MEMORANDUM


To: J. Albertine, D. Helms, W. Skinner

cc: Division (M7), FEL Coordination Group

From: F. Dylla

Subject: IRFEL Weekly Report Sept. 30-Oct. 4, 1996

Date: October 4, 1996


Management

The Omnibus FY97 Spending Bill was signed by President Clinton on Monday, 30 September. It includes $6M for continuation of the Navy's FEL Program.

On Oct. 3 John Albertine and Fred Dylla gave a briefing to Eli Zimet of ONR on the status of the Navy FEL program and discussed possible outyear (97-98) activities with the FY97 funding increment.

We are actively coordinating our schedule for installation activities in the FEL Facility with those of the Nuclear Physics Program to ensure availability of the requisite manpower.

Progress on the construction of the FEL Facility has been rapid, 1-2 weeks ahead of schedule. In effect, this is motivating rapid progress on machine design/procurements/fabrication to keep pace. This circumstance accentuates the need for management to assure product quality, and this need is receiving appropriate emphasis.

Injector Test Stand

We have been pushing toward routine operations of the gun in the ITS. A meeting of ITS principals was held to identify impediments to routine operation as well as to discuss plans to overcome them. The immediate need is for written set-up procedures that can be implemented by a nonspecialist. Deadline for this was set for 8 October.

Injector commissioning was productive this week, progressing to the point that we expect to start taking transverse-emittance data next week. Activities included the following:

1) The photocathode continued to sustain a QE of about 2% without resection.

2) We developed a procedure to center the laser on the cathode using the remote mirror control motors in conjunction with monitoring the electron beam as a diagnostic.

3) We measured the spot size on the cathode for use in the transverse emittance experiments.

4) We solved the noise problem in the harp position readbacks.

5) We operated the injector at >1 mA average current with a charge per bunch of 40 pC, commensurate with what is needed for first light.

6) We operated the electro-optical modulators in the mode needed for the transverse emittance tests, achieving the desired extinction ratio of about 100,000:1.

7) We aligned the drive-laser optical path and connected the remote laser monitoring head on the beamline.

Regarding development of the new HV stack:

1) Contrary to our plans, two metallized ceramics were shipped overland to us last Friday, so we could not personally pick them up and take them to the brazer (Hitemp, in California). Consequently, this delayed the start of Kovar ring brazing. However, the parallel work of getting the Kovar rings annealed and plated was started by shipping the rings to Hitemp. We will use receipt of the ceramics at Jefferson Lab as an opportunity to inspect them here and forego an on-site vendor inspection. Thus, we now plan to go to Hitemp in two weeks, at the end of the brazing cycle, and while there, we will install the rotisserie for ion implantation at Lawrence Berkeley Lab and start the implantation.

2) Tests of the ion-implanted samples with high dose rates yielded good initial results. We started testing for survivability from a 250C bake.

3) The electrodes for testing the coating for the cathode support tube were cleaned and sent to FM Technologies for coating.

4) Polishing of the new cathode support tube is on time, reaching 15 micron diamond grit, and machining of the Mid-Voltage Ring is nearly finished, per schedule.

The cryounit is fabricated and installed in the SRF Test Cave. It is presently at LHe temperature and is vacuum tight. Acceptance testing starts in earnest on Monday, 7 October.

We made progress toward obtaining hardware required to reconfigure the gun's beamline for parallel measurement of the beam's transverse and longitudinal emittance. This includes ordering optical modulators for the drive laser that will increase the ghost-pulse extinction ratio for better sensitivity in the longitudinal-emittance measurement. It also includes completion of the coil for the necessary focusing solenoid, and fabrication of the magnet's core was started at an outside vendor.

Accelerator Systems

There has been considerable and on-going interaction between the beam-transport designer and the magnet engineers toward resolving how best to deal with the fringe fields of the dipole magnets. The present strategy continues to be to use a saddle-coil configuration with field clamps that localize the fringe fields. Preliminary beam-transport analysis indicates that, with this design strategy, the impact on the machine design will be extremely small, perhaps a 2-3 inch displacement of the 180-degree bends. We anticipate timely resolution of this matter.

A detailed set of particle-tracking studies indicates, even under overly pessimistic circumstances, no need for an electron-beam scraper between the cryomodule and the wiggler. Indications are that a scraper placed in the first high-dispersion region of the first recirculation bend will add insurance for low (100-nA-level) beam loss during energy recovery. Additional analysis is slated to quantify this notion.

Held internal review of the multislit diagnostic project. The prognosis is looking good for automated transverse-emittance measurements of the space-charge-dominated 10 MeV beam with one-second updates and with accuracy approaching 10%. The project is on track.

Testing of the beam-position monitors (BPMs) has begun to establish their utility for the IRFEL. The "BPM test stand" is essentially an analog computer, a suite of electronics that replicates the signal that a BPM would see as the electron beam sweeps by it, and it is used to measure the response of the BPM's electronics. This methodology has been benchmarked with the nuclear-physics machine, where it is found to be very accurate, and the methodology was easily modified for application to the IRFEL. Initial tests of the 4-channel BPM electronics for the IRFEL are favorable, as had been anticipated.

A procurement package for the electronics racks and doors needed for the IRFEL was prepared, signed off, and forwarded to our Procurement Office.

FEL Systems

Wiggler

Corrected assembly drawings were received from the vendor and the procurement of components for the wiggler appears to be on track. Using the top level drawings we are now able to initiated design of the vacuum pipe, mounting system, beamline insertable viewers, and support table. That work began this week with conceptualization of the support approach for the beamline. The planned design allows us to use an optical bench girder with no holes which is very cost effective. Work is proceeding on schedule.

Optics

Following the successful review of the resonator system last week, procurement of the resonator components was begun. Orders for the vacuum components, mounts, and stages were initiated. Detailed drawings for fabrication are in check. From earlier diagnostic orders a low level 2 micron camera for viewing the synchrotron light was received. Also received was a highly quantum efficient thermoelectrically cooled line camera with response to 1.8 microns which will be used to align the electron beam in the wiggler. The initial set of components were ordered to perform a thermal distortion measurement of cavity mirrors in their mounts on the bench.

Operations/Commissioning

Tracking analysis to determine need for scrapers was completed, and the requirement has been inserted into the "engineering queue". The vacuum-pipe apertures were verified to be large enough that beam loss is not expected to be a serious problem. Nevertheless, we plan to add a single scraper with adjustable aperture in the first high-dispersion region of the first recirculation bend. Its purpose is two-fold. First, it will suppress beam loss in the presence of unusually high energy spread, as might be generated in experiments involving high-efficiency extraction from the wiggler. Second, it can be used in experiments to study the interplay between beam loss and rf stability. Aside from these benefits, it will provide insurance against uncertainties in the distribution function of the beam at the wiggler exit. Engineering this scraper is nearly identical to engineering the insertable dumps.

Facility

Facility progress continues ahead of schedule. The sixth of seven wall pours was completed this week for the lower level and work continued on framing the ceiling pour. The first of three pours of the three foot thick concrete ceiling slab will commence tomorrow with the west end of the building. The second pour is scheduled for the following Wednesday. The final wall pour is also expected so that the entire lower level will be surrounded. The contractor was awarded the third safety incentive payment in August for having no safety citations during that period. (There were also none in September and the contractor will receive an award for that, too, next month.). Several scheduling issues regarding joint occupancy in January were discussed at the monthly contractor meeting and several approaches were identified which may simplify the initial installation tasks by TJNAF personnel.

A meeting was held with Mike Kelley (DuPont) on Oct. 4 to continue discussions of the fit-up of the polymer processing laboratory.