MEMORANDUM

To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report, September 8-12, 1997

Date: September 12, 1997

Management

Installation and commissioning preparations dominate the week's activities. Highlights include installation of the back leg vacuum system, the majority of the arc magnet stands, and three of the optical chicane dipoles. In addition, bakeout of the gun vacuum system began in preparation for the gun re-commissioning.

On Thursday, Sept. 11, Bob Marianelli and Eric Rohlfing from the DOE-BES Program Office, and Dan Lehman from the DOE-ER Construction Management Office visited the laboratory to review the progress on the IR Demo project and discuss future DOE interactions. Eric Rohlfing is reviewing the BES pre-proposals in Chemical Sciences that were submitted to DOE last week. BES management requested the project commissioning schedule and a listing of current and potential university collaborators (particularly at the local universities). We also discussed the options available for extending the IR Demo wavelength range. Of particular interest to BES is the mid-to-far IR range because of the scientific applications noted in the 1994 NAS Study. Note: that the IR Demo with the present 42 MeV linac can deliver long wavelength radiation to approximately 25 mm. A brief white paper on the wavelength upgrade options available to the IR Demo will be prepared for BES.

H. Grunder and F. Dylla made a presentation on Sept. 10 to SURA Executive Committee on the status of FEL program. A related discussion concerned possible involvement of the SURA Materials Council with FEL User Lab proposals and sponsorship of a proposed workkshop on Laser Processing in January 1999.

Preparations were made for next week's SURA/DOE Science and Technology Review. Review team members who will be paying particular attention to the FEL Program presentation are John Galayda (Advanced Photon Source), Erik Johnson (BNL) and Steve Laderman (Hewlett Packard Laboratories).

Financial data was collected this week for preparation of the project monthly report for August.


Accelerator Systems

Regarding the beam-transport system:

After a series of at out-of-plane measurements of the integral field across the 9 cm good field region that validated D. Douglas' assumptions, all eight optical chicane dipoles (DWs) were signed off. Three were installed. The standard DW was held back to perform a representative field map. In addition, measurements were taken using 1006 steel field clamps substituting for the production 1018 clamps. Virtually identical field integrals were observed.

The first DU magnet was measured using the hall probe with continued measurements on it and the first article DV planned for early next week. The remaining seven magnets of this series were shipped from Everson.

The final configuration of the field clamp on the DV dipole at the intersection with the 10 MeV lines (and the configuration of any magnetic shielding) had been left to the magnet measurement phase of the magnet's commissioning. However, our tests indicate this approach is not prudent. Field clamps have proved to be exceptionally influential in maintaining uniform field integrals across the good field regions and cut-and-try modification will not converge on a solution fast enough. We will rather define the configuration using finite element magnet modeling using TOSCA. Tom Schultheiss from Northrop Grumman is consulting next week with Robin Wines, bringing a TOSCA model of the DW dipole that he can morph into the DV style to speed up the analysis.

Assembly of the eight reverse bend dipoles at Everson Electric continued with shipping expected around September 24.

Arrangements with Everson to assemble the 180 Degree Dipoles are nearly complete and the cores and parts were shipped to them from Process Equipment Co. However, gluing the segmented mu metal and brass to these cores will use bolts to provide the flattening force rather than the press used on previous magnets. Everson wants several trials on small prototypes first to prove this different process. The resulting delay may stretch final assembly of a first magnet to end of October. We are proposing to do a trial assembly of the second magnet's parts first with a non glued substitute for the mu metal and brass. The assembly also would prove out the coil placement and all magnet hardware. We would ship it here and install that assembly in late September into the first arc to prove out the stands, vacuum chamber for the complete arc and the diagnostics that mount at the 90 degree point in the magnet. Final assembly of the first magnet would proceed in parallel.

In the quadrupole and sextupole area, winding of coils and manufacture of the cores for the eight Panofsky trim quads continued (with about 60% of the task done) at Magnet Enterprises International (MEI).

In the corrector area, manufacture of the eight coils for the phasing dipoles (DGs) continued at MEI. Mu metal cores as well as the cores for the other reverse bend correctors (DF&DCs) are being fabricated at Magnetic Shield Corp. and fabrication of the 8 coils for the DFs and 8 coils for the DCs was started at a new vendor, Advance Magnet Lab.

Bids for air core corrector half-coil sub-assemblies are due in September 15. In house manufacture of one additional prototype horizontal air core corrector (DB) and two inner vertical correctors (DH) continued. Magnetic measurements of the rough prototype indicated total harmonic content on a 2 inch radius of 2% with a 1% quadrupole dominating. Tests will continue to see if the quadrupole can be nulled out by adjusting the relative placement of the half coils.

All reverse bend chamber bodies are welded and flange welding will start early next week.

There is continued progress in installation, the beam line in the injector dump region is leak tight. Work continues on the line for the recirculation dump. All remaining arc stands were delivered and installed.

Regarding RF systems:

The 225 kV power supply was operated. We conducted a HV test to 20 kV and ran RF from one 50 kW klystron into shorts. At close of business Friday, work was progressing on second unit.

The elbow was affixed to the HV power supply tank for the gun. We ran HV tests in air successfully. We are preparing for 14-15 a psi hydrostatic test early next week.

New software is ready to install for cryomodule control. We are also preparing software changes for controlling the injector (modifications of ITS software).

Regarding instrumentation and control systems:

We began assembling beam viewer camera mounts in tunnel. The beam instrumentation and vacuum cabling to accelerator enclosure was finished. Hewlett Packard workstations and X-Terminals delivered and set-up in building. The MPS design review was held on Friday, Sept. 12. The review committee will provide a report next week. PSS certification for individual components continues. Buffer boards for video multiplexing prototypes are complete and turned over for software testing next week.

FEL Systems

Work continued this week on the drive laser and the optical system. After we made more modifications to the stands we are aligned through the telescope box down to the fourth mirror can. The two mirror cans being built by our Machine Shop were completed today (9/12). They will be cleaned this weekend and installed next week. The drive laser was operated about 30 hrs. this week to continue checking out the new divide-by-40 hardware, and associated electronics. Once again, the phase was controlled very well; the error signal was no more than 0.4 deg. peak-to-peak. Drift was quite low, about +/- 0.1 deg. We also continued testing remote control of other optics equipment, and are resolving the controls problems that have turned up.

Discussions with the two optics companies producing cavity mirrors resulted in plans for them to send their test plates to China Lake for testing. Rocky Mountain Instruments (RMI) sent mirrors to Zygo to check the ROC, the results are ROC = 4.00157m, quite close to the value determined by China Lake. Once China Lake can tell RMI how to modify the test plate to make it correct, they will refigure the optics. The other vendor, Research Electro-Optics (REO) will also send China Lake their test plate, after they remove the AR coating (which was marred by overspray) and repolish and recoat the mirrors. They will also try annealing one mirror to see if some of the compressive stress caused by the coating will be relieved, which will lengthen the ROC. The right angle valve for the upstream optical cavity assembly passed particulate and vacuum tests, it will be installed as soon as personnel are available.

Regarding the wiggler: Checked permeability of vacuum chamber welds. It is <1.05 which is acceptable.

Commissioning/Operations

Uwe Happek visited from the University of Georgia to discuss the design and methodology of the interferometric bunch-length monitor. He brought the first unit with him, and our plan is to acquire and use three of them on the FEL.

Work continued toward specifying the RF phases in the injector. Space-charge forces, because they are nonlinear and dynamic, complicate the task of determining the transfer matrices. Our approach is to determine the matrices for the RF elements numerically and do multiparticle statistical simulations to study the overall system sensitivity to RF phase. Using PARMELA is the most likely avenue.

The photocathode gun is baking in preparation for drawing electrons off the cathode on 23 Sep 97. Numerous activities must be completed prior to then. A partial list of activities follows, and is offered here as an indication of the level of planning required for commissioning a subsystem of the FEL:

Partial List of Items to Complete for Gun Turn-On

Item Person Due

Lock vacuum valve to Quarter closed. K. Jordan 9/8

Provide sketch for LCW manifold T. Siggins 9/8

Install LCW manifold for INJ N. Wilson 9/10

Install Instrument Air for HVPS purge line. J. Parkinson 9/10

Test HVPS at 15 psig with air. J. Fugitt 9/10

Install HVPS Status chassis D. Gelhaar 9/11

PSS Certifications H. Robertson 9/11

a) HVPS J. Fugitt 9/11

b) Laser Shutter K. Jordan 9/11

Fit-up HVPS tank & bellows to Gun J. Fugitt 9/15

Bake Gun & beam line. T. Siggins 9/15

Check fit-up between Gun and HVPS tank. J. Fugitt 9/15

Align Drive Laser M. Shinn 9/16

Align Light Box S. Benson 9/17

Provide Controls for: K. Jordan 9/17

a) HVPS e) Laser pulses

b) Magnet f) Telescope picomotors

c) Viewers g) Operator shutter

d) Valve h) Video & Spiricon

SOP for HVPS J. Fugitt 9/17

PSS Certification for HVPS H. Robertson 9/17

OSP for FEL building R. Legg 9/17

High Voltage process Gun T. Siggins 9/18-22

Generate 1st e-beam from Gun. R. Legg 9/23