To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IR Demo Project Weekly Report, October 6-10, 1997

Date: October 10, 1997

Management

A project close-out letter was signed this week by the DOE Site Office and the Navy High Energy Laser Program Office officially recording the end of the IR Demo Construction Project on Sept. 30, 1997. Both offices recognized the project as being "complete for all practical purposes allowing the IR Demo commissioning to proceed on schedule". As part of the close-out report, the summary financial reports were prepared for the final month of the construction project (Sept.).

Four more pre-proposals from LPC collaborators were prepared this week for submission to the DOE-BES Program Office. Expressions of interest on possible FEL user activities received this week from physics and chemistry faculty from Princeton University, Univ. of Wisconsin and Univ. of Maryland.

Preparations continued for our participation in the Oct. 27-29 workshop on "Scientific Applications of 4th Generation Light Sources" at Argonne National Laboratory. Several members of the contingent who have submitted FEL user proposals have volunteered to attend workshop working sessions on materials physics and chemical physics.

Today is the last day of John Albertine's job as Program Manager for the Navy HEL office. Jefferson Lab wishes him well in his new career and thanks him for his leadership of the IR Demo Project.

Installation Activities

A punch list of remaining installation activities was prepared as an appendix for the construction project close out letter. These activities are being performed during the day shift over the next month; second and third shift are being reserved for commissioning activities.

Highlights for installation accomplishments this week include the following: a test fit-up of a reverse-bend dipole (DQ) in the east arc; the recirculation dump was installed; supply and return LCW lines were installed for the east arc region; the girder assembly for the upstream linac cryomodule connection was installed; and several components of the gun HVPS elbow were temporarily removed and modified to improve the stand-off voltage and the SF6 seal integrity.


Commissioning Activities

The gun assembly was operated at 400kV+ for approximately one shift to further evaluate the high voltage conditioning of the assembly. The gun appears to condition to the required voltages for first light rapidly. After this test, the gun HVPS elbow was disassembled for the modifications noted above.

RF check-out of the injector buncher cavity continued. The system achieved 2kW CW and 2.5kW pulsed. On Friday, software for the cryounit and linac software was being checked out prior to anticipated SRF commissioning next week.

Software for auto turn-on of the injector was tested, as was control software for vacuum valve operation.

The drive laser transport optics were aligned and the transport line for the FEL output was leak-checked.