To: J. Cook, D. Helms, W. Skinner
cc: Division (M7), FEL Coordination Group
From: F. Dylla
Subject: IR Demo Project Weekly Report, October 5-9, 1998
Date: October 9, 1998
Management
This week was spent diagnosing and high voltage conditioning the
photogun. Highlights include: (1) successful high voltage conditioning
of gun to 480kV, however the cathode photo response was minimal
requiring replacement of cathode. (2) numerous interactions
with industry groups.
Three industrial groups visited the laboratory this week to discuss
on-going and new interactions with the FEL project and ARC: (1)
Siemens Automotive (Newport News); (2) Neocera (College Park,
MD) and Advanced Energy Systems (Princeton, NJ). The group from
Siemens is discussing joint ARC/FEL studies on laser surface modifications
and laser micromachining of metals. Neocera is a company involved
in the development of laser pulse deposition systems. Advanced
Energy Systems is a new spin-off from Northrop Grumman that will
continue the former Northrop Grumman collaboration on FEL and
SRF technology development.
F. Dylla met with representatives of the LLNL laser processing
group and the program manager of DARPA's Precision Laser Machining
Consortium at this week's OSA conference in Baltimore. The LLNL
group has recently delivered an ultra short pulse (170 fs), Ti-sapphire
laser machining system to the ORNL Y-12 plant. Because of the
short pulse, reasonable micromachining rates can be achieved with
the system's modest average power (18 watts). The developer of
this system cannot envision this laser technology evolving above
100 watts.
DARPA's 5 years of support of the Precision Laser Machining consortium
comes to an end by next September. To date the prime contractor
TRW has delivered a 500 watt Nd-YAG laser processing system for
industrial tests. The consortium will continue its activities
next year without further DARPA support. According to the DARPA
program manager (L. Durvasula), DARPA will not be funding any
new activities in laser processing. Laser work will concentrate
on detection of chemical and biological agents.
We heard from the UVA chemistry department that their preproposal
for establishing a chemical physics lab at the FEL was approved
by the NSF.
FEL Installation/Maintenance Activities
The totality of the Machine Protection System (MPS) was satisfactorily
tested this week. A formal audit of the MPS is scheduled to be
conducted in parallel with the next high-voltage processing of
the gun.
The alignments of the wiggler and its adjacent quadrupole magnets
were checked. Some adjustments appear to be needed, and they
will be made next week.
The nitrogen line to the gun and its high-voltage-power-supply
tank was modified.
Preventive maintenance was done on the Instrument Air compressor.
Administrative locks and tags were placed on the two large magnet
power supplies while we are down. Covers for their connections
to the large dipole magnets are being designed.
Progress was made in releasing the instrumentation-and-control
documentation. Complete CAD packages for two printed circuit
boards were released, and the boards were ordered. The wiring
diagrams and assembly drawings for five different chassis were
also finished.
FEL Commissioning Activities
Concerning the photocathode gun, last week's helium processing
turned out to have no discernable influence on either the cathode's
photoresponse or the field emission. Consequently this week was
spent doing high-voltage processing, ultimately up to 480 kV,
prior to opening the gun. During the processing, a new site of
field emission was generated, and as it processed (up to 480 kV),
a strong nitrogen component prevailed in the emission. Based
on this observation, a conjecture is that the site may have been
associated with the coating on the stalk.
In view of the ultimately successful outcome of high-voltage processing,
we are in the process of replacing the cathode wafer today, after
which we will do a vacuum bake, heat clean and cesiate the new
cathode, and then bring the gun on-line. Once the bad cathode
is removed, it will be subjected to Auger analysis in the hope
of gaining information about the cause of the gun problems. At
this writing (1115, 9 Oct 98) the estimated date for gun turn-on
is 20 Oct 98. If successful (meaning delivery of 60 pC pulses
at 350 kV), commissioning activities will resume per the plans
already in place.
Regarding lasing, it is not known how much cw power the installed
CaF mirrors can sustain. The power may peak at ~400 W due to
thermal distortion, but the actual limit awaits empirical determination
by way of successful commissioning of the full machine. Presuming
the limit is well below a kilowatt, and recognizing the need to
lase at wavelengths other than 5 µm, it is of interest to
start considering in detail other lasing configurations, and we
have begun to do so.
In this light, we have developed a set of requirements for lasing at 3 µm with sapphire mirrors. The strategy is to follow the philosophy of the "High Power Setup Procedure", i.e., first lase straight ahead, then lase with recirculation using 60 pC bunch charge and the electron-beam quality that has already been achieved. The fundamental implication is that a total beam energy of 47.5±0.5 MeV will be needed at the wiggler. A 4 mA average current (e.g., 60 pC at 75 MHz) should be sufficient to provide 1 kW light near 3 µm. These numbers are to be compared to the original design parameters of 42 MeV with 135 pC bunch charge at 37.4 MHz (5 mA
average current).
A concern about the higher beam energy is whether the acceptance
of the injection/extraction chicanes is sufficient to accommodate
the energy in view of unknowns about the transverse beam halo.
We plan try it, and if problems show up, then perhaps increasing
the energy of the injected beam will help.
Analysis of the sapphire mirrors at China Lake has shown that
the vendor has yet to succeed in applying high-reflectivity coatings
of sufficiently good quality. Their coatings delaminated, and
they contain scratches and pits. Consequently they cannot sustain
the high-average-power light associated with kilowatt lasing.
Last week M. Shinn met with the vendor to discuss the problem
and determine remediary measures. Our intent will be to work
with the vendor to expedite delivery of acceptable optics.
Another potential avenue for kilowatt lasing is to do it at 6
µm with ZnSe optics. We are due imminently to receive a
set of these optics, after which we will mount them and subject
them to acceptance tests. The option for using them, of course,
depends on the outcome of their tests.
In view of all of these considerations, we plan to stay the course
of commissioning at 5 µm with the installed CaF optics and
extract as much power from them as possible. Afterward, at an
opportune time, we will conduct a machine-development program
to explore the feasibility of providing 47.5 MeV beam at high
cw currents. In parallel, work on the sapphire and ZnSe optics
will continue, and we will have some basis for deciding the timing
of their installation.
Duke University continues to plan for irradiation of stents in the straight-ahead machine to be done in conjunction with the next (presently unscheduled) preparation of GEn targets for the Lab's nuclear physics program. The motivation for the irradiated stents is to use them in conjunction with angioplasty. By inserting stents during angioplasty, there is the prospect of substantially increasing the time interval between successive treatments. Duke is fabricating the hardware necessary for installing stents in our straight-ahead dump line.