MEMORANDUM


To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report Oct. 28-Nov. 1, 1996

Date: November 1, 1996

Management

SURA held a review of the institutional management of Jefferson Lab on Oct. 28-29. An FEL program overview was presented at the review in addition to "customer" statements by John Albertine from the Navy FEL and Mike Kelley, chair of the LPC.

A technical, cost and schedule progress review of the IR FEL Demo project was held on Oct. 29 by the Navy and DOE.

A meeting was held with Northrop Grumman management on Oct. 31 to discuss continuing technical support the IRFEL Demo project by Northrop Grumman engineering staff. A draft agenda was circulated to the chairman of SURA's Maritime Technical Advisory Committee (MTAC) for the committee's first meeting on Dec. 17-18.

Injector Test Stand

Regarding operation of the 250 keV gun:

The troublesome electro-optic modulator was repaired and reinstalled. Its extinction ratio was remeasured and found to be 2.7e-5. This is sufficiently low and allows experiments to proceed.

The distribution of the laser spot was remeasured with the new modulator and found to be gaussian, as desired, but a drift on a time scale of minutes caused the spot to wander across the copper aperture which is imaged on the cathode. To correct this, two mirror mounts on the optical drive line were replaced. Final measurements of the laser beam spot size and distribution are in progress prior to starting the production runs that will provide publishable transverse-emittance data.

The laser-beam pulse length was optimized using the autocorrelator, resulting in an rms value of 17 ps. This will be used for the experiment.

The dispersion at the harp used for momentum-spread measurements was characterized. All of the components on the experimental beamline are now commissioned.

Three operators from the nuclear-physics machine were trained on the setup of the present machine configuration. We are now running two-shift operations in the ITS.

Regarding fabrication of the new high-voltage stack:

A day-by-day schedule for the high-voltage (HV) stack was compiled. Completion date is projected to be 26 November, provided all processes go well.

The bulk resistivity of the second ceramic insulator of the new batch was measured before coating it. Assuming this difficult measurement was done with sufficient accuracy, we believe the bulk conductivity is large enough to dissipate the buried charge anticipated from the field-emitted electrons. A build-up of these electrons in the ceramic is the suspected cause of the vacuum leaks in the present HV stack. This second ceramic was then coated with the standard spray and fired. The coating's resistivity was measured and found to have a value about 20 times higher than the coatings on the ceramics of the previous batch, a variability that motivates continued work on ion implantation. We anticipate that, though higher than in previous successful ceramics, this value still allows drainage of field-emitted electrons and establishment of the required uniform field gradient. The first ceramic insulator of this batch is being prepared for a spray and firing on Monday, November 4. If this insulator's coating matches the resistivity of the previous one, remaining work at the vendor is to plate the metalized ends of both with nickel, braze on the kovar rings, leak-test it, and ship.

The new mid-voltage ring for the new stack is being polished on two shifts and is now at 600 grit, silicone carbide.

The rotisserie for the alternate ion-implantation charge-bleed treatment is not yet shipped. The contact surface of the ceramic insulator's rolling rings was wearing against the rotisserie rollers. We installed a ball-bearing contact to take thrust loads and coated all contact surfaces with Rulon.

Testing of the anti-field-emission-coated sample electrodes started at the College of William and Mary.

Regarding testing of the injector cryounit:

Cryounit tests are almost done. The performance of the magnetostrictive tuner meets its frequency-range specification. Microphonics data were taken and passed to the RF Modeling Group for interpretation. The initial assessment is that the microphonics are not a problem. Low-gradient unloaded Qs were measured and were favorable. On one of the cavities, the unloaded Q was measured to a cw gradient of 9 MV/m, at which point the rf power available in the Cryomodule Test Facility was exhausted. We are in process of adding to the available power. Plans are to finish all measurements of unloaded Q for both cavities early next week, at which time acceptance tests will be complete.

Regarding other ITS progress:

RF testing of chopper cavity, which will be needed for measurements of bunch length as part of the reconfiguration for 350 keV operation, was completed successfully. The cavity is now in the machine shop to have its solenoid and associated flange removed and replaced with a new flange on which will be mounted a new solenoid. These design changes are part of the reconfiguration of the beamline necessary to permit the longitudinal and transverse 350 keV experiments to be run in parallel.

Accelerator Systems

The prototype dipole magnet with the saddle coil was modified to include a prototype field clamp and then tested. The field clamp was found to be successful in suppressing the extent of the protrusion of the fringe field from the aperture of the magnet. However, it also lowered the strength of the integrated fringe fields below the value assumed in designing the transport lattice. Initial indications are that this has no significant effect on the lattice. In any event, we have decided to include, in the magnet design, provision for mounting field clamps should we later decide to use them. This provides time (if needed) to experiment with field clamps without further delaying procurement.

Software development for "10 MeV" transverse-emittance measurements with the multislit diagnostic is almost complete. Progress has been much more rapid than originally anticipated. Various mechanical parts for this diagnostic are on order. All of the parts should be in hand by mid-December.

An internal review of the design of the vacuum system for the IRFEL was held. It included impedance analyses, vacuum hardware, and vacuum control/interlock electronics. Conclusions of the review panel were that impedance issues are within budget for this machine but that some hardware should be made with less impedance, if easily done, so that an upgrade would also fall comfortably below its impedance budget. There was agreement that the system pumping and design concepts are sound and that ordering standard parts, pumps, valves and bellows could proceed. Principal recommendations were that both the method of interfacing the baked system to the unbaked system and the methods and emphasis on the handling of particulates needs greater attention. Some of this study can take place in the Injector Test Stand. Additional recommendations were given concerning details of the vacuum-system design, to include assorted components and procedures.

FEL Systems

Wiggler

STI Optronics continues to receive parts as the wiggler continues on schedule.

We integrated the STI Optronics top-level drawings into the assembly drawings for the wiggler girder. The design should be mostly done by next week, after which we will be able to order the optical bench. We also plan to order a smaller optical bench for holding the wiggler when it is not on the beamline.

Optics

Procurement of the optical components for the resonator cavity continues. The drawings were modified to include the final adjustments to specifications for vacuum compatibility and machining techniques. One drawing remains to be modified for the inclusion of LVDT position sensors. The others are in preparation for sending out for quotes.

Operations/Commissioning

A proposed procedure for commissioning the injection line of the IRFEL was written.

We held the first meeting of the Diagnostic Review Committee to consider nominal changes to the baseline diagnostics suite that were proposed as a result of further considerations of commissioning procedures, such as that of the injection line. This first trial of our "change-order process" went smoothly.

Preparation of a Users' Manual designed to define the user interactions, facility capability, and instrument availability has begun. This will be a living document that will be continuously updated to include new capabilities and new requirements from the users as they occur. It will incorporate the outputs of the working-group sessions from the last meeting of the Laser Processing Consortium.

Facility

Laying in of the rebar for the final third pour of the ceiling is nearly complete, and construction continues on schedule. It was discovered that the placement of the waveguide penetrations in one zone was off by 9 feet. The contractor intends to fill in that hole and add a new penetration by cutting the first 6" to clear the rebar and then jackhammering a large enough hole that a new properly positioned and sized hole can be cast in the 3-foot slab. A schedule for this activity is being developed. In principle, it does not hold up any other work. A major pour of wall areas and shielding around the entrance labyrinth was completed this week.

Specifications for the new clean room to be installed in the FEL Facility were revised. Although we expect that the new room will cost somewhat more than moving the old one, we believe that it would improve the schedule for moving the injector laser by about 2 months.

We laid out the optical-transport line for the FEL Facility and resolved issues concerning interference with cable trays and the clean hood for the gun.