0. 1 kW vs. Configuring a User Lab: Apparently conflicting mandates
have been passed down to the Team. I and some others regarded our clear
priority to be establishment of kW-level performance, a
commissioning-intensive task. Our I&C team regarded the priority to be
setting up a User Lab and getting its LSS ready. These tasks are not
mutually exclusive; they overlap. Diagnostics experts (including
members of the I&C group) have been "traditionally" assigned to Owl
Shifts for intensive beam diagnostics that feed into machine setup
during Day and Swing Shifts. The group is feeling stressed, and with
their perceived priority combined with my direction, they feel it
impossible to satisfy their requirements. Bohn will discuss the matter
with F. Dylla.
I. Gun Cathode: Today the cathode is putting out 45 pC at most. At
37.4 MHz, we can in principle achieve about 1.6 mA recirculated beam,
whereas to date we have achieved "only" 1 mA cw recirculated beam (at
37.4 MHz while producing >100 W cw laser power as measured upstairs,
meaning about 140 W out of the FEL proper), after which either BLM or rf
trips have been showing up. Consequently 45 pC suffices to enable
continuing the machine setup. L. Merminga is on Day Shift this week;
she will be checking whether rf transients are influencing the machine
setup. But, the cathode is deteriorating. Plans are as follows:
- Recesiate Friday Day Shift, 11 Dec 98, unless it is needed earlier.
If the gun comes up well, resume running Friday Swing Shift. If not,
heat clean over the weekend, do high-voltage processing and another
short heat clean, then remake the cathode -- resume running sometime the
following Tuesday or Wednesday.
- Replace the wafer immediately after Christmas break -- it is due to
be replaced. Downtime will then be 23 Dec 98 through 19 Jan 99, exactly
in phase with the planned downtime of CEBAF, meaning we will not have
conflicts with lack of MCC staffing.
II. Achieving 1 kW: Presently, as mentioned above, we've achieved a
little over 100 W cw laser power measured upstairs in the FEL Optical
Control Room (~140 W downstairs) with about 1 mA cw recirculated beam.
We need another order of magnitude, and we're working on it. The plan
by which we will be proceeding is as follows:
- Achieve 60 pC, 2.2 mA cw recirculated beam in the presence of
moderate lasing; gradually increase the strength of lasing.
- Raise the bunch charge to 80-90 pC; achieve ~3 mA cw recirculated
beam, ultimately with strong lasing.
- Increase the repetition rate to 75 MHz with 60 pC bunch charge to
achieve ~4 mA cw recirculated beam, ultimately with strong lasing.
(Note: This is nontrivial in that the associated beam mode is not
presently configured into the MPS; it had not been part of our initial
planning, and K. Jordan estimates it could not be available prior to
mid-Feb 99.)
- If/when lasing is limited by the present photon optics (we don't
yet know conclusively where the limit is!), then:
- replace the existing downstream mirror with an available,
more highly reflecting silicon mirror; should roughly double the power
ceiling.
- replace the 5 micron optics with the sapphire (3 micron)
mirrors; set up the machine for 48 MeV energy and 3-micron lasing.
(Note: The sapphire mirrors are presently at the vendor after failing
tests at China Lake. After modification is complete, they will be returned
to China Lake for further tests. If they pass, we'll get them from China
Lake. Bottom line -- they probably won't be available for a couple of
months.)