MEMORANDUM
To: J. Cook, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IR Demo Project Weekly Report, October 27-31,
1997
Date: October 31, 1997
Management
Dr. Eli Zimet from ONR and Joung Cook from NRL visited the laboratory
on Friday Oct. 31 to review progress on the FEL project and discuss
future interactions with the Navy. The visit was very valuable
in gauging the Navy's interest in both FEL technology and the
use of the FEL User Facility for laser-material studies.
Jefferson Lab's FEL program was a co-sponsor of this week's workshop
on "The Scientific Applications of 4th Generation Light Sources,
which was held at the Advanced Photon Source on Oct. 27-29th.
The IR Demo and its User Facility were prominently mentioned
in overview talks on FEL technology development and in working
groups discussing applications of high power IR and UV light to
materials physics and chemistry. Even though the 4th Generation
Light Source is usually a term reserved for an x-ray source with
a considerably higher brightness (x 10e4) than the present 3rd
generation sources (like APS, ESRF and Spring-8), the workshop
broadened the definition to include the full spectrum from IR
through DUV to x-rays, in view of the fact that a linac-driven
FEL could provide the brightness advantage across this full spectrum.
To reinforce this broader definition of 4th generation sources,
we were able to attract five of the users of the IR Demo to the
workshop to give presentations during the scientific application
working sessions. The final product of the workshop will be a
white paper outlining a research plan for the development of 4th
generation sources and a summary of scientific applications in
materials, chemistry, biology and atomic physics.
Installation Activities
The injection line from photogun assembly to injector dump is
now fully installed and ready for commissioning activities. All
components for the drive laser assembly and drive laser transport
have been completely installed, aligned and tested for operation.
The injection line dump shielding has been put in place.
A corrector magnet in the injection line (which is not needed
for initial commissioning and can be removed and replaced without
interruption of the vacuum) was removed for measurements in the
magnet test area. These measurements will be useful for us to
provide to the vendor responsible for completing the remaining
corrector magnets for the accelerator.
The optical chicane vacuum chambers have been replaced after they
were removed for a minor modification needed for fit-up of BPM
assemblies. Final assembly of the wiggler vacuum chamber within
its supporting frame was completed this week. Assembly of the
clean hoods which will be placed over the optical cavity assemblies
proceeded this week prior to next week's planned installation
of the optical cavities.
Commissioning Activities
We ran beam at 350 kV from the gun through the buncher cavity
to a viewer assembly just upstream of the injector cryounit.
The buncher was operated at its nominal power loading of 2 kW.
The drive laser in its final configuration ran to the required
level of performance in these tests.
RF commissioning of the injector cryounit began this week. The
exit cavity was operated at gradients of approximately 9.5 MV/m
until problems with waveguide guard vacuum faults were noted.
SRF commissioning activities were halted and leak test operations
were begun. On Thursday, leaks were found at the interface seal
for the warm window. The cryounit was then warmed up to allow
the warm window assemblies to be removed and the new seals installed.
We plan to cooldown the cryounit on next Tuesday, which is a
scheduled maintenance day for the CEBAF accelerator. (This minimizes
the effect of any small probability transients that the cool-down
may impart on the 2K cooling system.)