of the 250 keV gun:
We ran the gun for a 6-hour period at 1 mA average current, during
which the quantum efficiency (QE) dropped from 4.8% to 3.5%, with
the bulk of the change occurring in the first 45 minutes. The
data show an e-folding time of about 40 hours. The area of the
cathode used was 6 mm off center. It had an initial QE about
30% higher than the center of the cathode which was used for previous
tests. After the run, the relative QE of the center of the cathode
was remeasured and, within the accuracy of the measurement, found
to be unchanged. The effect of the solenoid on the emittance
of the beam exiting off-axis is still unknown, so we don't yet
know whether this additional current from the cathode is usable
for the FEL.
We continue to have problems with electro-optical modulators (EOMs).
Of the four in-hand, two have failed hard, and two do not meet
the specification but might be usable. Consequently, no thesis-quality
transverse-emittance data have been taken. We are working with
the vendor to remedy the situation and expect replacements sometime
next week. Meanwhile, a schedule to cover multiple-shift operation
has been posted in anticipation of laser availability. Presently
plans are to explore gun stability via additional cw runs while
laser operation is worked.
Regarding fabrication of the new high-voltage stack:
The first ceramic was coated with the high resistance coating
at HiTemp. Unfortunately, the final layer of plating (nickel)
on the metalized ends evaporated and spoiled the coating properties
because of the high firing temperature. Processing a second ceramic
was started by removing the nickel down to the moly-manganese
base metalization and preparing for the high resistance coating.
The original ceramic will have its metallization and coating
ground away and be remetalized and coated again. The process
is being monitored by a Jefferson Lab employee detailed to HiTemp.
The new mid voltage ring for the stack is being polished on two
shifts.
A taper in the bores of the flimsy kovar rings for the new ceramics
prevented complete fit-up on the metalized ends. The rings were
rebored by our shop and sent back to HiTemp.
The rotisserie for ion implantation was pumped down and tested
for rotation and its shipping crate made up. We will have to
mount a more powerful alternate motor to drive it, but in all
other respects, it is ready to ship. The test body made from
the original ceramic material was prepared for the full scale
ion implantation test at Lawrence Berkeley Lab.
We have decided that the anti-field-emission coated cathode support
tube would be installed later, after we try the new stack of ceramics
at the higher voltage gradients. It is more prudent to make changes
"one at a time" and experience shows that we could recover
from a leak in a ceramic if they exhibit the same characteristic
punctures. Polishing has stopped at 9 micron diamond grit on
cathode support tube.
The first anti-field-emission coated sample electrodes were received
from FM Technologies. They will undergo effectiveness tests at
the College of William and Mary next week.
Regarding testing of the injector cryounit:
The cavity quality factor for the second cavity in the unit was
measured to be 5.5 e9 at 4 MV/m. This agrees with measurements
in the Vertical Test Assembly done prior to installation of the
cavities into the cryostat. Today (Friday, 25 Oct) and Monday
we will make measurements at higher gradients. All acceptance
tests should be complete by close of business Tuesday.
Tests were done of the magnetostrictive tuner to generate 1 A
and 5 A direct-current hysteresis loops. We are evaluating the
results.
The static heat load of the cryostat is about 6 W, which concurs
with the design value.
Regarding other ITS progress:
The chopper cavity, which will be needed for measurements of bunch
length aspart of the reconfiguration for 350 keV operation, is
now undergoing rf testing.
Acceptance tests of the ITS BPM were successfully completed.
Accelerator Systems
A simulation of the IRFEL injector with first-light beam was run
this week. It indicates that we can compress 33 pC bunches down
to rms bunch lengths of about 0.5 ps by the time they reach the
entrance of the linac. Based on this finding, we project that,
with the additional bunching provided by the optical chicane preceding
the wiggler, we should be able to get rms bunch lengths of about
0.25 ps at the wiggler if the linac is phased correctly. This
is substantially shorter than the nominal 1 ps requirement for
first light. Our projection still needs to be confirmed via simulations
of the beam all the way to the wiggler, and they are currently
underway.
The saddle coil for the modified prototype dipole magnet was received
and installed. The prototype magnet was then characterized.
The saddle-coil configuration provided a substantial improvement
in the magnitude of the fringe fields, taking them all the way
down to the default levels that had been used in the original
linear-optics design of the transport lattice. It also cut down
how far the fringe fields extend from the magnet aperture, although
they still extend further than we would comfortably like. Therefore
we are going to machine a prototype field clamp and can probably
install it and test the modified magnet by the end of next week.
The Northrop-Grumman magnet designer visited us this week, and
we coordinated the above developments with him. He plans to adjust
his dipole-magnet designs to accommodate the saddle-coil configuration.
We expect to be able to place the optical-chicane dipoles in
procurement in about 3 weeks. The remaining dipoles will follow
after finalizing their respective designs.
The procurement package for the weak quadrupole magnets was reduced
because a decision was made to remove 10 quadrupole magnets from
the nuclear-physics accelerator for use in the IRFEL. It also
was modified to include a 2-month window for ordering the additional
weak quads that would be needed for upgrading the design to include
a second cryomodule. The package was then sent to Procurement
early this week.
Detailed requirements were identified for the beamline leading
into the straight-ahead dump that will be used in generating first
light. Based on these requirements, this beamline was designed,
and the necessary beam-rastering magnets were specified. A similar
design was also completed for the beamline leading into the injector
dump, again in order to specify the necessary beam-rastering magnets.
A similar analysis is underway for the beamline leading to the
energy-recovery dump.
FEL System
Wiggler
STI Optronics has signed off the top-level assembly drawing and
has sent us both the hardcopy and an electronic copy of the drawing.
This will be integrated into the assembly drawings for the wiggler
girder. The conceptual design for the wiggler girder is complete,
and details are now being engineered. A review was held with
V. Christina from Northrop-Grumman to go over the conceptual design
of the vacuum chamber.
Optics
Layouts for the optical transport lines for both the FEL and for
the photoinjector in the new FEL Facility were initiated. Many
of the existing components in the ITS optical transport line can
be reused. Procurements of components for the optical cavity
continue.
Operations/Commissioning
Considerable progress was made in delineating the control interfaces
that are implicit in the design of the IRFEL. This has enabled
us to get better organized with respect to identifying the required
control software and generating the software that isn't already
available.
As mentioned above, detailed requirements were identified for
the beamline leading into the straight-ahead dump that will be
used in generating first light.
Facility
Due to rain last week, plans were shuffled for the concrete pour
that would finalize the ceiling of the enclosure and the truck
ramp base. Wall forms for the shielding level were placed and
most of the forms for the second pour for the entrance labyrinth
were positioned. The pour is now scheduled for next Tuesday,
and it will include many of these areas. The overall schedule
is unaffected.
We started the procurement process for a new drive-laser clean
room for the FEL Facility. It will lead to a schedule improvement
because it will be ready as soon as the ITS is shut down.
We held an internal design review for the high-voltage power supply to be installed in the FEL Facility for powering the gun there. We plan to get a bid package out for the pressure vessel by late November.